Waste stream forecasting in a site waste management plan
The statutory requirement for site waste management plans went in 2013, but the planning condition did not. A forecast you can report against is what discharges it.
A construction waste forecast is the part of a site waste management plan that a council can actually test, and it is usually the part written last and least. The Site Waste Management Plans Regulations 2008 were revoked in England in 2013, so there is no longer a statutory duty to produce one. What remains is a planning condition, a local policy requirement, or a BREEAM credit, and all three expect a quantified forecast by material stream with a diversion target attached.
The forecast has a second purpose that pays for itself. A plan that predicts 400 tonnes of concrete arising from a demolition, and identifies a crusher hire and a reuse destination on site, turns a disposal cost into a materials saving. That calculation is the reason to do this properly rather than to a template.
What the plan has to forecast
Read the condition wording first, because the required content varies. Most conditions ask for four things.
- Estimated quantities of waste by material stream, in tonnes, with volumes where the material is bulky.
- The proposed management route for each stream: reuse on site, recovery off site, recycling, or disposal.
- A diversion from landfill target, expressed as a percentage by weight.
- Arrangements for recording what actually arises, and for reporting against the forecast.
Where the condition also asks for the waste hierarchy to be applied, say so explicitly and in order: prevention, preparing for reuse, recycling, other recovery, then disposal. The duty to apply the hierarchy sits in the Waste (England and Wales) Regulations 2011, and quoting it costs a sentence.
Distinguish the document from an operational waste strategy for the finished building. A Site Waste Management Plan deals with construction and demolition arisings, while a Waste Management Strategy deals with bin stores, container capacity and collection once the building is occupied. Conditions sometimes conflate them, and a plan that answers the wrong one gets refused.
Estimating quantities by material stream
Build the forecast from the schedule of works rather than from a rate per square metre, and use the rate only as a sense check at the end.
For a demolition, take the areas and thicknesses off the survey drawings and convert with material densities. For new build, take the bills or the outline quantities and apply a wastage allowance to each material. The wastage allowance is where professional judgement earns its place: cut and fill on groundworks, offcuts on timber and plasterboard, overordering on blockwork and packaging on everything delivered.
| Stream | Typical sources | Route to state |
|---|---|---|
| Inert: concrete, brick, block, hardcore | Demolition, groundworks, substructure | Crush and reuse on site as fill or sub-base |
| Excavated soils | Groundworks, foundations, drainage | Reuse on site where suitable, or recovery off site |
| Timber | Formwork, packaging, carpentry offcuts | Segregated recycling |
| Plasterboard | Drylining offcuts | Segregated, because gypsum is excluded from mixed landfill |
| Metals | Structure, services, reinforcement offcuts | Segregated recycling with a rebate |
| Packaging and plastics | Deliveries throughout | Segregated recycling |
| Hazardous: asbestos, paint, oils, contaminated soil | Demolition and refurbishment | Consigned separately under the hazardous waste rules |
State the source of every rate you use. A forecast built from your own completed projects is stronger evidence than a published benchmark, and either is acceptable so long as the basis is named. Figures with no stated basis are the reason these plans get queried.
Asbestos deserves its own line. A refurbishment and demolition survey under the Control of Asbestos Regulations 2012 has to be carried out before work starts, and the results change both the forecast and the programme. Where a survey has not yet been done, say so and flag the quantity as provisional rather than putting in a number.
Setting diversion and reuse targets
Pick a target you can achieve and evidence. A stated diversion figure becomes a condition, and a plan that promises a figure nobody can report against creates an enforcement problem for the developer.
Two separate targets are worth distinguishing. Diversion from landfill by weight, which is heavily influenced by whether inert material is crushed and reused on site, and reuse on site as a proportion of arisings, which is the figure that actually reduces vehicle movements. Reporting both tells a better story than a single headline.
Where the site has an existing building being taken down, a Pre-redevelopment Audit identifies materials and components worth recovering before demolition begins, and its findings feed directly into the reuse target. Doing that audit after the demolition contractor is on site is too late.
Segregation on a constrained site
Segregation is a space problem. On an urban site with no room for six skips, the honest answer is a smaller number of streams on site plus off site sorting at a licensed facility, with recovery rates evidenced by the operator's own data.
Say which arrangement you are proposing and why.
- Full segregation, where space allows: separate containers by stream with clear signage.
- Partial segregation: inert and hazardous separated on site, with a mixed container for the rest sorted off site.
- Sequenced segregation: one or two streams at a time, matched to the trade on site that week, which works well on refurbishments.
Then name the facility and ask the operator for their recovery rate. A recovery rate from the receiving facility, in writing, is what lets you report against a diversion target when the containers left site mixed.
Include the practical items too: container positions on the site plan, wheel washing, road sweeping, and the point where the crusher will sit if inert material is being processed. Those belong in the Construction Management Plan as well, and the two documents should agree.
Duty of care records and carriers
Section 34 of the Environmental Protection Act 1990 imposes the duty of care on anyone who produces, carries or disposes of waste, and the records are the evidence of compliance.
Four record types cover a construction site. Waste transfer notes, or season tickets for repeat movements, describing the waste and its European Waste Catalogue code. Hazardous waste consignment notes for asbestos, paints, oils and contaminated soils. Carrier registration checks for every operator used. And permit or exemption checks for every receiving site.
Assign responsibility for keeping them to a named role on the contractor's team, and say in the plan that copies will be made available to the local planning authority on request. An officer discharging the condition at practical completion will ask for the transfer notes and a reconciliation, and a site that has kept them in a lever arch file rather than a shoebox discharges in days.
Reporting actual against forecast
Set out the reporting arrangement in the plan itself: what is recorded, how often, in what units, and by whom.
A workable arrangement is a monthly log of tonnages by stream, taken from transfer notes and weighbridge tickets, reconciled against the forecast, with a short explanation of any variance above a stated percentage. Explaining variances honestly is better than adjusting the forecast retrospectively, and officers respond well to a plan that says the demolition produced more inert material than expected and more of it was reused.
Keep photographs of the segregation arrangement in use. They answer the question of whether the plan was implemented, which is a different question from whether the targets were met.
Making the plan conditionable
Write the plan so the condition can be discharged from the document itself.
Name the person responsible. Give the forecast in a single table with a stated basis for each rate. State the diversion target and the reuse target separately. Describe the segregation arrangement and the receiving facilities. Set out the records to be kept and the reporting cycle. And provide a short closing statement listing exactly what will be submitted at practical completion.
Then check the plan against the condition clause by clause before submitting it, because the most common reason for a refused discharge is a plan that is perfectly good and answers a slightly different question.
This article is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Are site waste management plans still a legal requirement?
Not in England. The Site Waste Management Plans Regulations 2008 were revoked in 2013. Plans are still required by planning conditions, by local policy, and to satisfy BREEAM credits, and the duty to apply the waste hierarchy under the Waste (England and Wales) Regulations 2011 continues to apply regardless of whether a plan is produced.
How do I estimate construction waste quantities?
Build the forecast from the schedule of works. For demolition, take areas and thicknesses from survey drawings and convert using material densities. For new build, apply a wastage allowance to outline quantities by material. Use a rate per square metre only as a sense check, and always state the source of each rate you rely on.
What diversion from landfill target should I state?
One you can achieve and report against, because the figure becomes a condition. Distinguish diversion from landfill by weight, which is dominated by whether inert material is crushed and reused on site, from reuse on site as a proportion of arisings, which is the figure that actually cuts vehicle movements. Reporting both is more credible than one headline.
What records does the duty of care require on site?
Waste transfer notes or season tickets describing the waste and its catalogue code, hazardous waste consignment notes for asbestos, paints, oils and contaminated soils, carrier registration checks for every operator, and permit or exemption checks for every receiving site. Section 34 of the Environmental Protection Act 1990 imposes the duty on producers, carriers and disposers alike.
How can a mixed skip count towards a diversion target?
By evidencing the receiving facility's recovery rate. Where an urban site has no room for full segregation, separate inert and hazardous material on site and send the remainder for off site sorting at a licensed facility, then obtain that operator's recovery rate in writing. That figure is what allows reporting against the target.