Flood, Drainage and SuDS

Wave overtopping on a tidal frontage and freeboard

7 min readBy PlanScope Editorial Team

On a tidal frontage the design flood level is the still water level plus the wave component. Here is how overtopping discharge is calculated and how freeboard follows from it.

On a tidal frontage the design flood level is not the still water level. It is the still water level plus whatever the waves do on top of it, and freeboard is what you add after both have been quantified. Miss the wave component and a finished floor level that looks 600mm clear of the extreme tide can be wet twice in a winter.

The assessment has two halves. Establish the extreme still water level for the design event, then calculate mean overtopping discharge at the defence crest for the wave condition that coincides with it. Both belong in the Flood Risk Assessment, and on any site of scale the Environment Agency will read that section first.

Still water level against the overtopping component

Extreme still water level combines astronomical tide with surge. For tidal flood risk, the boundary between Flood Zone 3 and Flood Zone 2 sits at a 0.5 per cent annual probability, so the 0.5 per cent event is the usual starting point for the design still water level. Add the sea level rise allowance for the region and the development lifetime from the Environment Agency's climate change allowances, which are published by river basin district and by epoch and are revised periodically.

Wave action sits above that. A wave breaking on a vertical wall at high tide can throw water several metres beyond the crest even when the still water level is below it, and the volume that lands behind the defence is the number that matters for people and property. So the deliverable is a discharge, expressed as litres per second per metre of defence, rather than a level.

Two mistakes recur. Using a mean sea level rise figure from an older allowance table because it was in the previous project file. And applying the fluvial 1 per cent event out of habit on a site whose dominant source is tidal.

Discharge rates and the tolerable limits

Mean overtopping discharge is calculated using the empirical formulae in the EurOtop manual, which is the reference UK and European practice uses for wave overtopping at coastal structures. Tolerable limits differ by receptor and they differ by more than an order of magnitude between them. A pedestrian standing on a promenade, a vehicle on an access road, a building behind a defence and the structural integrity of the defence itself each have their own threshold.

Take those limits from the current edition of the manual rather than from a spreadsheet inherited from a previous job. They have changed between editions, and an objection that your limits are out of date is one you cannot answer at committee.

Peak individual wave volumes deserve separate attention. A frontage can pass the mean discharge test and still be unsafe, because a single large volume arriving in two seconds is what knocks a person over. Where a public route or an escape route sits behind the defence, report both mean discharge and maximum individual volume.

Fetch, wind and the design condition

Offshore wave conditions come from hindcast data or a nearshore transformation model. What the assessment needs is the inshore condition at the toe of the defence, which means taking the offshore significant wave height and period and transforming them across the local bathymetry, accounting for shoaling, refraction and depth-limited breaking.

Fetch matters most on estuarial and sheltered frontages, where the design wave is locally generated by wind rather than swell arriving from deep water. On a narrow estuary the critical direction is often not the prevailing one, because the longest fetch may lie across the channel. Check the fetch in every direction, not just the windward one.

The design condition is a joint probability question. The extreme tide and the extreme wave do not necessarily occur together, so combining the 0.5 per cent tide with the 0.5 per cent wave overstates the event. Use a joint probability approach and state the dependence assumption explicitly, because that assumption is the single most contestable input in the whole calculation.

Crest levels and set-back as alternatives

Raising the crest is the obvious answer and often the worst one. A higher wall reduces overtopping and blocks the sea view that made the site viable, and on a promenade frontage it usually attracts a landscape and townscape objection of its own.

The alternatives are worth modelling before the wall goes up:

  1. Set the buildings back so the overtopping volume dissipates across a defined splash zone.
  2. Change the defence profile, since a sloped or stepped revetment with a recurve at the crest can cut discharge substantially compared with a plain vertical face.
  3. Add roughness, through rock armour or a stepped apron, to dissipate energy before the wave reaches the crest.
  4. Accept a higher discharge and design the receiving surface for it, with falls, drainage and no habitable use at ground level.

Set-back is usually the cheapest and the one planning officers prefer, because it reads as an urban design move rather than a flood defence. It also avoids committing a future authority to maintaining a structure it did not ask for.

Sea level rise over the development lifetime

The allowance you apply depends on the lifetime you claim. Residential development is normally assessed over 100 years, commercial over a shorter period, and the lifetime has to be stated and justified rather than assumed.

This is where a tidal site differs sharply from a fluvial one. Fluvial climate change allowances increase peak flows; sea level rise raises the baseline the waves sit on, which increases overtopping non-linearly. A 300mm rise in still water level against a fixed crest can multiply mean discharge several times over, because the freeboard between crest and water is the dominant term in the overtopping formulae. Model the end-of-lifetime case, not just the present day.

Illustrative example. A 40-unit scheme behind a vertical masonry sea wall passes the overtopping test at present-day levels with the wall crest 1.2m above the design still water level. Apply the sea level rise allowance for the 2120 epoch and the effective freeboard falls, which pushes mean discharge above the tolerable limit for the pedestrian route immediately behind the wall. The scheme was consented with a set-back and a raised terrace rather than a raised wall, and with a condition tying the terrace levels to the modelled case. The figures here are illustrative and are not a substitute for site-specific modelling.

Mitigation at the building rather than the boundary

Where the frontage cannot be changed, the mitigation moves to the buildings. Finished floor levels above the design flood level, with freeboard on top, is the first move. Practice commonly uses 300mm of freeboard for fluvial sites, but on a wave-affected frontage the Environment Agency may ask for more, and the figure should be agreed at pre-application rather than assumed.

Beyond levels, the usual package is no habitable accommodation at ground floor on the seaward side, flood-resistant construction to the exposed elevation, safe access above the design level, and a written flood warning and evacuation plan. Note that safe access is the requirement that most often defeats an otherwise well-designed tidal scheme, because a dry building reached across a flooded road is not a safe development.

Residual risk has to be stated rather than argued away. If the defence fails or is overtopped beyond the design case, say what happens, how deep it gets and how long it lasts.

How the assessment is presented for review

Structure the wave section so a reviewer can reproduce it. State the source of the extreme still water levels, the offshore wave data set and its period of record, the transformation method, the joint probability assumption, the defence geometry with a survey reference, the formulae used and the edition of the manual, and the tolerable limits with their source.

Include the sensitivity runs. A reviewer who can see that your result holds under a more pessimistic dependence assumption will accept the central case. One who is shown a single run will ask for the others anyway, three weeks into determination.

Where the site also needs the Exception Test, the overtopping work carries directly into the safety limb, and the drafting is easier if the two are written together rather than bolted on. The two limbs and the evidence each needs are covered in exception test evidence, and the sequential approach that comes before it in the Sequential Test.

Wave overtopping modelling is specialist coastal engineering work and needs a suitably qualified author. Enter your postcode on PlanScope to see which flood and drainage reports your site is likely to need before you commission it.

This is general guidance rather than legal advice. Check the position with your local planning authority, the Environment Agency or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What annual probability event is used for tidal flood risk?

A 0.5 per cent annual probability is the boundary between Flood Zone 3 and Flood Zone 2 for tidal sources, so the 0.5 per cent extreme still water level is the usual design starting point. Add the sea level rise allowance for the region and the development lifetime. Check the current allowance tables, because they are revised periodically.

How much freeboard is needed on a wave-affected site?

There is no single figure. Practice commonly uses 300mm above the design flood level on fluvial sites, but on a frontage subject to wave overtopping the Environment Agency may expect more, and the design flood level itself has to include the wave component. Agree the figure at pre-application rather than assuming it.

Can I combine the extreme tide with the extreme wave?

Combining the 0.5 per cent tide with the 0.5 per cent wave overstates the event, because the two are not fully dependent. Use a joint probability approach and state the dependence assumption in the report. That assumption is usually the most contestable input in the calculation, so include a sensitivity run alongside the central case.

Is raising the sea wall the best way to control overtopping?

Often not. A higher crest cuts discharge but blocks views, attracts townscape objections and commits someone to maintaining it. Setting buildings back so the overtopping volume dissipates across a defined splash zone, changing the defence profile or adding roughness are frequently cheaper and read better in planning terms.

Who should carry out a wave overtopping assessment?

A coastal engineer or a flood risk consultant with coastal modelling experience. The work involves nearshore wave transformation, joint probability analysis and empirical overtopping formulae, and the Environment Agency reviews it as specialist engineering. A drafted report structure helps, but the numbers need a qualified author.

Sources and further reading

flood riskcoastalwave overtoppingfreeboardclimate change allowancestidal flooding

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS6 min read

Water supply capacity: what a developer must evidence

Four documents carry the water supply case, none of which the applicant can write. Why the enquiry belongs alongside transport and drainage scoping, not at drafting stage.

Read article →
Flood, Drainage and SuDS6 min read

Rainwater harvesting and the drainage credit

Attenuation needs empty volume and a supply tank is designed to be full. How a credit can be earned through a two-zone tank, and why harvesting belongs in the water efficiency case.

Read article →
Flood, Drainage and SuDS7 min read

Who maintains the SuDS after the houses are sold

Adoption, highway transfer or a management company: the route has to be fixed at concept drainage stage, because each one constrains where components can sit.

Read article →
Flood, Drainage and SuDS7 min read

Surface water sewer capacity and the undertaker's position

The right to connect under section 106 of the Water Industry Act 1991 survives, subject to limited refusal grounds. Why the capacity enquiry has to come before the layout is fixed.

Read article →
Flood, Drainage and SuDS7 min read

Floodplain compensation: level for level volume calculations

Compensatory storage has to be replaced within the same elevation band it was lost from, not just in the same total volume. The calculation method, the siting rules and the drawings that get it approved.

Read article →
Flood, Drainage and SuDS6 min read

Property flood resilience works and planning permission

Internal resilience works fall outside the definition of development, and demountable barriers are not building operations. Listed buildings, conservation areas and raised external levels are the exceptions.

Read article →