Transport, Highways and Parking

What Active Travel England looks for in an application

7 min readBy PlanScope Editorial Team

Active Travel England has been a statutory consultee since June 2023. What triggers the consultation, what the assessment scores and how to respond.

Active Travel England became a statutory consultee on planning applications in England on 1 June 2023, and for a scheme that crosses the threshold its response is now part of the decision. The trigger is size: residential development of 150 dwellings or more, 7,500 square metres or more of floorspace, or a site area of 5 hectares or more. Below that, the local highway authority is still the body you are dealing with.

What the new consultee looks at is narrower and more specific than a highways review. It is not interested in junction capacity. It is interested in whether somebody can walk or cycle out of your site to the places they actually need to reach, and whether the design makes that pleasant enough to do twice a day.

When the consultation is triggered

The thresholds sit in the amended Development Management Procedure Order 2015 consultation arrangements and are read the same way as other major development triggers.

Trigger Threshold
Residential units 150 or more
Floorspace, any use 7,500 m² or more
Site area 5 hectares or more

A scheme that meets any one of the three is caught. Outline applications count, which matters because the design detail that Active Travel England cares about is often reserved, and a reserved matters submission that departs from the illustrative layout can attract a fresh objection.

Schemes below the threshold are not outside the policy. Local plan policy, the National Planning Policy Framework (August 2026 edition) and the local highway authority all apply as before, and our note on when a transport assessment is triggered covers the separate thresholds that drive the transport evidence base.

How the assessment is structured

The consultee works from published criteria and scores the scheme rather than writing a free form letter. In practice the response reads as a series of themed findings with a rating, which is useful because it tells you exactly which part of the design failed and by how much.

The themes are consistent across responses. The connections the site makes to the surrounding network. The quality and directness of routes inside the site. Cycle parking, judged on usability rather than count. Crossings and junctions where walking and cycling routes meet vehicles. And the mix of uses and densities that determine whether there is anywhere worth walking to.

Two reference documents sit behind almost every comment. Cycle Infrastructure Design, published as Local Transport Note 1/20, sets the design standards for cycle provision, and Manual for Streets governs residential street layout. If your layout has not been tested against both, the response will say so.

The practical effect is that the assessment is a design review, not a traffic review. That changes who needs to answer it. A transport consultant alone will not fix a layout problem, because the fix is usually in the masterplan.

Connections beyond the red line

This is where most schemes lose marks. A layout can be exemplary inside the boundary and still deliver residents onto a 60 mph rural road with no footway.

The consultee looks at where people are going: the nearest primary school, the nearest food shop, the nearest bus stop or station, the nearest employment. Then it asks whether there is a route to each that a twelve year old or a person using a mobility aid would use. Distance matters less than severance. A 600 metre walk on a continuous footway with a signalised crossing beats a 400 metre walk that ends at an unlit verge.

Delivering off site links is a legal problem as much as a design one. The usual mechanisms are a section 278 agreement with the highway authority for works within the public highway, a section 106 obligation to fund or deliver a link, and a Grampian condition where third party land is involved and delivery cannot be guaranteed. Each takes time. Land assembly for a single footway connection has delayed more schemes than any of the design points below.

Where the site touches an existing right of way, upgrading it can be the cheapest connection available, though the legal route differs from ordinary highway works. And where the connection crosses a trunk road, a different consultee is engaged, as set out in our piece on access to the strategic road network.

Cycle parking judged on quality

Every applicant provides the number of spaces the local standard requires. Very few provide spaces anyone would use.

The criteria that come up repeatedly are practical.

  • Location. Cycle parking has to be at least as convenient as the car parking. A store at the back of a block reached through a fire door and down a ramp will not be used.
  • Access. No steps, no lifts as the only route, no narrow doorways, and doors that a person holding a bicycle can open.
  • Security. Covered, lit, overlooked or access controlled, with stands that support the frame at two points.
  • Spacing. Two tier racks packed to the minimum pitch are counted but not used. Sheffield stands at proper centres are worth more than double the number of wall hooks.
  • Non standard cycles. A proportion of spaces sized for cargo bikes, adapted cycles and trailers, because standard stands exclude a lot of people.
  • Visitor provision. Short stay stands at the entrance, separate from the resident store.

For houses rather than flats, a shed or garage counts only if it is accessible without moving a car and is shown on the plans at a usable size.

Crossings, desire lines and street design

Inside the site, the recurring criticisms are predictable: routes that follow the carriageway rather than the desire line, crossings set back from the junction so that pedestrians walk further, shared use footways where separate provision would fit, and tight forward visibility that pushes cyclists into the middle of the lane on a road designed for 30 mph.

Corner radii are a good proxy for how seriously a layout has been designed. A generous radius lets a car turn at speed across the point where people cross. Tightening it, raising the crossing to footway level and continuing the footway surface across the side road does more for the assessment than any amount of supporting text.

Shared surfaces attract particular scrutiny because they work well at very low traffic volumes and badly above them, which is the point our note on shared surface streets develops.

Lighting is part of this. A route that is direct, overlooked and lit to the relevant standard is used after dark. One that runs behind rear gardens is not, whatever the plan shows.

Responding to an objection

An objection is not fatal and it is not rare. The council must have regard to it, and in practice most case officers will hold the application until it is resolved or will condition the outstanding points.

The response that works is a design change with a drawing. The response that does not is a letter explaining why the existing design is acceptable. Where the point is contested, deal with it in the transport evidence: a Transport Assessment can carry the revised layout, the connection strategy and the delivery mechanism for off site works in one place, and the Travel Plan can secure the measures that depend on occupation rather than construction.

Be realistic about what a travel plan can carry. Measures that rely on behaviour change do not compensate for a missing footway, and a consultee that has flagged severance will say so.

Timing the engagement

The cost of an Active Travel England comment rises sharply with time. At masterplan stage a connection point can be moved for nothing. At reserved matters it costs a redesign of two development parcels and a fresh consultation period.

Three practical steps. First, run the walking and cycling audit before the layout is fixed, not after, and record where the routes to school, shops and public transport actually go. Second, open the off site land negotiations early, because that is the long lead item. Third, where the scheme is phased, show which connections are delivered in which phase, because a link promised in phase four will be challenged.

And keep the illustrative masterplan honest. If the outline layout shows a green link that the reserved matters scheme cannot deliver, the objection arrives late and lands hard.

Enter your postcode on PlanScope to see which reports your site is likely to need.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

When does Active Travel England have to be consulted?

For applications in England meeting any one of three thresholds: 150 dwellings or more, 7,500 square metres or more of floorspace, or a site area of 5 hectares or more. Outline applications count, so a reserved matters layout that departs from the illustrative masterplan can attract a fresh response at a late stage.

Can a council approve a scheme Active Travel England has objected to?

Yes. The consultee response is a material consideration the council must have regard to, not a veto. In practice most case officers will hold the application until the point is resolved or will impose conditions covering the outstanding matters, so an unresolved objection usually costs programme time rather than the permission.

What cycle parking standard is applied?

Numbers come from the local plan or parking standards, but the consultee judges quality against Cycle Infrastructure Design, published as Local Transport Note 1/20. Expect comments on step free access, covered and secure storage, stand spacing, provision for cargo and adapted cycles, and separate short stay visitor stands at the entrance.

Does a travel plan answer an objection about missing footways?

No. Measures that rely on behaviour change do not substitute for physical connections, and a response that has flagged severance will usually say so directly. The travel plan is the right place for monitoring, incentives and occupier measures, while the connection itself needs a design change and a delivery mechanism.

How are off site connections delivered?

Usually through a section 278 agreement with the highway authority for works in the public highway, a section 106 obligation to fund or build a link, or a Grampian condition where third party land is involved. Land assembly is the long lead item, so start those negotiations before the layout is fixed.

Sources and further reading

active travel englandstatutory consulteescycle parkingltn 1/20transport assessmentmajor development

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking7 min read

Mobility hubs and shared transport secured by condition

A condition can require the bays and the power supply. It cannot fund an operator or make a car club viable. How to split the commitment so the scheme survives withdrawal.

Read article →
Transport, Highways and Parking7 min read

Network Rail consultation where a crossing is affected

Where a scheme adds movements across a level crossing, the rail operator's risk assessment governs the outcome rather than highway capacity. What the evidence has to show.

Read article →
Transport, Highways and Parking6 min read

Section 59 claims for extraordinary traffic damage

A section 59 claim arrives after the road has been resurfaced, by which point the only useful evidence is the baseline survey nobody took.

Read article →
Transport, Highways and Parking7 min read

Access onto a single track rural lane

On a single track lane the highway objection is about geometry and conflict rather than flow. What to survey, what to draw and how to make a passing bay offer deliverable.

Read article →
Transport, Highways and Parking7 min read

Committed development and cumulative impact in a TA

Agree the committed development list and the background growth factors with the highway authority before commissioning surveys, because the list usually decides the capacity conclusion.

Read article →
Transport, Highways and Parking7 min read

Pedestrian audits and crossing provision evidence

An audit that produces a located, priced schedule of defects and remedies is evidence. A page of photographs is not. How to choose routes, score them and link findings to mitigation.

Read article →