Viability, Obligations and Commercial

What section 106 can secure that the levy cannot

7 min readBy PlanScope Editorial Team

Section 106 mitigates the impact of one scheme, the levy funds infrastructure generally. How the regulation 122 tests decide which mechanism carries a contribution.

The community infrastructure levy pays for infrastructure in general. A section 106 obligation pays for the specific thing that makes this development acceptable. That single distinction explains almost every argument between an applicant and an authority about which mechanism should carry a contribution, and it is written into regulation 122 of the Community Infrastructure Levy Regulations 2010.

Under regulation 122, a planning obligation may only be taken into account in granting permission if it is necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to it. The levy is subject to none of those tests. It is a charge per square metre set out in an adopted charging schedule, and the authority spends it where it chooses within the rules on infrastructure.

The three tests a planning obligation must meet

The regulation 122 tests are statutory, not policy, so an obligation that fails them cannot lawfully be taken into account. In practice the tests do most of their work at the negotiation stage, when an officer asks for a contribution towards something that the scheme does not make necessary.

Ask three questions in order. Would the development be acceptable without this obligation? If the answer is yes, the obligation fails the first test. Does the need arise from this development rather than from an existing deficiency? If it does not, the second test bites. Is the sum proportionate to the impact the scheme actually causes? A flat rate contribution applied to every application regardless of size will struggle on the third.

Authorities that maintain a tariff style schedule of contributions in a supplementary planning document are not automatically in breach, because the schedule can be a starting point. It becomes a problem when it is applied without a site specific justification.

Site specific mitigation against pooled infrastructure

Some mitigation can only sit in an obligation. A new bus stop outside the site entrance, a footway link across third party land, a financial contribution to a specific junction improvement identified in the transport assessment, off site habitat land for biodiversity net gain, travel plan monitoring, a management company for open space: each of these exists because of this scheme and is tied to it.

Other infrastructure is pooled by nature. Secondary school places across a district, a leisure centre, a strategic road scheme, town centre streets and squares: no single application makes any of them necessary, and the levy exists precisely to collect small amounts from many developments towards them.

The practical consequence is that you should resist a section 106 request for something that appears in the authority's infrastructure funding statement as levy funded, and you should expect to pay through an obligation for anything the officers can point to on your own red line plan.

Affordable housing and why it stays in section 106

Affordable housing is delivered by obligation, not by the levy. The levy is a charge on floorspace that funds infrastructure, and it cannot deliver on-site tenure mix, nomination rights, a mortgagee in possession clause, a cascade for unsold units or the staircasing rules for shared ownership. All of those need a deed.

That is why affordable housing negotiation, viability testing and the drafting of the obligation run together. Where a scheme cannot support policy compliant provision, the argument happens inside the viability assessment and is recorded in the deed through a review mechanism rather than through a reduced levy bill. The levy is not negotiable in that way, though relief and exemptions exist for self-build, social housing and charitable use.

First Homes add their own drafting requirements, including the discount and its perpetuity, as set out in our note on how the First Homes obligation works. The Affordable Housing Statement is the document that explains the offer to the officer before the deed is drafted.

Double charging and how authorities avoid it

An authority cannot use both mechanisms to pay for the same item twice, and the test is whether the obligation is necessary once the levy contribution is taken into account. Since 2019 the control on this is transparency rather than a fixed list: charging authorities publish an infrastructure funding statement each year setting out what the levy has collected, what it has been spent on and what obligations have been secured.

Read the statement before you negotiate. If the project the officer wants a contribution towards appears there as levy funded, say so in writing at the pre-application stage. If it does not appear, an obligation is the right route and arguing about it only delays the decision.

Question Levy Section 106 obligation
Legal basis Community Infrastructure Levy Regulations 2010 Section 106 of the Town and Country Planning Act 1990
Tested against regulation 122 No Yes
Negotiable No, the charging schedule applies Yes, within the three tests
Can secure affordable housing No Yes
Can secure site specific mitigation Not directly Yes
Indexation Applied annually under the regulations As drafted in the deed

The regulation 123 legacy and what replaced it

Until 2019 two controls sat in the regulations. A charging authority published a regulation 123 list of the infrastructure the levy would fund, and obligations could not be pooled from more than five separate planning permissions towards a single project. The 2019 amendment regulations removed both, replacing them with the annual infrastructure funding statement.

The practical effect is that authorities can now pool obligations without the five permission limit, which makes the regulation 122 tests the main discipline on what can be asked for. Older advice that relies on the pooling restriction is out of date, and quoting it in a negotiation marks you out as working from a stale precedent.

Negotiating where the authority asks for both

The usual flashpoint is education or highways. The officer asks for a contribution calculated from a county formula, and the district is a levy charging authority whose funding statement shows levy receipts allocated to school expansion. Both cannot be right for the same places.

Deal with it in this order.

  1. Ask which specific project the contribution funds and where it appears in the funding statement.
  2. Ask for the evidence that the need arises from your development, in the form of pupil yield or trip generation applied to your unit mix.
  3. Offer the mitigation that is site specific, which usually costs less and is always more defensible.
  4. Put the regulation 122 analysis in writing, applied item by item, and ask for a response before the committee report is drafted.
  5. If the request survives all of that, accept it and move on, because an appeal on obligations alone rarely repays the delay.

Small schemes have their own route out. Residential extensions and self-build dwellings can claim levy exemptions, and the traps in those claims are covered in our note on the residential extension exemption. Development appraisals also need the levy treated as a fixed cost rather than a negotiable one, which changes the return assumptions discussed in developer return assumptions in viability.

Recording the split in the heads of terms

Heads of terms should list each obligation, the trigger for payment or delivery, the indexation basis, the review mechanism where one applies, and a sentence explaining why the item meets the regulation 122 tests. Adding that sentence forces the discipline early and gives the officer the wording for the committee report.

Note that the Levelling-up and Regeneration Act 2023 contains powers for a replacement infrastructure levy, and implementation has moved more than once, so check the current position before advising a client on a scheme with a long programme.

PlanScope drafts the planning statement and the affordable housing statement that set out the obligations case, and flags where figures are missing. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. The deed itself is legal drafting and belongs with a solicitor.

This is general guidance, not legal advice. Check the position with your local planning authority and your legal adviser before relying on it. Enter your postcode on PlanScope to see which supporting documents your scheme is likely to need.

Frequently asked questions

What are the regulation 122 tests?

A planning obligation can only be taken into account in granting permission if it is necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind. The tests are set out in regulation 122 of the Community Infrastructure Levy Regulations 2010 and apply to every obligation.

Can the community infrastructure levy pay for affordable housing?

No. The levy funds infrastructure and cannot deliver tenure mix, nomination rights, cascade provisions or review mechanisms, all of which need a deed. Affordable housing is secured by a section 106 agreement or unilateral undertaking, with viability evidence supporting any departure from the policy requirement.

Is the pooling restriction on obligations still in force?

No. The restriction on pooling contributions from more than five planning permissions towards one project was removed by amendment regulations in 2019, along with regulation 123 lists. Charging authorities now publish an annual infrastructure funding statement instead, and the regulation 122 tests remain the main control.

How do I check whether a contribution would be double charging?

Read the authority's infrastructure funding statement, which sets out what levy receipts have funded and what obligations have been secured. If the project behind the requested contribution is already shown as levy funded, raise it in writing at pre-application stage and ask for the regulation 122 justification item by item.

Can the levy amount be negotiated?

Not in the way an obligation can. The levy is calculated from the adopted charging schedule and indexed under the regulations, so it behaves as a fixed cost in an appraisal. Relief and exemptions exist for self-build housing, residential extensions, social housing and charitable use, each with strict procedural requirements.

Sources and further reading

section 106community infrastructure levyplanning obligationsaffordable housingviability

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial8 min read

Marriage value and site assembly in a viability appraisal

Assembly costs are real, but most of them do not reduce what a scheme can contribute. Where acquisition costs, ransom premiums and created marriage value each belong in the appraisal.

Read article →
Viability, Obligations and Commercial7 min read

Varying a planning obligation after five years

After the five year relevant period, a statutory application under section 106A replaces negotiation, and a refusal can be appealed under section 106B. What the authority can decide and what it cannot.

Read article →
Viability, Obligations and Commercial7 min read

Social infrastructure contributions and how they are justified

Contribution requests are built from a yield factor, a capacity claim and a published cost. The arithmetic is usually right, so the argument belongs on the capacity evidence and the statutory tests.

Read article →
Viability, Obligations and Commercial7 min read

Pooling restrictions and clawback in planning obligations

Regulation 123 and the five obligation pooling cap went in September 2019. What remains is the statutory test in regulation 122, the infrastructure funding statement, and careful drafting against duplication.

Read article →
Viability, Obligations and Commercial8 min read

Indexation of section 106 contributions and which index applies

The index family and the base date decide how far an indexed contribution moves. Name the series exactly, set the base date to the prices the figure is expressed in, and recalculate every demand.

Read article →
Viability, Obligations and Commercial8 min read

Phasing a scheme to manage section 106 triggers

Phasing moves when obligations fall due rather than how much they total. Define phases by land parcel, build in a revised phasing plan mechanism, and tie affordable delivery to occupation within each phase.

Read article →