What to submit with a Class MA prior approval application

7 min readBy PlanScope Editorial Team

Prior approval under Class MA is deliberately narrow. Applications fail on an unaddressed prescribed matter or on thin evidence of the two-year Class E use, not on design.

A prior approval application under Class MA is narrow by design. The authority may only consider the matters the Order prescribes, so the Class MA prior approval submission checklist is short, and the applications that fail usually fail because one prescribed matter was left unaddressed rather than because the scheme was poor. Get the eligibility conditions and the prescribed matters covered and the 56-day clock works in your favour.

Read the current text of Class MA before you start. Part 3 of Schedule 2 to the GPDO 2015 has been amended repeatedly, and summaries written a few years ago are out of date.

Eligibility before anything else

Class MA permits a change of use from Class E, the commercial, business and service class, to Class C3 dwellinghouses. The eligibility conditions sit in the Class itself and they are absolute: fail one and the Class is simply unavailable.

The building must have been in a Class E use, or a use falling within Class E, for a continuous period of at least two years before the date of the application. That requirement remains, and evidencing it is the single most common stumbling block.

The Class is also unavailable where the building is listed or within the curtilage of a listed building, is a scheduled monument, sits on land within a site of special scientific interest, is in a safety hazard area or a military explosives storage area, or where the land is in agricultural use. An Article 4 direction can remove the Class for a defined area, and many authorities have made them for town centres.

Two conditions that applied when Class MA was introduced, a 1,500 square metre floorspace limit and a three-month vacancy requirement, were removed by amendment in 2024. Confirm the current position against the Order on legislation.gov.uk rather than against any secondary source, including this one.

Evidencing the previous use

The authority needs to be satisfied, on evidence, that the two-year Class E use test is met. There is no prescribed form of proof, so assemble a bundle:

  • Business rates records for the unit covering the whole period, showing the description and the ratepayer.
  • Leases or licences with their terms and dates, and any assignment.
  • Utility bills or service contracts in the occupier's name.
  • Dated photographs of the unit in use, and signage.
  • Company accounts or VAT registration showing trading from the address.
  • A statutory declaration from the owner or former occupier where documentary evidence has gaps.

Gaps matter more than volume. A six-month hole in the middle of the period invites the argument that the use was not continuous, so address any gap directly with an explanation rather than hoping it passes unnoticed.

Where the building was in mixed use, be precise about which parts were in Class E and for how long, because the Class applies to the building or part of it.

The prescribed matters the authority considers

The Order lists what prior approval covers, and nothing else is a ground for refusal. The list runs to transport impacts and safe site access, contamination risks, flooding risks, impacts of noise from commercial premises on the intended occupiers, the effect on intended occupiers where only part of a building changes use, the loss of a ground floor use in a conservation area, the provision of adequate natural light in all habitable rooms, and the sustainability of an area that is important for industry, storage, distribution or waste management.

Address each one explicitly, under its own heading, even where the answer is short. An officer working through a statutory list with a deadline is looking for the heading.

Prescribed matter What to supply
Transport and access Existing access arrangement, parking position, refuse and servicing
Contamination Desk study, and intrusive work where the history warrants it
Flooding Flood zone, finished floor levels, access and egress
Commercial noise Survey of the actual noise climate and the mitigation designed in
Part change of use How the remaining commercial use and the dwellings coexist
Conservation area ground floor The frontage effect of losing the commercial unit
Natural light Window positions and sizes for every habitable room
Industrial area sustainability Whether the area is designated and how the use fits

Flooding, contamination and noise information

These three carry the most refusals, and each has a sensible proportionate answer.

On flooding, check the flood map for planning and state the zone. In Flood Zone 2 or 3 a Flood Risk Assessment is expected, addressing finished floor levels, safe access and egress and residual risk. Converting ground-floor commercial space to dwellings in a flood zone is the hardest version of a Class MA application, and sometimes the honest answer is to keep the ground floor commercial.

On contamination, a desk study covering the site history is usually enough for an upper-floor office conversion. Where there is an industrial history, former fuel storage or made ground, a Land Contamination Assessment with intrusive investigation will be expected, and that work has to be done by a suitably qualified person.

On noise, the prescribed matter is the effect of commercial noise on the future residents, which is the agent of change principle in statutory form. A Noise Impact Assessment measuring the actual environment, including any plant, servicing and late-night activity nearby, and specifying glazing and ventilation to achieve internal levels, is what satisfies it. Generic assertions do not.

Natural light to habitable rooms

Adequate natural light in all habitable rooms is a hard requirement, and it is the matter that most often defeats deep-plan office floorplates. Bathrooms, hallways and kitchens that form part of a larger room are not habitable rooms for this purpose, but bedrooms and living spaces are.

Supply room-by-room plans showing each habitable room with its window, the window dimensions, the room depth and the orientation. Where a room is deep or has a single window, a daylight calculation is worth doing rather than waiting to be asked, and the choice of baseline and method matters as much as the result, as set out in the mirror image baseline in a daylight assessment.

Rooms with no window at all will not pass. Rooflights, light wells and internal courtyards can work, but they need to be shown and dimensioned.

Drawings, conditions and space standards

Submit existing and proposed floor plans at a sensible scale, existing and proposed elevations where any external change is proposed, a site location plan with the red line, and a unit schedule with areas.

Development under Class MA carries a condition requiring the dwellings to comply with the nationally described space standard, so put the areas and the room dimensions on the schedule and show compliance. Bin and cycle storage, while not a prescribed matter in its own right, will come up through transport and servicing, and the arithmetic should match the approach in waste storage calculations for a waste management strategy.

Timescales and non-determination

The procedure in paragraph W of Part 3 gives the authority 56 days from a valid application to determine it, including any consultation. If the authority does not notify a decision within that period, the development may proceed subject to the conditions in the Class, which is the deemed approval route.

Do not rely on it casually. Deemed approval only follows a valid application, and validity disputes are where it unravels. Pay the fee, supply the prescribed information, and keep the submission receipt and the correspondence.

Once prior approval is granted, the development has to be completed within three years. Where the scheme needs external alterations beyond what the Class permits, those need separate permission, and it is usually cleaner to run the two applications together.

Draft the supporting statements for a Class MA submission in minutes, then check the wider document set against all 66 report types.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. A lawful development certificate is the only formal way to confirm that works or a use are lawful. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What does the two-year use test require?

The building must have been in a Class E use for a continuous period of at least two years before the date of the application. There is no prescribed form of evidence, so assemble business rates records, leases, utility accounts, dated photographs and company records, and address any gap in the period directly rather than leaving it to be noticed.

Is there still a floorspace limit for Class MA?

The 1,500 square metre limit that applied when Class MA was introduced, and the three-month vacancy requirement, were removed by amendment in 2024. Part 3 of the GPDO has been amended repeatedly, so confirm the current wording of Class MA on legislation.gov.uk before relying on any summary of it.

Can the council refuse on grounds outside the prescribed matters?

No. Prior approval is limited to the matters the Order lists, which include transport and access, contamination, flooding, commercial noise affecting future occupiers, natural light to habitable rooms and the sustainability of designated industrial areas. Design, density and amenity standards beyond those matters are not grounds for refusal under the Class.

What happens if the council does not decide in 56 days?

Paragraph W of Part 3 provides that the development may proceed subject to the conditions in the Class where the authority has not notified a decision within 56 days of a valid application. Deemed approval depends on validity, so pay the fee, supply the prescribed information and keep the submission receipt and correspondence.

Do space standards apply to a Class MA conversion?

Yes. Development permitted by Class MA carries a condition requiring the new dwellings to comply with the nationally described space standard. Put the unit areas and room dimensions on a schedule with the drawings and show compliance, rather than leaving the officer to scale it off the plans.

Sources and further reading

class maprior approvalpermitted developmentchange of usechecklists

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →