A worked biodiversity net gain calculation on a small site

6 min readBy PlanScope Editorial Team

An illustrative walkthrough of the statutory biodiversity metric on a 0.2 hectare plot, from baseline habitat parcels to the 10 per cent uplift and the gain plan.

A small residential plot rarely gives you neat numbers. The statutory biodiversity metric wants each habitat parcel measured in hectares, put in a distinctiveness band and given a condition score, and the arithmetic that follows decides whether your scheme clears the 10 per cent requirement or lands a fraction short. This is an illustrative biodiversity net gain small site worked example for a plot of roughly 0.2 hectares with a pair of new dwellings on it, using the published small sites metric method. The numbers below are illustrative. They are here to show where the units come from, not to be copied into your own gain plan.

Where the 10 per cent obligation comes from

Schedule 7A to the Town and Country Planning Act 1990, inserted by the Environment Act 2021, attaches a biodiversity gain condition to most planning permissions in England. Post-development biodiversity value has to exceed the pre-development value of the onsite habitat by at least 10 per cent, and the gain must be secured for at least 30 years. The regime applied to major development from 12 February 2024 and to small sites from 2 April 2024.

Several exemptions matter at this scale. Development that affects less than 25 m2 of onsite habitat and less than 5 m of linear habitat falls under the de minimis threshold. Householder applications are out. So is self-build and custom housebuilding of no more than nine dwellings on a site no larger than 0.5 hectares, provided the other conditions in the regulations are met. If you are relying on an exemption, say which one and why in the application, because a validation officer will look for it. The wider mechanics are set out in our explainer on the statutory framework behind mandatory net gain.

Drawing the baseline parcels

Start with a plan, not a spreadsheet. Walk the site, mark every distinct habitat and measure it. Our illustrative plot divides into three parcels: 0.11 hectares of modified grassland (a mown lawn and a rough back corner), 0.06 hectares of developed land and sealed surface (the existing bungalow footprint, a concrete drive and a patio), and 0.03 hectares of a second modified grassland parcel in noticeably better condition at the rear boundary. A 22 m native hedgerow runs along one side.

Two things trip people up here. Hedgerows, watercourses and area habitats are scored in separate modules of the metric, and units cannot be traded between them. A 10 per cent gain in area units does nothing for a hedgerow shortfall. And the baseline is the habitat as it exists, unless the land was cleared after 30 January 2020 without permission, in which case the metric asks you to assess the habitat as it was before clearance.

Condition assessment and who can do it

Each area parcel needs a condition assessment against the criteria in the metric's own habitat condition sheets. Modified grassland, for instance, is assessed on sward height variation, the proportion of wildflower cover, bare ground and the presence of undesirable species. Get the condition wrong and every number downstream is wrong.

The Environment Act 2021 regime expects the statutory metric to be completed by a competent person, and the biodiversity gain plan has to be approved by the local planning authority. For most small sites that means an ecologist who can defend the condition calls. A Biodiversity Net Gain Assessment drafted from site information is a starting point for that professional, not a replacement for the site visit.

An illustrative baseline figure

Area habitat units in the metric are the product of four things: area in hectares, the distinctiveness score of the habitat type, the condition score and the strategic significance multiplier. Distinctiveness runs in bands from very low through low, medium and high to very high, scored 0, 2, 4, 6 and 8. Condition runs from poor at 1 through moderate at 2 to good at 3, with half steps between.

Parcel Area (ha) Distinctiveness Condition Baseline units
Modified grassland, poor 0.11 Low (2) Poor (1) 0.22
Modified grassland, moderate 0.03 Low (2) Moderate (2) 0.12
Developed land, sealed surface 0.06 Very low (0) n/a 0.00

That gives a baseline of 0.34 area habitat units, assuming strategic significance of 1.0 because neither parcel sits in an area identified in the local nature recovery strategy. The 10 per cent target is therefore 0.374 units. Small numbers, and that is the point: on a plot this size, a single parcel moved one condition step changes the answer.

The hedgerow sits in its own column and needs its own 10 per cent uplift, calculated from length in kilometres rather than area.

The post-development side of the sheet

Proposed habitats are scored the same way, then discounted twice. The metric applies a time-to-target-condition multiplier, because a created meadow is not a meadow on the day of handover, and a difficulty multiplier reflecting how reliably that habitat can be created or enhanced. Both are built into the published spreadsheet. Do not attempt them by hand, and do not quote a multiplier from an older metric version.

Trading rules bite hardest on small sites. Habitat of medium distinctiveness or above must be replaced with the same habitat type, or something of higher distinctiveness, at the same or better condition. Losing a patch of priority habitat and offering amenity grassland in exchange does not work, whatever the unit total says. Our illustrative scheme keeps the better grassland parcel, converts 0.04 hectares of former sealed surface into a species-rich lawn managed on a two-cut regime, plants 14 m of new native hedgerow and retains the existing hedge with a 1 m protected root zone. Retained habitat carries forward at its existing value, so retention buys units at the lowest cost on the sheet.

When onsite gain falls short

Most small urban plots cannot reach the target on site, because the developable footprint eats the only habitat there is. The statutory hierarchy then applies: avoid losses first, then deliver gains on site, then off site, and only then buy statutory biodiversity credits from the government scheme as a last resort. Credits are priced to be unattractive by design and the price schedule is published, so check the current figures before you build them into an appraisal.

Off-site units bring a spatial risk multiplier that reduces their value the further they sit from the development, and they need registering on the biodiversity gain sites register with a 30-year legal agreement behind them. The practical consequences of that choice are set out in our note on trading down and the off-site sections of a gain plan. Budget the time as well as the money. Finding a habitat bank with the right habitat type in the right catchment has delayed more than a few small schemes.

Recording the result

The metric output goes into the application as evidence, usually alongside a short ecology statement explaining the condition calls and the management regime. But the biodiversity gain plan itself is a post-permission document, submitted for approval before development can lawfully begin, and it has to show the pre-development value, the post-development value, the percentage change and how the gain will be maintained. Our guide to the gain plan as a post-permission document sets out what goes in it.

Keep the metric file, the condition sheets, the habitat plan and the photographs together from day one. When a case officer queries a condition score eight months later, the site as it was has usually gone under a slab.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required, and the statutory metric must be completed by a competent person.

Frequently asked questions

Do I need biodiversity net gain for a single new house?

Usually yes, unless an exemption applies. A single dwelling is small site development rather than a householder application, so the biodiversity gain condition normally attaches to the permission. The de minimis exemption only helps if the works affect less than 25 square metres of onsite habitat and less than 5 metres of linear habitat, which rules out most greenfield plots.

Can I complete the small sites metric myself?

The metric is a published spreadsheet anyone can download, but the Environment Act 2021 regime expects a competent person to complete it, and habitat condition assessment is the part that needs training. Most local planning authorities will query a metric with no named author and no site visit record behind the condition scores.

What happens if my site cannot reach 10 per cent on site?

You work down the statutory hierarchy. Avoid habitat loss where you can, deliver what gain the layout allows on site, then secure off-site units registered on the biodiversity gain sites register with a 30 year agreement. Statutory biodiversity credits sold by government are the last resort and are deliberately priced above market units.

Does retaining existing habitat count towards the gain?

Retained habitat carries its existing value into the post-development total, so keeping a hedge or a decent grassland margin protects units you would otherwise have to recreate. It does not by itself produce a gain, because the same value appears on both sides of the calculation. Improving the condition of retained habitat is what generates units.

When is the biodiversity gain plan submitted?

After permission and before development begins. The plan needs local planning authority approval, and starting work without that approval breaches the biodiversity gain condition. Build a realistic gap into the programme between the decision notice and the intended start on site, because approval is not instant and officers often ask for revisions.

Sources and further reading

biodiversity net gainbng metricsmall sitesecologyenvironment act 2021self build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Templates, Checklists and Examples

View all →
Templates, Checklists and Examples7 min read

Checklist for responding to planning objections

An applicant's response to objections is a sorting exercise first. Answer the material points with dimensioned evidence, acknowledge private law issues in one neutral sentence, and offer conditions where you cannot prove a point.

Read article →
Templates, Checklists and Examples6 min read

Checklist for handover of planning documents at completion

The planning file handed over at completion is what a buyer's solicitor asks for years later. Here is the index, and the records that are hardest to recreate.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a tree works application under a TPO

TPO applications are free and decided in eight weeks, but vague descriptions get them refused. Here is the evidence that gets consent granted as proposed.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a demolition prior notification submission

A demolition prior notification is narrow by design. The authority can consider only the method of demolition and the proposed restoration of the site.

Read article →
Templates, Checklists and Examples7 min read

Checklist for a larger home extension prior approval

A single storey rear extension deeper than 3m on a semi, or 4m on a detached house, needs prior approval under Class A. Here are the limits, the information to supply and how the neighbour consultation timetable works.

Read article →
Templates, Checklists and Examples7 min read

Checklist for responding to an invalid application notice

Until an application is validated there is no determination clock. Here is how to sort each item on an invalidity notice, decline requests that are not on the published local list, and protect the validation date.

Read article →