Planning Process

Appealing against a planning condition on its own

6 min readBy PlanScope Editorial Team

You can appeal a condition alone, but the inspector redetermines the application and can refuse the permission. Section 73 keeps the original permission alive.

You can appeal against a condition on a planning permission without appealing the permission itself, under section 78 of the Town and Country Planning Act 1990. The catch is the one most architects are never warned about: on that appeal the inspector redetermines the application, and section 79 allows the decision to be reversed or varied whether or not the appeal relates to that part. So an appeal aimed at one condition can end with the permission refused. That risk is why most condition disputes are run as a section 73 application instead.

Both routes work. They have different consequences for the permission you already hold, and choosing between them is the actual decision.

The right to appeal a condition

Section 78 gives a right of appeal against a decision to grant permission subject to conditions. The appeal is made to the Secretary of State and dealt with by the Planning Inspectorate, normally by written representations for a case of this kind.

The grounds are substantive rather than procedural. You are arguing that the condition should not have been imposed, or should be worded differently, measured against the six tests in the Planning Practice Guidance on the use of planning conditions: necessary, relevant to planning, relevant to the development permitted, enforceable, precise, and reasonable in all other respects.

One point to check first. Where a condition is one that must be satisfied before work starts, section 100ZA of the 1990 Act requires the applicant's written agreement before the authority imposes it, subject to the prescribed procedure. If that agreement was never sought, you have an argument about the condition that does not depend on the six tests at all.

Risk that the whole permission is reconsidered

The inspector is not confined to the condition. The appeal puts the application back before a decision maker who deals with it as if it had been made in the first instance, and the powers in section 79 are wide.

In practice inspectors do not go looking for reasons to refuse a permission the authority granted. But the risk is real where the permission is finely balanced, where the development plan has changed since the grant, where a new constraint has arrived such as mandatory biodiversity net gain, or where a consultee has changed position.

Three situations where the risk is high enough to rule out an appeal:

  • The permission was granted against an officer recommendation for refusal
  • The development plan or national policy has moved since the decision
  • The condition under challenge is the thing that made the scheme acceptable

That last one is the trap. Appealing the condition that resolved the harm invites the inspector to conclude that without it the development is unacceptable.

Section 73 as the alternative route

A section 73 application asks for permission to develop without complying with a condition previously imposed. The authority can grant permission subject to different conditions, or refuse, and a refusal carries its own right of appeal.

The important feature is that a section 73 grant is a new permission. The original permission remains in existence, so a refusal leaves you where you started rather than with nothing.

Section 78 appeal Section 73 application
Who decides first Planning Inspectorate The local planning authority
Original permission at risk Yes No
Typical timescale Months Eight weeks, then appeal if refused
Fee Appeal fees where applicable Application fee, lower than a full application
Can change the description of development No No, though limited variation powers were added by the Levelling-up and Regeneration Act 2023
Result Decision replaces the original A new, separate permission

Two consequences of a section 73 grant catch people out. The new permission does not automatically carry the planning obligations attached to the original, so a deed of variation or a new agreement may be needed, and varying a section 106 agreement after permission covers how that works. And a section 73 permission is a new chargeable development for levy purposes, which needs checking before it is submitted rather than afterwards.

Section 73 also cannot be used to extend the time limit for implementation. That restriction is express.

Deadlines and which clock applies

Get this right because the deadline is jurisdictional. A section 78 appeal against conditions must be made within six months of the date of the decision notice, reduced to twelve weeks for householder and minor commercial appeals.

The six months runs from the date on the notice, not from the date you received it or the date the condition became a problem. Where a condition only reveals itself as unworkable during detailed design, the appeal window may already have closed, and section 73 becomes the only route.

A separate and much shorter clock applies to any legal challenge. Judicial review of a planning decision must be brought promptly and within six weeks, so if the argument is that the condition is unlawful rather than unreasonable, take advice immediately.

Evidence that a condition fails the tests

Appeals and section 73 applications turn on the same evidence, so the work is not wasted whichever route you choose.

  1. Quote the condition in full and identify which of the six tests it fails
  2. Show what the condition requires in practice, with the drawing or the cost of compliance
  3. Show that the harm the condition addresses either does not arise or is dealt with another way
  4. Where another regime already controls the matter, identify it, because a condition duplicating Building Regulations or an environmental permit is unnecessary
  5. Offer alternative wording, because a decision maker presented with a workable alternative is more likely to vary than to delete
  6. Deal with the reason the authority gave, not the reason you assume it had

Point five does most of the work. An appeal or application that asks for deletion and nothing else forces a binary answer, while one that offers precise alternative wording gives the decision maker a route to yes. The planning statement supporting a section 73 application should contain that wording as a tracked change against the original condition.

Costs where a condition was unreasonable

Costs are available at appeal where a party has behaved unreasonably, and the published guidance on appeals sets out the categories. Imposing a condition that plainly fails the tests, or refusing to vary one in the face of clear evidence, can fall within them.

Build the record. Write to the authority before appealing, setting out the condition, the test it fails and the alternative wording, and ask it to vary the condition under section 73 or confirm it will not. A documented refusal to engage is the evidence a costs application needs. The same correspondence often resolves the matter without any application at all, which is the better outcome.

Choosing between the two routes

Section 73 is the default. It protects the original permission, costs less, goes to the authority first and produces a decision in weeks rather than months.

Appeal under section 78 where the authority has made its position clear and will not shift, where the permission is secure enough that reconsideration carries little risk, and where you want an inspector rather than the same officer to decide. Appeal also where the condition makes the scheme undeliverable and a section 73 refusal would simply add eight weeks before the appeal you were always going to bring.

And where the authority has gone silent on a section 73 application, the non-determination options apply instead, which our guide to appealing non-determination sets out.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can an appeal against a condition lose me the permission?

Yes. Section 79 allows the decision to be reversed or varied whether or not the appeal relates to that part, so the inspector redetermines the application. The risk is highest where the permission was granted against an officer recommendation, where policy has moved since the grant, or where the condition is what made the scheme acceptable.

What is the deadline for appealing a condition?

Six months from the date of the decision notice, reduced to twelve weeks for householder and minor commercial appeals. The clock runs from the date on the notice rather than from receipt, so a condition that only proves unworkable during detailed design may already be out of time for an appeal.

Why is a section 73 application usually the better route?

Because it does not put the original permission at risk. A section 73 grant is a new, separate permission and the original stays in existence, so a refusal leaves you where you started. It also goes to the authority first, costs less and is determined in weeks rather than months.

What should I watch for after a section 73 grant?

Two things. The planning obligations attached to the original permission do not automatically carry across, so a deed of variation or a new agreement may be needed. And a section 73 permission is a new chargeable development for levy purposes, which should be checked before the application is submitted.

Does the applicant have to agree to a pre-start condition?

Section 100ZA of the Town and Country Planning Act 1990 requires the applicant's written agreement before a condition requiring something to be done before development starts is imposed, subject to the prescribed procedure. If that agreement was never sought, you have an argument that does not depend on the six policy tests.

Sources and further reading

planning conditionsappealssection 73section 78planning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Process

View all →
Planning Process7 min read

Varying a permission for development already begun

Section 73B of the Town and Country Planning Act 1990 allows a permission to be varied where the effect is not substantially different, including for works already carried out. How the test works, and how to choose between the routes.

Read article →
Planning Process7 min read

Planning history searches before you buy a site

The standard search misses more planning risk than it finds. Here is what to check on the register, and what to ask before you exchange.

Read article →
Planning Process6 min read

Accompanied and unaccompanied inspector site visits

The inspector will visit your site before deciding the appeal. Knowing whether it is accompanied, and what you are allowed to say, changes how you prepare.

Read article →
Planning Process6 min read

The appeal questionnaire and what the council must supply

The council's appeal questionnaire arrives within days of the start date and carries the officer report, policy extracts and consultation responses. Read it before you draft a word.

Read article →
Planning Process6 min read

What stops the eight week clock on an application

The determination period runs from the day after a valid application is received. Consultee silence and amended drawings do not pause it; only a written extension does.

Read article →
Planning Process7 min read

Writing a consultation response an officer can use

Objections that cite a policy number and show evidence get addressed in the officer's report. Objections that express concern get summarised in a sentence.

Read article →