Planning Process

Varying a permission for development already begun

7 min readBy PlanScope Editorial Team

Section 73B of the Town and Country Planning Act 1990 allows a permission to be varied where the effect is not substantially different, including for works already carried out. How the test works, and how to choose between the routes.

A section 73B application is the route Parliament created for a change that is too large for a non-material amendment and too small to justify starting again, including a change to development that has already been built. It was inserted into the Town and Country Planning Act 1990 by section 110 of the Levelling-up and Regeneration Act 2023. The gate is a single test. The local planning authority has to be satisfied that the effect of the permission as varied would not be substantially different from the effect of the existing permission.

Before you programme an application around it, check whether the section has been brought into force and whether the fee and procedure regulations that go with it have been made. As at October 2026 the safest assumption on any live scheme is that you verify the position on legislation.gov.uk and with the case officer rather than relying on a secondary account of it.

What the section provides for

Three features set it apart from the older routes. It can alter the description of development. It can alter, remove or add conditions and other operative parts of the permission. And it is available where the works have already been carried out, which the older routes handle badly.

That combination matters more on site than it reads on the page. A housebuilder who has set a terrace 600mm further back than the approved layout, or lifted a ridge by 300mm to deal with ground conditions, has until now had three unattractive choices: a non-material amendment under section 96A that the officer may refuse because the change is not non-material, a section 73 application that cannot touch the description of development, or a retrospective application under section 73A that reopens the permission in full.

The new route is aimed squarely at that gap.

The test the authority applies

The authority may grant the varied permission only if it is satisfied that its effect will not be substantially different from the effect of the existing permission. Two points follow for anyone drafting the submission.

First, the comparison is between permissions, not between the scheme and the development plan as a whole. The existing permission is the baseline and the question is what changes about its effects. Height, massing, overlooking, parking, drainage discharge, trip generation, hours of use: each needs a before and after position.

Second, "substantially different" is a judgement, so the application has to do the work of showing why the difference is modest. Reciting that the change is small will not carry it. A short comparison schedule, drawing by drawing, with the quantified difference against each approved drawing number, is worth more than several pages of narrative. Where the difference is nil, say so and show the drawing reference.

Keep the policy argument proportionate. If the varied scheme engages a policy the original did not, for example because floorspace crosses a parking standard threshold, that is the point at which the effect starts to look substantially different and the route starts to look wrong.

How it differs from section 73 and section 96A

The three routes are not interchangeable, and choosing the wrong one costs weeks.

Route What it can change Development already built
Section 96A Non-material amendments, including conditions, but not the description of development Treated cautiously by most authorities
Section 73 Conditions only, and nothing that conflicts with the description of development Only while the permission is extant
Section 73B Conditions, operative parts and the description of development, subject to the effects test Expressly contemplated
Section 73A Anything, because it is a fresh permission for works already done Its purpose

The constraint on section 73 comes from the Court of Appeal decision in Finney v Welsh Ministers in 2019, which confirmed that a condition cannot be varied in a way that contradicts the operative description of what was permitted. That is why a scheme described as "erection of 14 dwellings" cannot become 15 by varying a plans condition. Section 73 also cannot be used to extend the life of a permission, and section 73(5) says so. Read the equivalent provisions in section 73B before you assume the position is different there.

Section 96A has one practical advantage worth keeping in mind. It is quick, usually determined inside 28 days, and it carries no publicity requirement. It also carries no right of appeal if the authority refuses, which is the trade-off.

Development already carried out

Where the works are built, the sequence of events changes the risk. A section 73A application invites the authority to assess the development as it stands against current policy, with the original permission reduced to background. On a scheme consented under an earlier version of the development plan, or before mandatory biodiversity net gain applied, that reopening is the real exposure rather than the amendment itself.

A variation route that keeps the original permission alive and asks only about the difference in effect protects that position. It does not cure an enforcement risk on its own. Until the varied permission is granted, the building sits outside what was authorised, and the authority's enforcement powers are unaffected by the existence of a pending application.

Two practical steps reduce the exposure. Tell the case officer before submission, in writing, what has changed and why. And keep the as-built survey evidence, because the comparison schedule stands or falls on measured dimensions rather than on contractor assurances.

Where the project needs a supporting narrative setting out the policy position on the change, a focused Planning Statement addressed to the difference in effect is more use than a general one that restates the original case.

Whether the route is in force, and what to check

A provision on the statute book is not a provision in force. Section 110 of the 2023 Act depends on regulations bringing it into force, and the route also needs an application form, a publicity requirement and a fee before an authority can accept it. Check three things before you rely on it: the in-force position for section 110 on legislation.gov.uk, the current fee schedule, and whether the authority's own validation list refers to the route at all.

If any of those is missing, the honest answer to a client is that the application must take one of the existing routes. That is less satisfying than describing the new one, and it is what keeps a programme intact.

Choosing between the routes on a live scheme

Work through it in this order.

  1. Define the change in measured terms against the approved drawing numbers, including what has already been built.
  2. Ask whether the change conflicts with the description of development. If it does, section 73 is closed to you.
  3. Ask whether the change is capable of being called non-material. If the officer agrees in pre-application correspondence, section 96A is the fastest route and the least costly.
  4. If the change is material but the effects are close to the original, test whether the section 73B route is available and what the fee would be.
  5. If none of that works, budget for a fresh application and the current policy requirements that come with it, including biodiversity net gain where it applies.

Obligations are a separate exercise. A varied permission does not automatically carry the original section 106 agreement with it, so the deed needs checking and often a supplemental agreement, which is covered in our note on varying a section 106 agreement after permission. Fees also move, and some changes attract reductions worth claiming, which we set out in the guide to planning fee exemptions and reductions.

An illustrative example: a consented scheme of nine houses where the plot 4 garage was built 1.2m wider to suit a retaining wall. The description says "erection of 9 dwellings with associated garages", so section 73 is available for the plans condition only if the wider garage does not conflict with that description. The officer's view on overlooking and on the parking layout decides whether a non-material amendment is realistic. The comparison schedule, one line per drawing, is what settles it either way.

Enter your postcode on PlanScope to see which supporting reports a variation application is likely to need before you commit to a route.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is a section 73B application?

It is an application to vary an existing planning permission under section 73B of the Town and Country Planning Act 1990, inserted by section 110 of the Levelling-up and Regeneration Act 2023. Unlike section 73 it can alter the description of development and can cover works already carried out, provided the authority is satisfied the effect of the varied permission would not be substantially different from the original.

Can I use section 73 if the building has already been put up?

Only while the permission remains extant and only for conditions. Section 73 cannot vary a condition in a way that conflicts with the description of development, which the Court of Appeal confirmed in Finney v Welsh Ministers. Where the built form departs from the description itself, the alternatives are a non-material amendment, a variation under section 73B once it is in force, or a retrospective application.

How does the substantially different effects test work?

The authority compares the effect of the permission as varied against the effect of the existing permission, rather than reassessing the scheme from scratch. The applicant has to evidence the difference, topic by topic, covering matters such as height, overlooking, parking, drainage and trip generation. A comparison schedule set against each approved drawing number carries far more weight than narrative assertion.

Is a non-material amendment quicker?

Usually, yes. A section 96A application is normally determined within 28 days and needs no publicity. The trade-off is that there is no right of appeal if the authority refuses, and officers will decline it where they consider the change material. Securing an officer view in pre-application correspondence before you submit saves a wasted fee.

Does a varied permission keep the original section 106 agreement?

Not automatically. A deed is tied to the permission it was completed in connection with, so a new or varied permission often needs a supplemental agreement or a deed of variation binding the obligations to it. Check the drafting of the original agreement early, because the legal work frequently takes longer than the planning decision itself.

Is section 73B available yet?

It depends on regulations bringing section 110 of the Levelling-up and Regeneration Act 2023 into force, and on the fee and procedure rules that support it, so the position must be verified rather than assumed. Check the in-force status on legislation.gov.uk, the current fee schedule, and whether your authority's validation list recognises the route before you rely on it.

Sources and further reading

section 73bsection 73varying permissionplanning conditionslevelling-up actplanning process

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Process

View all →
Planning Process7 min read

Planning history searches before you buy a site

The standard search misses more planning risk than it finds. Here is what to check on the register, and what to ask before you exchange.

Read article →
Planning Process6 min read

Accompanied and unaccompanied inspector site visits

The inspector will visit your site before deciding the appeal. Knowing whether it is accompanied, and what you are allowed to say, changes how you prepare.

Read article →
Planning Process6 min read

The appeal questionnaire and what the council must supply

The council's appeal questionnaire arrives within days of the start date and carries the officer report, policy extracts and consultation responses. Read it before you draft a word.

Read article →
Planning Process6 min read

What stops the eight week clock on an application

The determination period runs from the day after a valid application is received. Consultee silence and amended drawings do not pause it; only a written extension does.

Read article →
Planning Process7 min read

Writing a consultation response an officer can use

Objections that cite a policy number and show evidence get addressed in the officer's report. Objections that express concern get summarised in a sentence.

Read article →
Planning Process6 min read

The repeat application fee exemption and its conditions

One further application after a refusal can be free of charge. The conditions are strict on timing, applicant identity and how much the scheme may change.

Read article →