Fire, Structural and Basements

Article 9A and the fire statement on the application form

7 min readBy PlanScope Editorial Team

Article 9A makes a fire statement a condition of a valid application for relevant high-rise residential buildings. The form is prescribed, the consultee is the Building Safety Regulator, and validation fails without it.

Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015 requires an application for planning permission to be accompanied by a fire statement where the development involves a relevant building. A relevant building, broadly, is one containing two or more dwellings or educational accommodation that meets the height condition of 18 metres or more, or seven or more storeys. The statement must be on the form published by the Secretary of State, or one substantially to the like effect. Miss it and the application is not valid, which is a programme problem rather than a drafting one.

The requirement has applied since 1 August 2021 and it introduced the first of the three Building Safety Act gateways into the planning system. The Health and Safety Executive, through the Building Safety Regulator, became a statutory consultee on those applications at the same time.

Where the requirement sits in the procedure order

Article 9A was inserted into the 2015 Order by amendment. Two elements matter to a consultant. The first is the definition of a relevant building, which combines a use test and a height condition, and which catches both new buildings and development of an existing relevant building. The second is that the article requires the statement to accompany the application rather than to be produced later, which puts it firmly in the validation stage.

Sitting alongside it is the consultation direction: the Health and Safety Executive must be consulted on applications for relevant buildings, and the standard consultee response period under the Order applies. That is the mechanism usually called Planning Gateway One.

The height condition is measured in the way the Building Safety Act framework measures it, so a scheme sitting close to 18 metres needs the measurement basis stated explicitly on the drawings rather than inferred from a storey count. The seven-storey limb catches buildings that fall under 18 metres with generous floor-to-floor heights, and it is the one most often overlooked on schemes at the margin.

The published form and its sections

The form is prescriptive, which is a help rather than a hindrance. It works through the fire safety principles behind the design and then through the specific matters a planning decision can affect.

In practice the substantive sections cover the fire safety design principles adopted, the site layout and how it relates to surrounding development, emergency vehicle access and the hardstanding provided for firefighting appliances, water supplies for firefighting, the means of escape and the evacuation strategy, and the location of the building relative to other structures. Each answer is expected to connect to something on the submitted drawings.

The commonest weakness is an answer that describes intent without showing provision. Stating that emergency vehicle access will be provided in accordance with the relevant guidance is worth very little if the site plan shows no appliance route within the required distance of the dry riser inlet. Where the answer depends on a drawing, name the drawing and its revision in the form.

A Fire Statement drafted this way, keyed to the drawing set, is much easier for the Regulator to comment on and much harder for an objector to pick apart.

Who is competent to complete it

There is no statutory requirement for a named professional designation on the form. There is a clear practical expectation, in the national guidance and in how the Regulator responds, that the person completing it holds the fire engineering competence the building demands. For a relevant building at this height, that normally means a fire engineer.

This is a report type where a competent professional is legally expected rather than optional, and a drafted document is a starting point for that professional, not a substitute for them. PlanScope can produce an AI-assisted draft structured to the form's sections, with missing facts flagged rather than invented, and a suitably qualified fire engineer then has to take ownership of the content. The professional directory is the route to arranging that review.

An architect completing the form alone, on a building of this scale, is taking on a risk that the practice's insurance may not cover. That point is worth making to a client early rather than after the Regulator's response arrives.

Validation consequences of omitting it

Because Article 9A requires the statement to accompany the application, an application for a relevant building without one is liable to be returned as invalid. The consequences are mechanical and they are all bad for the programme.

  1. The determination period does not start, so the eight or thirteen week clock has not begun.
  2. The fee may be returned, and the application has to be resubmitted rather than corrected in place.
  3. The statutory consultation with the Health and Safety Executive cannot be triggered, so the Gateway One response is delayed by the full resubmission period.
  4. Any planning committee slot held for the application is lost, and committee cycles are monthly in most authorities.

A related and more awkward failure is the statement that is submitted but is substantially incomplete. Some authorities validate it and let the Regulator raise the gaps, others refuse to validate. Either way the time cost lands on the applicant. Building the Article 9A check into your own pre-submission checklist, alongside the local validation list, is the simple fix.

Illustrative example. A 21 metre residential block of 68 flats is submitted in early January without a fire statement, on the assumption that fire safety is a Building Regulations matter. The authority returns it as invalid. Resubmission in February means the Gateway One consultation runs through March, and the committee date moves from March to May. Nothing about the scheme changed. The dates here are illustrative, but the shape of the delay is typical.

How it differs from a fire safety strategy

These two documents are confused constantly, and the distinction is worth stating plainly.

Fire statement (Article 9A) Fire safety strategy
Regime Planning, DMPO 2015 Article 9A Building Regulations, Gateway Two
Trigger Relevant building at application stage Higher-risk building before construction
Form Prescribed form published by the Secretary of State Report to BS 9991 or BS 9999 principles
Audience Local planning authority and the Building Safety Regulator Building Safety Regulator as building control
Scope Matters a planning decision can influence Full fire engineering design

The fire statement deals with what planning can control: layout, access, water supply, the relationship to neighbouring buildings, the broad evacuation approach. A Fire Safety Strategy deals with the engineered design in detail, and it comes later. Answering the Article 9A form with the contents of a strategy is not wrong, but it is expensive and it commits the design earlier than it needs to be committed.

Where the construction system itself is the fire issue, for instance a mass timber frame, the two documents start to overlap and the sequencing needs thought, which our note on mass timber frames at planning stage covers.

Amendments and resubmission

If the scheme changes after submission in a way that affects the matters on the form, the form should be updated and reissued to the authority so the Regulator can comment on what is actually being determined. Height changes, changes to the appliance route, changes to core arrangement and changes to the building's relationship with adjoining structures all qualify.

For a later section 73 application varying conditions, or a section 96A non-material amendment, the question is whether the amended proposal itself involves a relevant building and engages Article 9A. Treat that as a live question rather than assuming the original statement carries over, and ask the case officer in writing. Roof-level changes are a frequent culprit here, since adding plant or arrays alters access and, occasionally, the height measurement, as our note on roof level plant and photovoltaics discusses.

Conditions that follow approval

Where the Regulator's response raises matters that are not fully resolved, authorities commonly condition them: the firefighting access arrangements to be provided in accordance with an approved plan, the water supply provision to be agreed, or the evacuation lift and firefighting shaft locations to be retained as approved.

Read those conditions carefully against the Building Regulations programme, because a condition triggered before works start, requiring further fire information, can collide with a Gateway Two submission that is already in progress. Negotiating that trigger back to above-ground works is usually possible and usually worth the effort.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required, and this is general guidance rather than legal advice: check the current requirements with your local planning authority before relying on it.

Frequently asked questions

Which buildings need a fire statement under Article 9A?

Broadly, buildings containing two or more dwellings or educational accommodation that meet the height condition of 18 metres or more, or seven or more storeys. The requirement covers both new relevant buildings and development of an existing one. Because the storey limb can catch buildings under 18 metres, state the measurement basis on the drawings where a scheme sits near the threshold.

Can an architect complete the fire statement?

There is no prescribed designation on the form, but the national guidance expects the author to hold competence proportionate to the building, which for a relevant building normally means a fire engineer. Practices should also check their professional indemnity position before signing. A drafted document structured to the form is a useful starting point for that engineer rather than a replacement.

What happens if the fire statement is left out?

The application is liable to be returned as invalid, because Article 9A requires the statement to accompany it. The determination period never starts, the statutory consultation with the Building Safety Regulator is not triggered, and the scheme loses its place in the committee cycle. Resubmission rather than correction in place is usually required.

Is the fire statement the same as a fire safety strategy?

No. The fire statement is a planning document on a prescribed form, dealing with matters a planning decision can influence such as layout, appliance access and water supplies. A fire safety strategy is a Building Regulations document prepared to BS 9991 or BS 9999 principles, submitted later at Gateway Two, and covering the engineered fire design in full.

Does a section 73 application need a new fire statement?

It depends on whether the amended proposal itself involves a relevant building and so engages Article 9A. Do not assume the original statement carries across, particularly where the change affects height, core arrangement, roof-level plant or emergency vehicle access. Confirm the position with the case officer in writing before submitting the variation.

Sources and further reading

fire statementarticle 9admpogateway onevalidationbuilding safety

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements7 min read

Plant screens, enclosures and separation distances for substations

There is no single separation standard for a substation. Operator access rules, BS 4142 noise assessment and street frontage design all pull on the same position, and all three belong on the first layout.

Read article →
Fire, Structural and Basements8 min read

Shoring and temporary works during demolition

Planning does not approve temporary works, but propping footprint, highway occupation and party wall stability all constrain the permanent scheme. Resolve them at design stage, not after permission.

Read article →
Fire, Structural and Basements8 min read

Excavating a swimming pool in a garden

Class E of the GPDO covers a swimming pool in a domestic garden, but the enclosure, the plant room, twenty lorries of spoil and the backwash discharge are where schemes come unstuck.

Read article →
Fire, Structural and Basements7 min read

Rooftop plant and the capacity of an existing roof

An existing roof usually has very little spare capacity, and the reserve it appears to have is often in the slab rather than in the beams carrying it.

Read article →
Fire, Structural and Basements7 min read

Building beside railway infrastructure: asset protection

The council decides the application. The infrastructure manager decides whether your piling rig, your crane and your drainage are acceptable next to a live railway.

Read article →
Fire, Structural and Basements7 min read

Transfer structures over a commercial ground floor

The transfer zone sits between the commercial ceiling and the first residential floor, and it is additive. Developers usually discover that after the massing is fixed.

Read article →