A basement below the level of the public sewer needs a sump, a pump and protection against surcharge. What Approved Document H expects, and what the council and the sewerage undertaker each want to see.

A basement floor usually sits below the level of the public sewer, so waste water cannot run out by gravity. It has to be lifted. That means a sump, a pump and a rising main, plus protection against the sewer backing up into your new room when the network is full. Councils and building control both look at this, and a submission that says nothing about it invites a condition or a request for more information at validation.

Why a basement cannot always drain by gravity

Gravity drainage needs a fall from the appliance to the sewer connection. Where a new shower, WC or utility sink sits a metre or two below the invert of the sewer in the street, there is no fall to work with.

The second problem is surcharge. When a combined sewer fills during heavy rain, the water level in it can rise above the level of your basement floor. A gravity connection from a basement is then an open route for that water to travel the wrong way. Approved Document H to the Building Regulations deals with both issues together, and its expectation is straightforward: where a basement drain could be affected by surcharge, protect it.

Approved Document H distinguishes between a basement with a single appliance and one containing habitable rooms. A single appliance can sometimes be protected by an anti-flooding valve alone. Habitable accommodation is expected to be served by a pumped installation, because the consequence of a failure is people and possessions rather than a utility sink.

Pump, sump and rising main arrangements

The standard arrangement is a sealed sump set into the basement floor, a submersible macerating or free-flow pump, and a small-bore rising main that discharges above the surcharge level into a gravity manhole outside.

Three details decide whether the installation works for twenty years or twenty months:

  1. Sump volume. Approved Document H expects enough storage to hold a day's inflow if the pump stops, so that a power cut on a Friday night does not put foul water on the floor.
  2. Discharge point. The rising main should loop above the likely surcharge level before it falls into the gravity system, so the sewer cannot push back up the pipe.
  3. Pipe route. Keep the rising main accessible, with rodding access at changes of direction, and avoid burying a joint under a finished floor.

Pumping installations for waste water are covered by BS EN 12056-4, which sets out sizing and layout for drainage inside buildings. Ask your installer to say in writing which standard the unit is certified to, because that sentence is what building control wants to see.

Non return protection against sewer surcharge

An anti-flooding valve is a mechanical device that closes when flow tries to reverse. Devices for buildings are covered by BS EN 13564, which classifies them by type and by the appliances they may serve.

A valve is not a substitute for a pump in a habitable basement, and it is not maintenance-free. Grit and wipes are the usual reason a valve fails to seat, and a valve that has failed open gives no protection while looking perfectly normal from above. Fit it where it can be opened and cleaned without lifting a finished floor, and write the inspection interval into the drainage drawing.

Where the basement has both foul and surface water to deal with, keep them separate all the way to the boundary. A lightwell gully connected into the foul pump sump will fill it during a storm and trip the high-level alarm at the worst moment.

Power supply and failure resilience

Every pumped basement drainage system fails at some point. The question the design has to answer is what happens on that day.

A high-level alarm, audible inside the house rather than in the basement, is the minimum. Duty and standby pumps on alternating control are the normal answer for a basement with a bathroom, because a single pump gives you no margin. Where the basement contains a bedroom, consider a battery-backed alarm and a clearly labelled isolator, and make sure the circuit is not on the same RCD as the garden sockets.

None of this needs planning permission, and all of it belongs in the drainage statement you submit with an application. It also belongs in the homeowner file you hand over at the end of the job.

Undertaker agreement for the connection

Two separate permissions from the sewerage undertaker are commonly involved, and they are often confused.

The right to connect to a public sewer comes from section 106 of the Water Industry Act 1991, exercised by giving notice to the undertaker. The undertaker can refuse or set conditions where the connection would be prejudicial to its system, and a pumped discharge into a sewer already at capacity is precisely the case it will look at.

Separately, if your basement or its drainage runs within three metres of a public sewer, you need a build over or build near agreement. That is a different application, with its own form and its own timescale, and it is usually the item that delays a basement project. Apply early. Private sewers transferred to the undertakers in October 2011, so a pipe you believe is private may not be.

Maintenance obligations and who carries them

A pumping station serving one house stays private. The homeowner maintains it, pays for it and lives with it, and a buyer's surveyor will ask about it.

A pumping station serving several dwellings can sometimes be adopted by the undertaker under section 104 of the Water Industry Act 1991, but only where it is designed and built to the undertaker's current construction standards and the paperwork is in place before the pipes are covered. Retro-fitting an adoption is expensive and often impossible.

For a single-house basement, put a one-page maintenance schedule in the handover pack: pump type, valve type, service interval, alarm test method, and the name of the standard the installation was certified to. It costs nothing at the time and it answers a conveyancing enquiry years later. Our note on cellar conversion or new basement excavation covers where the planning line falls between the two, which affects whether any of this appears on a planning drawing at all.

What the submission should state

For a householder application involving a basement, the drainage information the council expects is short but specific. Set out the floor level of the new accommodation relative to the sewer, the pumped arrangement in outline, the non-return protection, and the point of discharge.

Where the property is in Flood Zone 2 or 3, or on a site of one hectare or more, a Flood Risk Assessment will be needed, and the Planning Practice Guidance on flood risk treats below-ground sleeping accommodation as a particular concern. The policy position on that is set out in our piece on sleeping accommodation below ground.

In much of London a Basement Impact Assessment is a local validation requirement, covering groundwater, structure and drainage together. Check the council's published validation list before you draw anything. And remember that basement works sometimes fall within permitted development and sometimes do not, depending on excavation, lightwells and external alterations, so a Lawful Development Certificate is the only formal way to confirm that what you propose is lawful.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This article is general guidance, not legal advice; check the position with your local planning authority, your building control body and the sewerage undertaker before relying on it.

Enter your postcode on PlanScope to see which reports a basement project at your address is likely to need.

Frequently asked questions

Does a basement conversion need planning permission for drainage?

Drainage itself is a building control matter rather than a planning one. Planning permission may still be needed for the basement works, depending on excavation, lightwells and external alterations, and many London boroughs require a Basement Impact Assessment as a local validation item. A Lawful Development Certificate is the only formal way to confirm the works are lawful.

Is an anti-flooding valve enough on its own?

Approved Document H allows a valve alone to protect a basement served by a single appliance. Where the basement contains habitable rooms, a pumped installation is expected instead, because the consequences of a reverse flow are much greater. Valves also need cleaning, since grit and wipes stop them seating, so fit one where it can be reached without lifting a finished floor.

How big should the sump be?

Approved Document H expects enough storage to hold roughly a day's inflow so that a pump failure or power cut does not put foul water on the basement floor. The sizing depends on the appliances served, so it is a calculation rather than a standard product choice. Ask the installer which standard the unit is certified to and record it on the drainage drawing.

Do I need permission from the water company?

Two things are often needed. The right to connect to a public sewer comes from section 106 of the Water Industry Act 1991 by notice to the undertaker, which can set conditions where its system is already under pressure. Separately, building within three metres of a public sewer needs a build over or build near agreement, which is a different application with its own timescale.

Who maintains a basement pumping station?

A station serving one house stays private, so the homeowner maintains and replaces it. A station serving several dwellings can sometimes be adopted under section 104 of the Water Industry Act 1991, but only if it is built to the undertaker's current construction standards with the paperwork agreed before the pipework is covered over.

Sources and further reading

basementdrainagebuilding regulationsflood riskhouseholder applicationsewer connection

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements7 min read

Plant screens, enclosures and separation distances for substations

There is no single separation standard for a substation. Operator access rules, BS 4142 noise assessment and street frontage design all pull on the same position, and all three belong on the first layout.

Read article →
Fire, Structural and Basements8 min read

Shoring and temporary works during demolition

Planning does not approve temporary works, but propping footprint, highway occupation and party wall stability all constrain the permanent scheme. Resolve them at design stage, not after permission.

Read article →
Fire, Structural and Basements8 min read

Excavating a swimming pool in a garden

Class E of the GPDO covers a swimming pool in a domestic garden, but the enclosure, the plant room, twenty lorries of spoil and the backwash discharge are where schemes come unstuck.

Read article →
Fire, Structural and Basements7 min read

Rooftop plant and the capacity of an existing roof

An existing roof usually has very little spare capacity, and the reserve it appears to have is often in the slab rather than in the beams carrying it.

Read article →
Fire, Structural and Basements7 min read

Building beside railway infrastructure: asset protection

The council decides the application. The infrastructure manager decides whether your piling rig, your crane and your drainage are acceptable next to a live railway.

Read article →
Fire, Structural and Basements7 min read

Transfer structures over a commercial ground floor

The transfer zone sits between the commercial ceiling and the first residential floor, and it is additive. Developers usually discover that after the massing is fixed.

Read article →