Costs, Fees and Budgeting

Budgeting a written representations appeal

7 min readBy PlanScope Editorial Team

Lodging a section 78 appeal costs nothing, so the budget is all preparation. Here is how the written representations procedure works, what drives the cost, and when a revised application is the better buy.

There is no fee to lodge a section 78 appeal in England, so the written representations appeal cost is entirely the cost of preparing your case. For a refused extension or a single plot, that can mean a few hundred pounds of agent time and nothing else. For a refusal that turns on drainage, trees or highway safety, the specialist rebuttal evidence usually costs more than the original application did. The budget depends almost entirely on how many of the refusal reasons need technical answers rather than argument.

When written representations is the right procedure

Written representations is the default for small appeals and the least costly of the three procedures. Everything is done on paper, there is no hearing, and the inspector visits the site and decides.

The Planning Inspectorate chooses the procedure against published criteria rather than simply accepting your preference. A hearing or an inquiry becomes more likely where the issues need testing through questioning, where there is substantial third party interest, or where the evidence is complex and contested. For a householder refusal or a one to nine dwelling scheme with two or three refusal reasons, written representations is almost always what you get.

Householder appeals run on a simplified version of the procedure. The appeal is decided on the application documents and the appeal form, and neither side submits a further statement. That matters for the budget and for the drafting, because there is no later opportunity to answer what the council says. Everything goes in at the start.

Procedure Typical use Main cost drivers
Written representations (householder) Refused extensions, outbuildings, dropped kerbs Drafting the appeal statement once, with no follow-up stage
Written representations (standard) Minor schemes, changes of use, small residential sites Statement of case, any technical rebuttal, final comments
Hearing Contested minor schemes needing discussion Advocate or agent attendance, preparation, a longer timetable
Inquiry Majors and heavily contested cases Counsel, expert witnesses, proofs of evidence

The timetable and what is due when

The Inspectorate sets a start date once it accepts the appeal as valid, and issues the timetable with it. Work to those dates rather than to any general rule, because the timetable is the document that binds you.

The deadline for lodging matters more than anything else in this process. Most section 78 appeals must be lodged within six months of the date on the decision notice. Householder and minor commercial appeals must be lodged within twelve weeks. Those limits are strict, and a late appeal is rejected rather than argued about.

  1. Diarise the lodging deadline from the date on the decision notice, not the date you received it.
  2. Decide procedure and strategy early, because the full case usually goes in with the appeal form.
  3. Commission any technical evidence before you lodge, since the timetable afterwards is short.
  4. Note the date the authority's questionnaire and statement are due, and read both the day they arrive.
  5. Use the final comments stage, where the procedure allows one, to answer the authority rather than to repeat yourself.

Building the statement of case around the refusal reasons

The inspector redetermines the application, so the appeal is about the scheme as refused. Structure the statement around the reasons for refusal in the order the decision notice gives them, and answer each one on its own terms.

For each reason, do three things. Identify the policy the council relied on and quote it accurately, including the development plan policy number and the relevant part of the National Planning Policy Framework with its edition stated. Set out the evidence that meets the objection. Then say what weight the matter should carry in the balance.

Where the refusal reason is a matter of planning judgement, such as character or amenity, the work is argument supported by site photographs, sections and comparable appeal decisions. Where it is technical, argument does not help. A reason citing surface water flooding needs a drainage answer, and no amount of policy prose substitutes for it.

A well-structured Planning Statement is the natural backbone of the appeal, because it already sets out the policy framework and the compliance case. Reuse it, update it to answer the decision notice, and keep the appeal statement to the issues actually in dispute.

New technical evidence and whether it will be accepted

New evidence that answers a refusal reason is normally admissible. A tree report, a drainage assessment, a daylight study or a noise survey commissioned after refusal can all be submitted with the appeal, and inspectors routinely consider them.

A changed scheme is different. The appeal is against the refusal of the application as submitted, so amended drawings that alter the development are not a route to a different permission. Minor clarifications and corrections are usually accepted. A reduced footprint, a relocated access or a different roof form generally are not, and the inspector may decline to consider them or warn that proceeding risks prejudice to other parties.

So the honest question before you spend is whether the refusal can be answered with evidence about the scheme as refused. If it cannot, a revised application may be the better purchase, bearing in mind that a fresh application brings a fresh fee and that planning fees are indexed each April.

Third party representations and how to answer them

The authority forwards the representations made on the application, and interested parties can write to the Inspectorate during the appeal. Neighbours sometimes raise matters the council never mentioned.

Answer the planning points and ignore the rest. Loss of a private view, property values, boundary disputes, rights of light as a civil matter and the identity of the applicant are not material planning considerations, and dealing with them at length wastes words the inspector would rather see spent on the refusal reasons.

Where a third party raises something material that the council overlooked, address it briefly and with evidence. An inspector who finds an unanswered material point will consider it anyway.

Site visit types and what the inspector will see

Most small appeals are decided after an unaccompanied visit, where the inspector views the site from public land. If the issues cannot be understood without entering the site, the visit is accompanied and both parties attend, though no discussion of the merits takes place.

Two practical steps pay for themselves. Make sure the inspector can see what matters, by arranging access where an accompanied visit is needed and by flagging anything that is not visible from the street. And submit photographs that show the relationships you are relying on, with a plan showing where each was taken from, because an unaccompanied visit in February sees a very different site from the one in your July photographs.

Where the spend actually goes

Three cost centres, in descending order for most small appeals.

  • Drafting the statement of case, which is agent or consultant time measured in days rather than hours on anything beyond a simple extension
  • Technical rebuttal evidence, which is the single largest variable and is driven by how many refusal reasons are technical
  • Drawings, photographs and the bundle, which is modest but rarely zero

Against that sits the cost of the alternative. A revised application carries a fresh fee, fresh consultant input and another eight to thirteen weeks of determination time, with no certainty of a different officer view. Where the refusal is a policy objection to the principle of development, the appeal is usually the better route because it puts the question to someone outside the authority.

And budget something for the possibility of losing. A dismissed appeal starts a two year period in which the authority may decline to determine a similar application, so the next move after a dismissal is usually a substantially different scheme rather than a quick resubmission.

If you are assembling the evidence base, check which reports your site is likely to need and see PlanScope pricing before you commission the specialists.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How much does a written representations appeal cost?

There is no fee to lodge the appeal itself in England, so the cost is the preparation. A simple householder appeal may be a day or two of agent time. An appeal where refusal reasons turn on drainage, trees or highways needs specialist rebuttal evidence, which is usually the largest item and can exceed the original application cost.

What is the deadline for appealing?

Most section 78 appeals must be lodged within six months of the date on the decision notice. Householder and minor commercial appeals must be lodged within twelve weeks. The limits run from the date on the notice rather than the date you received it, and a late appeal is rejected rather than argued over.

Can I submit amended drawings with the appeal?

The appeal is against the refusal of the scheme as submitted, so amended drawings that change the development are generally not accepted. Minor clarifications and corrections usually are. New technical evidence answering a refusal reason, such as a drainage assessment or a tree report, is normally admissible and often decisive.

Do I get to reply to what the council says?

In the standard written representations procedure there is a final comments stage, so you can answer the authority's statement. Householder appeals are simplified and have no further statements after the appeal form, which means everything has to go in at the start. Check the timetable issued with the start date.

Is an appeal better than a revised application?

An appeal is usually better where the refusal is an objection to the principle of development, because it puts the question to someone outside the authority. A revised application is usually better where the refusal is fixable by design. Remember that a dismissed appeal opens a two year period in which the council may decline a similar application.

Sources and further reading

planning appealswritten representationsappeal costssection 78refusalsbudgeting

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting8 min read

Costing a stopping up order for a highway or footpath

Public rights do not lapse through disuse and planning permission does not override them. This covers the section 247 and 257 routes, what objectors actually argue about, and how to keep the order off the critical path.

Read article →
Costs, Fees and Budgeting7 min read

Costing an affordable housing review mechanism

Early and late stage review mechanisms are decided by their definitions, not their headline percentages. This covers the inputs that move the answer, who pays for the review and the caps to secure before signing.

Read article →
Costs, Fees and Budgeting7 min read

Costing an employment land assessment for an allocated site

On an allocated employment site the fee sits in evidence gathering, not analysis. This covers the marketing records councils expect, the suitability tests that decide it, and how to sequence the work.

Read article →
Costs, Fees and Budgeting7 min read

Costing an odour assessment for a kitchen or waste use

The fee for an odour assessment depends on whether the council accepts a qualitative risk based appraisal or expects dispersion modelling. Here is what sits behind each, and how to scope the work before you commission it.

Read article →
Costs, Fees and Budgeting6 min read

Costing a telecommunications compliance declaration for a mast

An ICNIRP declaration is produced by the operator's own radio engineers and closes the health issue. Siting and appearance are the only matters the council can decide on.

Read article →
Costs, Fees and Budgeting6 min read

Costing an equalities impact assessment for a public applicant

The public sector equality duty is continuing, so an equalities impact assessment has to be revisited at every material change. Budgeting for one document is the common mistake.

Read article →