Costs, Fees and Budgeting

Budgeting an environmental statement for Schedule 2 work

7 min readBy PlanScope Editorial Team

The competent expert requirement sets the floor on what an Environmental Statement costs. Survey seasons set the programme, and the programme sets the cash flow.

An Environmental Statement for Schedule 2 development costs what it costs because regulation 18 of the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 requires it to be prepared by competent experts, and requires the applicant to provide a statement outlining their expertise or qualifications. That is a legal requirement rather than good practice. Nobody can draft their way around it, and an AI-assisted draft is a starting point for those experts rather than a substitute for them.

For a major scheme the evidence base commonly runs to £50,000 or more, and the shape of that spend is predictable even where the total is not.

What the Regulations require of the authors

Three provisions set the floor.

Regulation 18 requires the Environmental Statement to be prepared by competent experts and the applicant to state their expertise. Schedule 4 sets the content: a description of the development, the baseline, the likely significant effects, the reasonable alternatives considered, the mitigation proposed, monitoring arrangements and a non-technical summary. And regulation 6 governs screening, where the authority decides whether a Schedule 2 project with its thresholds requires assessment at all.

Screening is the first budget decision and the least costly one. A screening request costs a fraction of an Environmental Statement, and a negative screening opinion removes the obligation entirely. Where the scheme sits near a threshold, for instance an urban development project on a site of around 5 hectares or in the region of 150 dwellings, it is worth designing to stay below it if the planning case allows.

A scoping opinion under regulation 15 is the second. It is not compulsory and it is almost always worth obtaining, because it limits what the authority can later say is missing, and that is the main protection against addenda.

Link the obligation to the deliverable early. An Environmental Impact Assessment is one of the report types where a competent professional is legally required, and the budget should name the experts chapter by chapter from the outset.

Chapter structure and where the cost concentrates

An Environmental Statement is a set of technical chapters with a coordinating layer over them, and the cost is unevenly distributed.

Chapter Cost driver
Ecology and biodiversity Seasonal surveys, often across a full year
Transport Survey counts in neutral months, modelling, junction assessment
Air quality Monitoring period, dispersion modelling
Noise and vibration Attended and unattended survey periods, modelling
Archaeology Geophysics, then trial trenching if indicated
Landscape and visual Seasonal photography, viewpoint agreement, visualisations
Ground conditions Intrusive investigation, laboratory testing
Water and flood risk Hydraulic modelling, Environment Agency engagement
Coordination and reporting Chapter integration, cumulative assessment, the summary

Ecology, transport and archaeology are usually the three largest, and the first two are also the most likely to produce a result that changes the scheme. Spend on those first.

The coordinating layer is routinely under-budgeted. Making nine chapters consistent, with a shared description of development, shared assumptions and a single mitigation schedule, is real work, and the person who does it is the one who stops the authority finding contradictions.

Baseline survey seasons as a cost driver

Seasons do not change the fee much. They determine when you can spend it, and on a scheme carrying holding costs that is the expensive part.

  • Bat emergence and re-entry surveys run May to September, optimal May to August.
  • Great crested newt environmental DNA sampling runs 15 April to 30 June.
  • Breeding bird surveys run March to August, wintering bird surveys October to March, so a full ornithological baseline spans a year.
  • Botanical surveys run April to September.
  • Reptile surveys run April to October, best April to May and September.
  • Traffic counts need neutral months, avoiding August, December and school holidays.
  • Landscape photography needs both winter and summer conditions for a credible assessment.

A project that misses the bird season loses a year on the ornithology chapter. That is why the ecology scope should be set in the first month of the programme, before the masterplan is settled, and why quotes for the same scope differ so much, which we look at in why ecology survey costs vary between quotes.

The Preliminary Ecological Appraisal is the document that tells you which seasonal surveys you need, so commission it first and commission it early in the calendar year.

Cumulative assessment and the data it needs

Cumulative effects are where Environmental Statements are most often found wanting, and the work is administrative rather than technical.

You need a list of other development to assess in combination. That means a search of the authority's planning register, usually over a defined radius and a defined period, capturing permitted schemes, undetermined applications and allocations. Each has to be characterised well enough to be assessed, which sometimes means downloading another applicant's transport chapter.

Three things keep this down. Agree the radius, the date range and the inclusion criteria in the scoping opinion, so the list is defined rather than arguable. Ask the authority for its own list, since some maintain one for exactly this purpose. And do the search once, properly, with a dated record, rather than repeatedly.

Budget for a refresh. On a scheme determined 12 months after submission, the cumulative list will have moved, and the authority may ask for an update.

Non-technical summary and consultation copies

Small line, easy to forget.

The non-technical summary is a Schedule 4 requirement and it has to be readable by a non-specialist. It is not a cut-down version of the chapter conclusions, and a good one takes a specialist writer a week.

Publicity obligations under the Regulations require the Environmental Statement to be made available, with copies obtainable at a reasonable charge. Electronic publication carries most of this now, though a handful of hard copies for the authority, statutory consultees and the deposit point still need producing. Printing a multi-volume statement with figures at A1 is not a trivial cost, and it is one that lands at the point the rest of the budget is spent.

Addenda after further information requests

This is the overrun that hurts.

Regulation 25 allows the authority to require further information where it considers the Environmental Statement inadequate, and the response is normally an addendum. The addendum then triggers its own publicity and consultation period, which adds weeks to the determination of a scheme already running on a 16 week statutory period for EIA development.

The cost is threefold: the technical work, the republication, and the holding cost of the delay. Addenda arise most often from an inadequate cumulative assessment, a baseline survey carried out outside the right season, or a mitigation schedule that does not match what the chapters propose.

Two defences. Get a scoping opinion and follow it, because an authority that scoped out a topic struggles to request it later. And commission an internal review of the full statement by someone who has not written any of it, before submission. That review costs a fraction of an addendum.

Where the scheme is large enough, a planning performance agreement puts the authority's resourcing and timetable on a formal footing, and what that buys is covered in planning performance agreements and what you are paying for.

Sequencing the spend across two financial years

Most Environmental Statements span two financial years, so plan the cash flow rather than the total.

Year one usually carries screening, scoping, the preliminary ecological appraisal, the first seasonal surveys, baseline monitoring for air quality and noise, and the ground investigation. Year two carries the remaining seasonal surveys, the modelling, chapter drafting, coordination, the summary and the publicity costs.

Three practical rules. Front-load anything season-dependent, because a missed window moves the whole programme. Hold back a contingency equal to a meaningful proportion of the technical budget for a regulation 25 addendum, since the probability is not low. And do not let the masterplan freeze lag the baseline, because a design change after the surveys are complete can invalidate the assessment of effects.

For the supporting documents that sit alongside the statement rather than within it, see PlanScope pricing to compare the drafting routes.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

Who can prepare an Environmental Statement?

Competent experts. Regulation 18 of the Environmental Impact Assessment Regulations 2017 requires the statement to be prepared by competent experts and requires the applicant to provide a statement outlining their expertise or qualifications. That is a legal requirement, so the budget should name the expert for each chapter from the outset.

Is a scoping opinion worth paying for?

Almost always. A scoping opinion under regulation 15 is not compulsory, but it limits what the authority can later say is missing, which is the main protection against a request for further information and an addendum. Agree the cumulative assessment radius, date range and inclusion criteria within it.

Which chapters cost the most?

Ecology, transport and archaeology are usually the three largest. Ecology is driven by seasonal survey windows that can span a full year, transport by survey counts in neutral months and junction modelling, and archaeology by geophysics followed by trial trenching where the desk study indicates it.

What causes an addendum after submission?

Most often an inadequate cumulative assessment, a baseline survey carried out outside the correct season, or a mitigation schedule inconsistent with what the technical chapters propose. The addendum triggers its own publicity period, so the cost is the technical work, the republication and the delay to a scheme on a 16 week statutory period.

How should the spend be phased?

Front-load everything season-dependent, because a missed survey window moves the whole programme. Year one typically covers screening, scoping, the ecological appraisal, first seasonal surveys, air quality and noise baselines and ground investigation. Year two covers remaining surveys, modelling, drafting, coordination and publicity costs.

Sources and further reading

eiaenvironmental statementbudgetingschedule 2developers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting8 min read

Costing a stopping up order for a highway or footpath

Public rights do not lapse through disuse and planning permission does not override them. This covers the section 247 and 257 routes, what objectors actually argue about, and how to keep the order off the critical path.

Read article →
Costs, Fees and Budgeting7 min read

Costing an affordable housing review mechanism

Early and late stage review mechanisms are decided by their definitions, not their headline percentages. This covers the inputs that move the answer, who pays for the review and the caps to secure before signing.

Read article →
Costs, Fees and Budgeting7 min read

Costing an employment land assessment for an allocated site

On an allocated employment site the fee sits in evidence gathering, not analysis. This covers the marketing records councils expect, the suitability tests that decide it, and how to sequence the work.

Read article →
Costs, Fees and Budgeting7 min read

Costing an odour assessment for a kitchen or waste use

The fee for an odour assessment depends on whether the council accepts a qualitative risk based appraisal or expects dispersion modelling. Here is what sits behind each, and how to scope the work before you commission it.

Read article →
Costs, Fees and Budgeting6 min read

Costing a telecommunications compliance declaration for a mast

An ICNIRP declaration is produced by the operator's own radio engineers and closes the health issue. Siting and appearance are the only matters the council can decide on.

Read article →
Costs, Fees and Budgeting6 min read

Costing an equalities impact assessment for a public applicant

The public sector equality duty is continuing, so an equalities impact assessment has to be revisited at every material change. Budgeting for one document is the common mistake.

Read article →