Competence expectations under the building safety regime

6 min readBy PlanScope Editorial Team

Planning Gateway One puts a named author on the fire statement, and the Building Regulations put competence duties on clients, designers and contractors. Here is what that means for a planning submission.

Building safety competence in planning is not a general claim to be good at your job. For higher-risk buildings it is a documented answer to a narrow question: does the person who wrote this document have the skills, knowledge, experience and behaviours to write it, and can you show that if the Building Safety Regulator asks. The duty bites hardest at building control stage, but two planning-stage submissions already carry a named author whose competence is on the record.

The regime sits on the Building Safety Act 2022, with the Regulator hosted inside the Health and Safety Executive. A higher-risk building for the Regulator's purposes is at least 18 metres tall or has at least seven storeys, and contains at least two residential units. Planning Gateway One reaches a wider set of buildings than that, which is where architects most often get caught out.

Where the planning stage picks up a competence duty

Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015 requires a fire statement with applications for development involving relevant buildings, and makes the Health and Safety Executive a statutory consultee. A relevant building broadly means one containing two or more dwellings, or educational accommodation, that meets the height condition of 18 metres or seven storeys.

The fire statement is submitted on the published form, and the form asks who prepared it, what their qualifications are and what relevant experience they hold. That is the competence test in practice. An unnamed statement, or one signed off by a project architect with no fire engineering background, invites a holding response from the Regulator and a validation query from the council.

A Fire Statement is one of the report types where a suitably qualified professional is legally required rather than merely advisable. The same is true of a Fire Safety Strategy prepared to BS 9991 or BS 9999. PlanScope can draft the structure and the policy narrative around either, and the draft flags every site fact it does not hold, but it is a starting point for a fire engineer, not a replacement for one.

The roles that carry duties

Duties on clients, designers, principal designers and contractors were added to the Building Regulations 2010 by the 2023 amendment regulations and applied from 1 October 2023. They apply to all building work rather than to higher-risk buildings alone, which surprises people who assumed this was a tall-buildings problem.

The short version is that nobody may accept an appointment, or take on work, unless they have the competence for that particular job. Competence is assessed against the work in front of you rather than in the abstract, so an architect who is competent to design a three storey terrace is not thereby competent to act as principal designer on a 20 storey residential block.

Clients carry a duty too. A client must take reasonable steps to satisfy themselves that the people they appoint are competent, and must not appoint where they are not satisfied. In a development company that means a written check before the appointment letter goes out, not a conversation afterwards.

What counts as evidence

BS 8670-1 sets core criteria for competence frameworks in the built environment, and the associated PAS documents cover principal designers, principal contractors and the management of safety in occupied residential buildings. Institutions have built registers and assessment routes against them.

In an appointment file, useful evidence looks like this:

  • chartered membership or registration with the relevant institution, with the grade stated
  • a named individual rather than a firm, because competence attaches to people
  • project experience of comparable type, height and complexity, with dates
  • continuing professional development records relevant to the subject
  • the limits of the appointment, written down, so that the scope of what was assessed is clear

Titles alone prove little. Membership of an institution shows that a person met an entry standard at a point in time, which is why what chartered membership actually means is worth understanding before you rely on the letters after a name. The same question arises across the technical disciplines, from fire to ground conditions, and the answer is usually specific to the standard in play rather than generic. Who can carry out a Phase 2 ground investigation works through an example.

Consistency between the planning scheme and Gateway Two

A planning permission that cannot be built as approved is a commercial problem, and under the gateway regime it is a visible one. The Gateway Two application to the Regulator must show a building that satisfies the functional requirements, and the drawings will be compared with what the council approved.

Two areas cause most of the trouble. Vertical circulation is the first: staircase provision in tall residential buildings changed with the amendment to Approved Document B, and transitional arrangements determine which projects may still proceed on the earlier basis. Check the current Approved Document B and the commencement wording before you assume a scheme is in the old regime.

Fire service access and water supplies are the second, because they take up land outside the building line. A hardstanding for a pumping appliance that was never shown on the planning layout has to come from somewhere, and if it takes amenity space or parking you may need a section 73 application to vary the approved plans.

The way to avoid both is to have the fire engineer produce the strategy early enough that the planning drawings reflect it. That runs against the usual fee sequence, where the fire engineer arrives after permission. It is also why conflicts of interest when your designer writes the reports matter: the person marking the homework should not have set it.

Records that outlive the project

The golden thread requires information about the building to be kept, in a structured and accessible form, and handed on. Competence evidence forms part of the surrounding paper trail: who was appointed, on what basis, and what they were asked to do.

Keep the fire statement, the strategy it was based on, the version of the Approved Document or British Standard used, and the dated appointment record. When a building changes hands, or a defect emerges years later, those documents decide who answers for what.

Checks to run before you appoint

  1. Write down the scope of the appointment, including the building height, storey count, use and whether it is a higher-risk building.
  2. Ask for a named individual, their registration or membership grade, and two comparable projects with dates.
  3. Confirm the professional indemnity cover in place, the limit, and whether fire safety work is excluded, because exclusions are common.
  4. Record what you relied on when you decided the person was competent, and keep it with the appointment.
  5. Re-run the check if the scheme grows past a threshold, because a building that gains a storey may change category.

PlanScope's professional review route lets an AI-drafted document be sent to a reviewer who can check and sign it off, and the professional directory is where that request starts. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

Which buildings need a fire statement with the planning application?

Article 9A of the Development Management Procedure Order 2015 requires one for relevant buildings, broadly those containing two or more dwellings or educational accommodation that meet the height condition of 18 metres or seven storeys. The Health and Safety Executive is a statutory consultee on those applications, so the statement is read by the Building Safety Regulator as well as the council.

Do competence duties apply to small projects too?

Yes. The duties added to the Building Regulations 2010 and applied from 1 October 2023 cover all building work rather than higher-risk buildings alone. Clients, designers, principal designers and contractors must each be competent for the specific work they take on, and a client must take reasonable steps to check before appointing.

Can an architect write the fire statement?

Only if they hold the fire engineering competence for that building. The form asks for the author's qualifications and relevant experience, and the Regulator reads it. On a higher-risk building the statement is normally written by a fire engineer working from the fire strategy, with the architect coordinating the drawings that the statement describes.

What evidence of competence should be kept on file?

A named individual rather than a firm, their registration or institutional membership and grade, comparable project experience with dates, relevant continuing professional development, the written scope of the appointment and the professional indemnity position. Record what you relied on at the time you decided the person was competent, and keep it with the appointment letter.

What happens if the planning drawings conflict with the Gateway Two submission?

The Regulator assesses the building against the functional requirements and the drawings are compared with the approved scheme. Differences in staircase provision, fire service access or hardstanding usually mean a section 73 application to vary the approved plans, with the delay and fee that involves. Getting the fire strategy written before the planning drawings are fixed avoids most of it.

Sources and further reading

building safety actfire statementgateway onecompetencehigher-risk buildingsplanning submissions

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Professionals and Qualifications

View all →
Professionals and Qualifications6 min read

Checking a consultant's membership and currency

Letters after a name tell you somebody passed an assessment once. Currency, indemnity cover and the right institute are what protect you.

Read article →
Professionals and Qualifications6 min read

Odour assessment competence and who can sign one

An odour risk assessment needs dispersion judgement as well as ductwork knowledge. The two skills rarely sit in the same person, and almost never in the supplier.

Read article →
Professionals and Qualifications7 min read

Transport evidence: who signs a trip generation note

A trip generation note is only as good as the judgement behind the site selection. Here is the competence highway authorities look for and what to put in the brief.

Read article →
Professionals and Qualifications6 min read

Whole life carbon assessment competence and scope

The RICS whole life carbon standard fixes the modules, the 60 year study period, the data rules and the reporting format. Most differences between assessments come from scope choices, not arithmetic.

Read article →
Professionals and Qualifications7 min read

Overheating assessments and CIBSE TM59 competence

Nobody is licensed to run a CIBSE TM59 overheating assessment, so competence is judged on the inputs. The weather file, assumptions schedule and per-room results are the places to look.

Read article →
Professionals and Qualifications6 min read

What MRTPI tells you about a planning agent

Chartered membership of the Royal Town Planning Institute signals assessed competence and a binding code of conduct. It is not a financial remedy, and planning consultancy has no protected title at all.

Read article →