Cycle parking that meets the standards and gets used

7 min readBy PlanScope Editorial Team

Numbers come from the local plan, quality comes from LTN 1/20. Stand spacing, access routes, two tier racks and the design decisions that decide whether a cycle store is used or ignored.

Cycle parking design standards are set in two places, and meeting one does not mean meeting the other. The number of spaces comes from the adopted local plan or, in London, the London Plan. The quality of those spaces comes from the Department for Transport's cycle infrastructure design guidance, LTN 1/20, which sets out stand spacing, access dimensions and the provision expected for non-standard cycles. A scheme can hit the numerical standard exactly and still produce a store that nobody uses.

Counting spaces against the adopted standard

Start with the policy, because the count changes the floor area you need and therefore the layout.

Most authorities express residential standards per dwelling or per bedroom, with a separate short-stay figure for visitors. Commercial standards are usually per square metre of floorspace, varying by use class, with separate figures for staff and for visitors. London boroughs apply the minimum standards in the London Plan tables, and several apply higher local figures on top.

Three counting errors turn up repeatedly in submissions.

  • Counting a two-tier rack as two spaces without checking whether the authority discounts the upper tier.
  • Counting spaces in a store that can only be reached through a dwelling or a plant room.
  • Applying the residential standard to the whole building where part of it is commercial, which usually undercounts.

Write the calculation into the transport documents as a table showing the policy source, the standard, the resulting requirement and the provision. An officer who can check your arithmetic in ninety seconds is an officer who does not send a holding letter.

Short stay and long stay do different jobs

The two categories are not interchangeable and a scheme that provides only one of them fails both.

Type Who uses it Where it goes What it needs
Short stay Visitors, deliveries, quick trips Within sight of the main entrance, typically within about 25 metres Stands in the open, well lit, overlooked
Long stay Residents, staff, students Secure enclosure, can be slightly further from the entrance Enclosed, covered, controlled access, good lighting

Short-stay stands placed around the corner from the door are ignored, and the bikes end up locked to the railings by the entrance. That is worth designing for rather than fighting, because it is entirely predictable.

Long-stay stores placed in a basement reached by a narrow stair are also ignored, and the bikes end up in hallways and on balconies. Management companies then write to the authority about it, which is a poor outcome for everyone.

Stand type, spacing and the space behind

The Sheffield stand remains the default for good reasons. It supports the frame at two points, it takes two bikes, and it accepts almost any lock.

Get the dimensions right. A stand about 750 millimetres high, set at 1,000 millimetre centres as a minimum with 1,200 millimetres preferred, gives room to load a bike either side without the pedals fouling. Stands set parallel to a wall need clearance behind them so a bike can be manoeuvred, and a run of stands needs an access aisle of around 2,000 millimetres so that someone can get past a bike being loaded.

Wheel-only racks, the kind that grip the front wheel, should be avoided. They do not support the frame, they damage wheels, and a modern lock cannot secure the frame to them.

Provision for non-standard cycles matters more each year. Cargo bikes, trikes, adapted cycles and trailers do not fit a 1,000 millimetre bay, and LTN 1/20 asks designers to accommodate them. Several authorities now require a stated proportion of larger spaces, and designing a handful of oversized bays into the store from the start costs nothing compared with retrofitting them.

Two tier racks and when they should count

Two-tier racks fit more bikes into a given footprint, and they need around 2.7 metres of clear height to work, with a gas-assisted upper tier that can be pulled down and loaded.

They also exclude people. Lifting a bike to the upper tier is beyond many users, and a store that is wholly two-tier is effectively a store at half capacity for anyone with limited strength, an e-bike or a child seat.

The sensible approach is a mix, with ground-level Sheffield stands for a defined proportion of spaces and two-tier racks for the remainder. Some authorities count the upper tier at a discount or refuse to count it at all. Check the local position before the store is sized, because discovering it at validation means redrawing the plan.

Getting a bike from the street to the store

This is where most designs fail, and it is almost never covered in the transport statement.

Walk the route on the drawing. From the street, across the threshold, along the corridor, through the doors, into the store, and to the furthest stand. Then ask whether a person pushing a loaded bike can do it without lifting anything.

  1. Doors on the route need around 1,000 millimetres clear width, and a bike cannot be pushed through a door that opens towards you while you hold the handlebars, so specify hold-open devices or automatic openers.
  2. Steps on the route are fatal. A wheeling ramp bolted to a stair is a poor substitute and is unusable with a cargo bike.
  3. Where a lift is the only route, check the car dimensions against a 1,800 millimetre bike length and confirm the lift serves the store level.
  4. Thresholds, door closers and tight corners each add friction, and friction is what decides whether the store gets used.
  5. Where the store shares a route with refuse, check the two do not conflict on collection day, which is a common pinch point covered in the guidance on bin storage and collection points in flatted schemes.

Security, lighting and shelter

Theft is the reason people stop cycling. A long-stay store needs a solid enclosure, a controlled entry system that residents actually carry, and no gaps large enough to pass a bike through.

Lighting should be on the approach as well as inside, because a dark external route to a well-lit store is still a deterrent. Natural surveillance from windows or a circulation route helps more than a camera nobody monitors.

Cover matters for long stay and is welcome for short stay. An uncovered long-stay compound will produce rusted drivetrains within a season and the bikes will move indoors.

Where an authority expects a Secured by Design standard or an equivalent, the specification note belongs in the application rather than in a later condition discharge.

Showing it on the drawings

Six things make a cycle parking proposal easy to approve.

  • A dimensioned store plan at 1:50 or 1:100 with stands drawn to scale, not as symbols.
  • A bike shown in plan at each stand type, including one non-standard cycle.
  • The access route from the public highway marked, with door widths annotated.
  • A schedule tying the provision to the policy standard.
  • Elevation or section showing headroom where two-tier racks are proposed.
  • A note on security specification, lighting and the management arrangement.

As an illustrative example, a block of 30 flats in a borough requiring one long-stay space per one-bedroom unit and two per larger unit generates a store of a size that will not fit under the stair. Discovering that at planning stage produces a ground-floor store with a direct external door. Discovering it at Building Regulations stage produces a basement store, a stair, and a set of bikes in the communal hallway.

Where a travel plan is required, the cycle provision becomes one of its monitored measures, so the two documents should be written together rather than in sequence. The Travel Plan page sets out what that document usually covers. Parking for disabled residents follows a separate set of rules again, covered in accessible and blue badge parking in new development, and charging provision is dealt with in electric vehicle charging in new residential development.

To see which transport documents your scheme is likely to need, enter your postcode on PlanScope.

This is general guidance, not legal advice, so check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How far apart should Sheffield stands be?

A minimum of around 1,000 millimetres between stands, with 1,200 millimetres preferred, so that bikes can be loaded on both sides without pedals fouling. Allow clearance behind any stand set against a wall, and an access aisle of roughly 2,000 millimetres so someone can pass a bike that is being locked up.

What is the difference between short stay and long stay cycle parking?

Short stay serves visitors and quick trips, so it sits in the open within sight of the main entrance, well lit and overlooked. Long stay serves residents, staff and students, so it needs an enclosed, covered store with controlled access. A scheme providing only one of the two fails both requirements.

Do two tier racks count towards the standard?

It depends on the authority. Some count both tiers, some apply a discount and some refuse to count the upper tier. They need around 2.7 metres of clear height and a gas-assisted mechanism, and they exclude users who cannot lift a bike, so a mix with ground level stands is the sensible approach.

What access width does a cycle store need?

Around 1,000 millimetres clear through doors on the route, with hold-open devices or automatic openers, because a bike cannot easily be pushed through a door that opens towards the user. Steps on the route make a store unusable for heavier and non-standard cycles, and lifts need checking against a bike length of roughly 1,800 millimetres.

Do I need to provide for cargo bikes?

LTN 1/20 asks designers to accommodate non-standard cycles, including cargo bikes, trikes, adapted cycles and trailers, and several authorities now require a stated proportion of oversized spaces. Designing a few larger bays into the store at the outset costs almost nothing compared with retrofitting them after occupation.

Sources and further reading

cycle parkingltn 1/20transportsite designtravel plansustainable transport

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking6 min read

Temporary traffic orders for construction works

A construction programme usually needs four separate highway permissions, each under a different power. What each one covers, how long it lasts and what happens when works overrun.

Read article →
Transport, Highways and Parking8 min read

Highway drainage for a new rural access

Highway authorities treat run-off and material transfer onto a rural lane as a safety matter. The design comes down to the levels in the first few metres and the consent position for the roadside ditch.

Read article →
Transport, Highways and Parking7 min read

Car club and travel voucher contributions

The money is simple. The on-street bay needs a traffic regulation order the developer cannot deliver, and the operator may never come forward.

Read article →
Transport, Highways and Parking7 min read

Gated accesses and emergency service override

Three bodies have a view on a gated access: the highway authority, the fire service and the waste service. Design for all three before the driveway is drawn.

Read article →
Transport, Highways and Parking7 min read

Blocking back and queue length at a junction

A capacity ratio tells you how hard an arm is working. Only the queue in metres, compared against measured storage, tells you whether the junction behind will block.

Read article →
Transport, Highways and Parking7 min read

Which design vehicles to test in a swept path analysis

A tracking drawing is only as good as the vehicle chosen. The routine and occasional movements to test, and the parked car case most submissions omit.

Read article →