Drainage information required at outline stage

7 min readBy PlanScope Editorial Team

An outline application needs proof the site can be drained, enough land reserved to do it, and a deliverable discharge point. Detailed design belongs in a condition.

At outline stage a council needs to be satisfied that the site can be drained, that enough land has been set aside to do it, and that the rate and point of discharge are achievable. It does not need pipe sizes, manhole schedules or a hydraulic model. Where an outline application stalls on drainage, it is usually because one of those three things was asserted rather than evidenced, or because the applicant submitted a detailed design that fixed a parameter they later wanted to move.

The distinction matters commercially. A parameter plan that commits 0.4 hectares to attenuation in the wrong corner of the site is very hard to unwind at reserved matters.

What has to be fixed at outline

An outline application under Article 5 of the Town and Country Planning (Development Management Procedure) (England) Order 2015 seeks permission for the principle of development, with one or more of access, appearance, landscaping, layout and scale reserved.

Drainage is not one of the five reserved matters. It sits alongside them as a material consideration, so the level of detail required is whatever the decision maker needs to conclude the development is acceptable in principle. Three things normally have to be resolved at that stage.

  1. That surface water and foul water can both be dealt with, by a route that exists or can be secured.
  2. That the developable area shown can accommodate the drainage infrastructure without displacing the quantum of development applied for.
  3. That flood risk on and off the site is acceptable, which for sites in Flood Zone 2 or 3, or of one hectare or more in Flood Zone 1, means a site-specific Flood Risk Assessment at validation.

Everything past that is design, and design follows the layout that has not been fixed yet.

Showing that the site can be drained

The outline-stage Drainage Strategy is a feasibility document. It should establish the discharge hierarchy position with evidence rather than assertion, and that evidence is usually four items.

Preliminary infiltration testing, or a clear statement of why infiltration was ruled out. Underlying clay, a high water table, made ground with a contaminative history or a source protection zone are all legitimate reasons, but say which one applies and show the ground data behind it. Groundwater levels deserve particular care, and the wider question of groundwater flooding evidence and how to assess it often decides whether infiltration is available at all.

A written response from the sewerage undertaker to a pre-development enquiry, giving a point of connection and any capacity constraint for both foul and surface water.

Where discharge to an ordinary watercourse is proposed, confirmation of ownership or access to the outfall and an acknowledgement that consent under section 23 of the Land Drainage Act 1991 will be required from the lead local flood authority. For a main river, the Environment Agency's permitting position.

A greenfield runoff calculation with the method stated, and the resulting storage volume calculated for the design events with the Environment Agency climate change allowance applied. Say which allowance and which epoch you used.

That package tells the lead local flood authority the site works. It does not tell them how, and at outline it does not have to.

Land take for drainage in the parameter plans

This is the part applicants underestimate. Attenuation for a greenfield-rate discharge on a medium-sized residential site is measured in thousands of cubic metres, and if it is delivered in open basins at shallow depth the land take is real.

Calculate the volume first, then decide the form, then decide whether it is shown as a fixed parameter or as an area within which drainage will be provided. The second framing is usually better. A parameter plan that identifies a drainage zone of a stated minimum area, positioned at the low point of the site, gives the authority its certainty and leaves the designer room.

Some practical points that repeatedly cause trouble at reserved matters. Basin side slopes eat area, so a volume that looks like it fits at 1 in 3 slopes may not at the 1 in 4 the council's own guidance expects. Attenuation cannot sit under adoptable highway in some undertakers' standards. And a basin shown in the same location as the required open space or biodiversity net gain area will be counted twice by an optimistic layout and once by the officer.

Show the drainage zone, the developable area and the open space on the same plan at the same scale. If they overlap, resolve it before submission.

Discharge point and rate at outline

The discharge rate is a number the authority will condition, so give it deliberately. Greenfield rate applies on greenfield sites. On previously developed land, policy normally requires betterment against the existing rate, and the size of that betterment varies between lead local flood authorities, so check the local standard rather than assuming a percentage.

The discharge point needs to be deliverable. A proposed outfall on third-party land with no easement is not a strategy, and officers have become quicker at spotting this. Where an easement is needed, say so at outline and explain the route to securing it, because an authority can grant permission subject to a Grampian condition preventing commencement until the outfall is secured.

Flood Zone work runs in parallel. If the site needs the sequential and exception tests, do them at outline. The two limbs of the exception test and the evidence each needs are a matter of principle, not of layout, so leaving them to reserved matters is not an option.

What properly belongs in a condition

The Planning Practice Guidance sets six tests for conditions: necessary, relevant to planning, relevant to the development permitted, enforceable, precise and reasonable in all other respects. A detailed drainage design condition meets all six at outline.

A workable set usually reads along these lines.

Stage Condition
Before commencement of each phase Detailed surface water drainage design in accordance with the approved outline strategy, including infiltration test results, network modelling and exceedance routing
Before commencement Foul drainage details, including any off-site works agreed with the undertaker
Before occupation Verification report confirming the system was built as approved
In perpetuity Maintenance and management plan with responsibilities and frequencies

Two cautions on pre-commencement conditions. Section 100ZA of the Town and Country Planning Act 1990 requires the applicant's written agreement to a pre-commencement condition, so you will be asked to sign a schedule. Read it. And phrase phased conditions by phase rather than for the whole site, or the first phase cannot start until the last phase is designed.

When the authority asks for more than it needs

Lead local flood authorities are under pressure and some respond to an outline consultation with a request for a full detailed design. That is a disproportionate request and it can be resisted politely.

The reply that works sets out what the strategy demonstrates, points to the conditions offered, and asks specifically what residual question the authority has that the conditions do not answer. Most of the time the honest answer is that the officer wants reassurance on one point, usually infiltration or the outfall, and that point can be met with a single additional piece of evidence rather than a full design.

Where the request persists, the escalation is to the case officer rather than the consultee, because the decision on proportionality is the local planning authority's. An extension of time is usually preferable to a refusal on drainage grounds, since a refusal reason of this kind is expensive to overturn on appeal and easy to avoid.

Parameters that constrain later phases

The last thing to check before submission is what the outline permission will lock in. Read the proposed parameter plans and conditions as though you were the engineer designing phase three in four years.

Finished floor levels expressed as a fixed figure rather than a minimum become a problem when the detailed levels design moves. A drainage zone shown as a precise polygon becomes a problem when the layout shifts by 10 metres. A discharge rate stated for the whole site with no phasing becomes a problem when phase one has to build the whole attenuation volume before selling a house.

State rates and volumes by phase where the development will be phased. Express levels as minima. Describe the drainage zone as an area of at least a stated size within a broader parcel. And make sure the strategy document itself is the one listed in the approved plans condition, because whatever is listed there is what the reserved matters submission has to accord with.

Enter your postcode on PlanScope to see which reports an outline application on your site is likely to need.

This is general guidance, not legal advice. Check the position with your local planning authority and lead local flood authority before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is drainage a reserved matter?

No. The five reserved matters under the Development Management Procedure Order 2015 are access, appearance, landscaping, layout and scale. Drainage sits alongside them as a material consideration, so the level of detail needed at outline is whatever allows the decision maker to conclude the principle of development is acceptable.

Do I need infiltration testing before submitting an outline application?

You need either preliminary testing or a clear evidenced reason why infiltration was ruled out, such as underlying clay, a high water table, made ground with a contaminative history or a source protection zone. An unsupported statement that infiltration is not viable is the single most common cause of a holding objection from the lead local flood authority.

How should drainage land take be shown on a parameter plan?

Calculate the storage volume first, then show a drainage zone of a stated minimum area at the low point of the site rather than a precise polygon. Check it against side slope allowances, adoption restrictions on attenuation under highway, and any open space or biodiversity area, because those are frequently counted twice.

Can the council require a full detailed drainage design at outline?

It can ask, but the request is usually disproportionate where conditions can secure the detail. Reply by setting out what the strategy demonstrates, offering the conditions, and asking what specific residual question remains. Escalate to the case officer rather than the consultee, since proportionality is the local planning authority's decision.

Do the sequential and exception tests have to be done at outline?

Yes, where they apply. Both are questions of principle rather than layout, so they cannot sensibly be deferred to reserved matters. A site-specific flood risk assessment is a national validation requirement for sites in Flood Zone 2 or 3, and for sites of one hectare or more in Flood Zone 1.

Sources and further reading

outline planningdrainagesudsparameter plansconditionsflood risk

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS7 min read

Raising ground levels and the displacement objection

Raising a building platform above the flood level removes storage the river still needs. Here is when that is acceptable, what conditions follow and the alternatives.

Read article →
Flood, Drainage and SuDS7 min read

Floodplain compensation storage and level for level

Balancing volumes is not enough. Floodplain compensation has to replace storage at the same elevations, connected to the same reach, and be secured on land you control.

Read article →
Flood, Drainage and SuDS7 min read

Wet pond or dry basin: choosing between them

A retention pond and a dry detention basin do the same hydraulic job. The choice turns on treatment performance, water balance, aerodrome safeguarding and who maintains it.

Read article →
Flood, Drainage and SuDS7 min read

Choosing a flow control device for a small development

On a small site the permitted discharge rate is often so low that the physical outlet becomes the problem. Here is how vortex devices, orifice plates and weirs differ, and what head you need for each to work.

Read article →
Flood, Drainage and SuDS6 min read

Which rainfall dataset the drainage model should use

The rainfall input changes a drainage answer more than the model does. Here is how the older and newer national rainfall datasets differ, how to agree one with the lead local flood authority and what a reviewer checks first.

Read article →
Flood, Drainage and SuDS7 min read

Drainage for a single plot: what is proportionate

Major development drainage standards get applied to single plots far too often. Here is what one new house has to show, and when that changes.

Read article →