Extant planning permission and how to keep it alive
A permission is extant while it can still be lawfully implemented. Here are the section 91 and 92 time limits, what counts as a material start, and the options once a consent has gone.
A planning permission is extant while it remains capable of being lawfully implemented, which in practice means the time limit for starting work has not run out and nothing has happened to make the consent impossible to carry out. For anyone holding a consent through a slow market, that one word decides whether a site carries value or whether the whole application has to be run again. Most full permissions in England carry a three year limit under section 91 of the Town and Country Planning Act 1990. Miss it and there is no cure.
What extant means in practice
Extant is not a statutory term. It is the word practitioners use for a permission that is still alive: granted, unexpired, not revoked or quashed, and capable of being built out as approved. Once a permission has been lawfully begun it stays alive indefinitely, subject only to a completion notice under section 94 of the 1990 Act. A permission never begun dies on its expiry date, and nothing short of a fresh grant brings it back.
Three things take a permission out of that state. The time limit runs out without a material start. The permission is revoked, modified or quashed. Or the land itself changes so that the approved scheme can no longer be carried out as a whole, which is the ground the Supreme Court covered in Hillside Parks Ltd v Snowdonia National Park Authority in 2022.
That last route catches people out on long sites. If you build something materially different from the approved layout on part of a site, the original permission may become incapable of lawful completion across the rest of it.
The time limits that apply
Full permission carries a condition requiring development to begin within three years of the date of the grant, unless the authority imposed a different period. If no condition was imposed, section 91 supplies three years by default.
Outline permission works in two stages under section 92. An application for approval of reserved matters must be made within three years of the outline grant, and development must then begin within two years of the final approval of the last reserved matter. And both legs matter. A promoter who lets the reserved matters deadline pass has lost the outline even though the second period looks generous on paper.
| Consent | What must happen | Default period |
|---|---|---|
| Full permission | Material start on site | 3 years from grant |
| Outline permission | Reserved matters application submitted | 3 years from grant |
| Outline permission | Material start on site | 2 years from final reserved matters approval |
| Listed building consent | Works begun | 3 years from grant |
Authorities can and do shorten these periods, usually where a site is contentious or a policy position is about to change. Read the condition rather than assuming the default.
What counts as a material start
Section 56(4) of the 1990 Act sets out the operations that count as beginning development. Digging a trench that will hold the foundations, laying an underground main or pipe to those foundations, any work of construction in the course of erecting a building, demolition, laying out or constructing a road, and a material change of use all qualify.
The threshold is low in volume and high in care. A short length of foundation trench, properly set out in the approved position and recorded, has been enough in many cases. What defeats a start is not scale. It is doing the work in the wrong place, in breach of a condition, or without the paperwork that proves it happened.
An illustrative example: on a 48 unit scheme with eight months left on a three year permission, a contractor excavates and pours a section of foundation for plot one, photographs it against a dated site plan, and the engineer signs a short record of the setting out. That is a defensible start. The same trench dug 15 metres off the approved position, with no record, is an argument waiting to happen.
Starting work also triggers other duties. Under the Community Infrastructure Levy Regulations 2010 a commencement notice has to be submitted before development begins, and a failure there can cost relief that had already been granted. If you are starting purely to keep a consent alive, sequence the levy paperwork first.
Conditions that have to be discharged first
A condition precedent is one that must be satisfied before development begins. Where work is carried out in breach of such a condition, the courts have held that the work does not amount to lawful implementation at all, a line that runs from Whitley and Sons v Secretary of State for Wales. The practical result is brutal. You dug the trench, the clock still ran out, and the permission expired.
So the pre-commencement conditions are the real deadline, not the expiry date. Discharge applications take eight weeks to determine and often need further information, which is why the deemed discharge route for planning conditions is worth understanding before you are down to weeks. Work backwards from the expiry date through the discharge period, the consultee responses and the information you have to produce, and you usually find the real cut-off is six to nine months earlier than the date on the decision notice.
Watch for conditions that cannot be discharged at all without third party agreement, such as a highway works condition that depends on an agreement under section 278 of the Highways Act 1980, or a drainage condition requiring the undertaker's sign-off.
When a permission has lapsed
There is no general renewal application. The temporary procedure that allowed an application to extend a time limit no longer runs, and section 73 of the 1990 Act expressly cannot be used to extend the period within which development must begin or reserved matters must be submitted. A lapsed permission means a fresh application on the current policy position.
That is more than an administrative reset. The development plan may have changed, the red line boundary may need redrawing around a different access, biodiversity net gain now applies where it did not before, and any pre-application discussion starts from today's officer view. Budget for a new evidence base rather than a dusting-down of the old one.
Where only part of a scheme has lapsed, look closely at whether the permission was phased and whether each phase carried its own trigger. Phasing conditions sometimes preserve later parcels when the headline period has gone.
Variations, fresh applications and overlapping consents
If the scheme has moved on but the permission is still alive, a section 73 application varies conditions without touching the time limit, and section 96A deals with non-material amendments. Neither extends the life of the consent. Where the change is large enough to need a fresh permission over land already covered by an extant one, the Hillside question arises: can both be implemented together, or does building out the new one make the old one incapable of lawful completion?
Practitioners now deal with this by drafting the new application so that it either replaces the earlier permission for a defined area or is expressed as a variation of the original scheme as a whole. Get that wrong on a site with 10 years of build programme in front of it and the consequences land on your funder, not the planning officer. Understanding your scheme's lead-in time from permission to first completion helps size how much of this risk you are carrying.
Keeping the record
Evidence of implementation is the asset. Keep dated photographs with a visible reference point, the setting out records, the contractor's day sheets and invoices, the commencement notice and its acknowledgement, and the discharge decisions for every pre-commencement condition.
Where the position is contested or a lender needs certainty, apply for a certificate of lawfulness of existing use or development under section 191 of the 1990 Act. It is the only formal way to confirm that what was done was lawful implementation, and it is far less expensive to obtain while the people who did the work are still contactable.
If you are rebuilding an evidence base for a fresh application, the full list of report types by category is a quicker way to scope it than working from an old validation list, since requirements have moved. Enter your postcode on PlanScope to see which reports the site is likely to need now.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
How long does planning permission last in England?
A full permission must normally be begun within three years of the grant under section 91 of the Town and Country Planning Act 1990. Outline permission runs to two deadlines under section 92: reserved matters within three years, then a start within two years of the final approval. Authorities can impose shorter periods, so read the condition on your decision notice.
Can I extend the time limit on an existing planning permission?
No. Section 73 of the 1990 Act cannot be used to extend the period within which development must begin or reserved matters must be submitted, and the temporary extension procedure introduced during the last downturn no longer runs. If a permission is about to expire, the realistic choices are to make a lawful material start or to submit a fresh application.
What is the smallest amount of work that keeps a permission alive?
Section 56(4) lists the qualifying operations, and digging a foundation trench is the usual route. Volume matters less than accuracy. The work has to be in the approved position, carried out in accordance with the permission, done after every pre-commencement condition is discharged, and documented well enough to prove years later.
Does a breach of condition stop the permission being implemented?
Where the condition is a condition precedent, yes. The courts have held that work carried out before such a condition is discharged is not lawful implementation, so the clock keeps running. Treat the discharge of pre-commencement conditions as the real deadline and work backwards from the expiry date to allow for the eight week determination period.
How do I prove a permission was implemented?
Keep dated photographs against a fixed reference point, setting out records, contractor day sheets, invoices, the Community Infrastructure Levy commencement notice and the discharge decisions for each pre-commencement condition. For certainty, apply for a certificate of lawfulness of existing use or development under section 191 of the 1990 Act while the people involved are still contactable.