Farm anaerobic digestion: feedstock and traffic evidence

7 min readBy PlanScope Editorial Team

The feedstock table decides how a farm anaerobic digestion application is characterised, and the lane network decides whether it is acceptable. Both need real evidence.

The first question on a farm anaerobic digestion application is whether the use is still agriculture in planning terms. Appearance comes later. A digester fed from the holding, returning digestate to the same land, sits close to agriculture. One importing feedstock from thirty miles away and exporting gas to the grid is an industrial or waste use, wherever it happens to stand.

Councils decide that question on the feedstock catchment evidence, and applicants who treat it as a formality lose control of the whole application.

Agricultural or industrial in planning terms

Section 336 of the Town and Country Planning Act 1990 defines agriculture, and development reasonably necessary for the purposes of agriculture on a holding is treated differently from a commercial energy installation.

Three factors tip the balance:

  • Where the feedstock comes from. Predominantly from the holding points towards agriculture. Substantial imports from other farms or from food processors point away.
  • Where the output goes. Digestate spread on the holding is agricultural. Gas or electricity sold into the grid at scale is not, though a modest export does not by itself change the character.
  • The scale of the plant relative to the farm. A digester sized to the slurry of the resident herd reads differently from one sized to the local maize market.

Permitted development rarely helps. Part 6 of Schedule 2 to the GPDO 2015 covers agricultural buildings on units of 5 hectares or more, with prior approval for siting, design and external appearance, subject to floorspace limits. A small slurry digester serving the holding is occasionally argued through it. A commercial plant with clamps, tanks, a gas upgrading skid and a weighbridge is not, and trying it usually costs six months.

Say plainly in the Planning Statement which characterisation you are arguing for and why. Officers are far more receptive to an honest description of an industrial use in a rural location than to an agricultural label that does not survive the first question.

Feedstock catchment and the evidence to produce

This is the heart of the application, and it should be a table rather than a paragraph.

For each feedstock give the material, the annual tonnage, the origin by farm or supplier, the road distance, the number of vehicle movements it generates and the months of the year it arrives. Total it. Then show the proportion arising on the holding and the proportion imported.

Back it with the supply agreements or heads of terms, redacted for price if necessary. A statement that feedstock will come "mainly from the local area" is worth nothing, and the council will condition a restriction anyway, so you may as well write the restriction you can live with.

Two practical points. Maize and wholecrop arrive in a short harvest window, which concentrates traffic into a few weeks rather than spreading it. And the mix changes over the life of the plant, so build headroom into any tonnage condition or you will be back with a section 73 application in three years.

Traffic, and the lanes the traffic uses

Plant of this kind generates articulated deliveries, tractor and trailer movements, digestate tankers and occasional abnormal loads during construction.

The highway authority will look at the route from the strategic network to the site, not just the access. Single track lanes with passing places, a hump-backed bridge, a village street with no footway and a school on it, all feature more often in the refusal reasons than the access itself does.

A Transport Statement is usually the right document at farm scale, with a full assessment where movement numbers are high. It should give the daily and peak-week movement profile by vehicle type, the routing strategy, swept path drawings for the largest vehicle at the access and at any pinch point, and visibility splays measured on site rather than taken from a drawing.

Offer routing as a condition, with a written routing agreement and a driver briefing. Councils accept those where the operator can show who enforces them.

Digestate, odour and the permit

Digestate storage is sized in months, not litres. Where the holding lies in a nitrate vulnerable zone, the storage period required by the rules governing organic manures applies, and that usually means several months of covered capacity.

Cover it. An open lagoon or an uncovered tank is the single biggest source of odour complaints from these plants, and a cover also reduces ammonia loss and rainfall dilution. The visual consequence is a taller structure, which brings the landscape question forward.

On the regulatory side, a plant treating waste feedstock needs an environmental permit from the Environment Agency, and standard rules permits exist for anaerobic digestion. Plants using only crops and manures from the holding may follow a different route. Establish which applies before you fix the feedstock list, because the answer changes the planning description of development.

Odour is dual-regulated in the same way ammonia is. The permit controls the operation, and the council still has to be satisfied that the use is acceptable in its location. An Odour Assessment covering the clamps, the reception area, the digestate store and the emergency flare is what answers that. Councils expect a suitably qualified author and professional review is strongly advised. The interaction between scale, odour and screening plays out much as it does for poultry units.

Landscape, and what the tanks actually look like

Digester tanks, gas domes and silage clamps are large, pale and geometric, and they sit in landscapes that have nothing else like them. A flare stack adds a vertical element visible at night.

Handle it directly. A Landscape and Visual Impact Assessment with winter viewpoints, photomontages from the nearest public rights of way and a section through the site against the existing farm buildings does more than any amount of text about screening. Grouping the plant with the existing farmstead, rather than putting it in a clean field for construction convenience, is usually the single most effective mitigation.

Colour matters more than people expect. A dark recessive finish on tanks and cladding changes how the group reads from a distance, and it costs almost nothing at specification stage.

Grid connection and the things it drags in

The connection is a planning matter even when it is someone else's.

An electrical connection may run for kilometres to reach a suitable point, and the cable route crosses land, hedgerows, watercourses and possibly archaeology. Works by a statutory undertaker have their own permitted development rights, so the cable may not need permission, but the trenching still affects hedgerows and protected species and it still has to be programmed.

Gas to grid needs an entry unit, a propane injection facility in many cases, and a kiosk near the main. Show the connection point and the route on the application drawings even where consent for them is not being sought, because a scheme whose connection is undeliverable is a scheme that will not be built.

Illustrative example. A 500 kilowatt plant on a 240 hectare arable and dairy holding proposes 60 per cent of feedstock from the farm, 30 per cent from two neighbouring farms within four miles and 10 per cent imported. The council conditions the tonnage and the origin, restricts deliveries to weekdays between 07:00 and 18:00, requires a routing agreement, and requires the digestate store to be covered. The figures are illustrative.

Conditions to expect, and to draft first

Councils commonly condition feedstock type and tonnage, the proportion arising off the holding, delivery hours, vehicle routing, an odour management plan, a landscape and ecological management plan, external colour finishes, lighting, and restoration of the site if the plant ceases operating.

Draft your own versions and offer them. A condition you have written is one you can comply with, and a restriction on feedstock origin that you proposed is far easier to vary later than one imposed against your objection. Broader diversification questions, including where the line sits between farming and a separate business use, are covered in the piece on farm diversification into workshops and offices.

This is general guidance, not legal advice. Check the position with your local planning authority, the Environment Agency or a qualified professional before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is an anaerobic digester agricultural development?

It depends on where the feedstock comes from, where the output goes and the scale of the plant relative to the holding. A digester fed from the farm and returning digestate to the same land sits close to agriculture. One importing substantial feedstock and exporting gas commercially is an industrial or waste use wherever it stands.

Can a digester be built under agricultural permitted development?

Rarely. Part 6 of Schedule 2 to the GPDO 2015 covers agricultural buildings on units of 5 hectares or more, with prior approval and floorspace limits. A small slurry digester serving the holding is occasionally argued through it, but a commercial plant with clamps, tanks, gas upgrading and a weighbridge needs full planning permission.

What feedstock evidence does a council expect?

A table giving each material, its annual tonnage, its origin by farm or supplier, the road distance, the vehicle movements it generates and the months it arrives, with the proportion from the holding totalled. Supply agreements or heads of terms should back it, redacted for price where commercially sensitive.

How much digestate storage is needed?

Storage is sized in months rather than volume alone, and where the holding lies in a nitrate vulnerable zone the required storage period for organic manures applies. Cover the store: an open lagoon is the main source of odour complaints, and covering also reduces ammonia loss and stops rainfall diluting the material.

Does the plant need an environmental permit?

A plant treating waste feedstock needs one from the Environment Agency, and standard rules permits exist for anaerobic digestion. Plants using only crops and manures from the holding may follow a different route. Settle which applies before fixing the feedstock list, because the answer changes how the development is described in the application.

Sources and further reading

anaerobic digestionfarm diversificationfeedstockdigestateruralodour

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Rural and Agricultural

View all →
Rural and Agricultural7 min read

Succession, tenancies and who applies for permission

Planning permission runs with the land, so a tenant, a landlord or a promoter can all apply over the same field. The safeguard is the ownership certificate and the 21 day notice to agricultural tenants.

Read article →
Rural and Agricultural8 min read

Redundant farm buildings and the demolition question

Most standalone agricultural buildings can be demolished without a planning application, yet demolition removes any later conversion right and brings asbestos, ecology and restoration duties with it.

Read article →
Rural and Agricultural7 min read

Diversifying into events in a working farmyard

Part 4 of the General Permitted Development Order allows 28 days of temporary use a year on land, but excludes buildings and anything inside a curtilage. Where that leaves farm events, and the evidence a permanent consent needs.

Read article →
Rural and Agricultural8 min read

Visibility splays onto a rural lane

A speed survey comes before the drawing. How visibility splays are derived on an unclassified lane, how to measure them, and the land control problem nobody plans for.

Read article →
Rural and Agricultural7 min read

Re-using a rural building in the Green Belt

Two limbs decide a Green Belt conversion: permanent and substantial construction, and preserving openness. Most applications satisfy the first and lose on the curtilage.

Read article →
Rural and Agricultural7 min read

Livestock buildings and the distance to housing

The only fixed figure is the 400 metre permitted development limit. Beyond that, odour modelling, ventilation design and manure management decide what separation is acceptable.

Read article →