Fees for discharging planning conditions, explained

6 min readBy PlanScope Editorial Team

One fee covers any number of conditions on the same permission, so how you group them decides the bill. Where splitting requests is worth paying twice for.

The discharge of conditions fee in England is charged per request, not per condition, and it is set by the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012. There is one rate for conditions attached to a householder permission and a higher rate for everything else. Because the charge attaches to the request rather than the condition, the way you group conditions changes the bill, and on a scheme with fifteen conditions that difference is real money on a job that was probably quoted as a fixed fee.

What the fee actually buys

The formal name is an application for approval of details reserved by condition, and it is made under Article 27 of the Town and Country Planning (Development Management Procedure) (England) Order 2015. You submit the information a condition requires, the authority considers it, and it issues a decision confirming that the condition has been discharged in whole or in part.

That decision is a document you will need again. Purchasers' solicitors ask for the discharge notices on every pre-commencement condition, and a building control body or a warranty provider may want to see them. A verbal confirmation from a case officer is worth nothing at that point.

Partial discharge is normal and useful. Where a condition asks for three things and you can only evidence two, ask the officer to discharge in part and say so on the covering form, rather than waiting until the whole package is ready.

How the charge is worked out

The regulations set a flat sum for each request for confirmation of compliance. One request may cover any number of conditions on the same permission. The rate is lower where the conditions sit on a permission for householder development, and higher for all other development, including minor commercial schemes and single new dwellings.

Fees changed in December 2023 and have been subject to annual indexation since April 2025, so the figures move. Read the current amounts from the fee guidance on GOV.UK or the Planning Portal's fee calculator on the day you submit, rather than from a spreadsheet that has been on the office server since the last project.

Two points catch people out. The fee attaches to the permission, so where a scheme has an original permission and a later section 73 permission, conditions on each are separate requests with separate fees. And the free-go concession that lets you resubmit a refused planning application without charge does not apply here, because it is written for applications for permission rather than for requests under Article 27.

Grouping conditions, and when to stop

The obvious move is to submit every condition in one request and pay once. It is usually right, and it is what most practices do.

It is wrong in two situations. The first is where one condition depends on information you will not have for months, such as a contamination verification report or a materials sample that has to come from a specialist supplier. Holding the whole bundle back to save one fee can stall a start on site. The second is where the conditions belong to different consultees. A drainage condition sits with the lead local flood authority, a highways condition with the county, and an ecology condition with the council's own officer or an external adviser. Grouping them means the slowest consultee sets the pace for all of them.

A middle course works well on larger schemes. Submit the pre-commencement conditions in one request, early, and the pre-occupation conditions in a second request later. Two fees, a clean audit trail, and no risk of the roof covering condition delaying the ground works.

The clock, and deemed discharge

The authority is expected to determine a request within eight weeks of receipt, or a longer period agreed in writing. In practice these requests are often handled more quickly than a planning application, because the officer is checking a document against a condition rather than reassessing a scheme.

Where an authority does not respond, section 74A of the Town and Country Planning Act 1990 allows certain conditions to be treated as discharged. The applicant serves a deemed discharge notice, and if the authority still does not decide, the condition is deemed discharged after the period set in the DMPO. It is a narrow route. Conditions on development that was subject to environmental impact assessment, conditions requiring an agreement under section 106, conditions relating to contaminated land and several other categories are excluded, and the list sits in Schedule 6 to the 2015 Order. Read it before you rely on the mechanism.

Beware the Whitley principle while you wait. Starting work in breach of a genuine pre-commencement condition can mean the operation is not a lawful commencement at all, which matters when the permission is close to expiry.

When another application is the better-value route

Not every problem with a condition is solved by discharging it. Where the condition itself is unreasonable, imprecise or no longer necessary, an application under section 73 to vary or remove it may cost less over the life of the project than repeated attempts to satisfy wording that cannot be satisfied. Where the drawings have moved on slightly, a non-material amendment under section 96A carries a low flat fee and can remove the mismatch between the approved plans and the details you are about to submit.

Budget for the documents themselves as well as the fee. A condition requiring a construction management plan means someone has to write a Construction Management Plan, and on a constrained urban site that is a document with real content in it, covering deliveries, wheel washing, working hours and neighbour liaison. The same is true of landscape schemes, lighting details and biodiversity management plans. The Article 27 fee is often the smallest line in the discharge budget.

Putting a number on it at the fee-proposal stage

Architects and agents who lose money on condition discharge normally lose it by treating it as an afterthought at the end of a project. A simple approach avoids that.

  1. Read the decision notice on the day it arrives and split the conditions into pre-commencement, pre-occupation and in-perpetuity.
  2. Count the number of requests you realistically need, allowing for consultee groupings, and multiply by the current rate.
  3. List the conditions that require a document rather than a drawing, and price those separately.
  4. Add a contingency for one resubmission, because officers do ask for more information.
  5. Put the total in the appointment before the client asks what the extra invoice is for.

Where the documents themselves are the cost driver, drafting them in-house changes the arithmetic. PlanScope charges £50 per report on pay per report, and £150 per month or £600 per year on the Professional tier for architects, planning agents and consultants, which includes unlimited reports, removal of PlanScope branding and your own logo. See PlanScope pricing for the current tiers, and the full list of report types for what can be drafted.

This is general guidance rather than legal advice. Fees change, and the position on any particular condition should be checked with your local planning authority or a qualified professional before you rely on it.

Start with your postcode on PlanScope to see which documents a condition discharge is likely to need. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is the discharge of conditions fee charged per condition?

No. Under the Fees Regulations 2012 the charge is a flat sum for each request for confirmation of compliance, and one request can cover any number of conditions on the same permission. There is a lower rate for conditions on a householder permission and a higher rate for all other development, with amounts indexed annually.

Do I pay again if the council asks for more information?

You do not pay again to supply further information within the same live request, but a fresh request after a refusal to discharge attracts a new fee. The free-go concession for resubmitted planning applications does not extend to requests under Article 27 of the Development Management Procedure Order, so build one resubmission into the budget.

How long does a council have to decide a discharge request?

The expectation is eight weeks from receipt, or a longer period agreed in writing. Section 74A of the Town and Country Planning Act 1990 allows some conditions to be deemed discharged where the authority does not decide, but the excluded categories in Schedule 6 to the 2015 Order are wide and include environmental impact assessment development and contaminated land.

Should I submit all my conditions in one request?

Usually yes, because one fee covers the lot. Split them where a condition depends on information that will take months, or where conditions sit with different consultees such as the lead local flood authority and the county highways team. Grouping means the slowest consultee sets the pace for every condition in the bundle.

Can a condition be removed instead of discharged?

Yes. An application under section 73 of the Town and Country Planning Act 1990 can vary or remove a condition, and section 96A covers non-material amendments to approved plans. Where a condition is imprecise or no longer necessary, those routes can cost less over a project than repeated attempts to satisfy wording that cannot be met.

Sources and further reading

planning conditionsplanning feesdischarge of conditionssection 73architects

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

How a Grampian condition affects finance drawdown

The cost is almost never the off-site works themselves. It is the carry between holding a permission and holding one you can lawfully implement.

Read article →
Costs, Fees and Budgeting7 min read

Licences to occupy the highway during construction

Highway occupation charges accrue whether or not work is happening, and they sit outside the planning fee and the building control charge. On an urban site they run for the whole programme.

Read article →
Costs, Fees and Budgeting7 min read

Commuted sums for open space maintenance explained

Councils price open space maintenance as area by annual rate by commutation period, then ask for it as a lump sum in the section 106 agreement. Here is how the figure is built and how the drafting changes what you pay.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a public exhibition for a major scheme

An exhibition that produces a photograph of a full room and no analysis has spent money without buying anything. The budget should follow what the statement has to prove.

Read article →
Costs, Fees and Budgeting8 min read

Certificate C and D: notice and advertising costs

Certificates C and D are the only ownership certificates that require advertising, and the newspaper notice decides your submission date rather than the other way round.

Read article →
Costs, Fees and Budgeting9 min read

Nutrient credits and what drives their price

A nutrient credit buys a legally secured, monitored reduction held for the lifetime of your development in the same catchment. Price follows from land value, duration and the budget calculation.

Read article →