Fire statement content: the plans and the narrative

7 min readBy PlanScope Editorial Team

A Gateway One fire statement answers what planning can determine: layout, appliance access, water supply, the escape strategy in principle and the construction phase. The detailed design belongs at Gateway Two.

A fire statement at Planning Gateway One has to answer the fire safety questions that planning can actually determine: site layout, access for fire appliances, water supplies for firefighting, the escape strategy in principle, and the construction phase. Fire statement content is set by the published form, which is a prescribed form rather than a free narrative, and the Health and Safety Executive reads it as the statutory consultee. Everything that belongs to detailed design, from cavity barriers to sprinkler head spacing, belongs at the later gateways.

The threshold catches relevant buildings: those containing two or more dwellings, or educational accommodation, with seven or more storeys or a height of 18 metres or more. Article 9A of the Development Management Procedure Order 2015 is the provision that requires the statement, in force since 1 August 2021.

What the statement must address at planning stage

The form asks for the principles, concepts and approach to fire safety, and then works through a defined set of headings. The ones that carry the most weight at planning stage are:

  • Site layout and the relationship of the building to its boundaries and to neighbouring structures.
  • Emergency vehicle access, including the route from the public highway, hardstanding positions and turning provision.
  • Water supplies for firefighting, covering hydrant positions and available flow.
  • Means of escape for all occupants, including disabled occupants, and the evacuation strategy adopted.
  • Passive and active measures in outline, and the approach to limiting external and internal fire spread.
  • Facilities provided for the fire and rescue service.
  • Fire safety during construction.
  • Arrangements for ongoing maintenance and monitoring of the measures described.

Answer each heading in terms the planning decision can act on. Where the answer is a dimension, give the dimension. Where it is a strategy, name the strategy. A statement that says access will comply with the relevant standard tells the consultee nothing it can check.

Plans and drawings that accompany it

The statement is only as good as the drawings behind it. Submit, as a minimum:

  1. A site plan showing appliance access routes from the adopted highway, with widths, gradients and turning circles dimensioned and the swept path of the relevant appliance drawn.
  2. Hardstanding positions marked against the building, with the distance from the standing position to the furthest point of the building and to the dry or wet riser inlet.
  3. Hydrant positions, existing and proposed, with distances from the building entrances.
  4. Typical floor plans showing stair cores, lobbies, the firefighting shaft and the location of lifts, with escape routes indicated.
  5. A section through the building giving the height to the finished floor level of the top storey, measured from the ground level, so the threshold calculation can be checked.
  6. A roof plan where there is plant, a terrace or any occupied level above the top storey.

That last point catches people. Height for the purposes of the threshold is measured to the floor surface of the top storey, and rooftop plant is normally excluded, so a building that looks over 18 metres may not be a relevant building and one that looks under it may be. Draw the dimension and state the datum.

Access and water supply narrative

The access narrative needs to be written from the appliance outwards, not from the building. Start with the route a pump takes off the highway, identify any gate, barrier, bollard or crossover on that route, and say who holds the key or the override. Then state the standing position and how far it is from the riser inlet.

Water supply is the item most often thin. Hydrant provision is a matter for the fire and rescue service and the water undertaker, so the honest position at planning stage is often that existing hydrants have been located, available flow has been requested from the undertaker, and additional hydrants will be provided where the flow is inadequate. Say that, name the undertaker, and give the date of the enquiry.

Where the site has a private access road or a shared courtyard, the long-term legal arrangement for keeping that route clear matters as much as its geometry. An access route that becomes a parking area within two years of occupation is a real failure mode.

Building design and the evacuation strategy

Name the evacuation strategy and justify it. For most residential buildings at this height the strategy is stay put, supported by compartmentation, a single or multiple stair arrangement and a firefighting shaft. Where simultaneous or phased evacuation is proposed instead, the consequences for stair capacity, alarm provision and management need to be set out, because they affect the planning form of the building.

Two matters sit squarely in planning rather than in building control. The first is the number and position of stair cores, because that is a plan decision that cannot be unwound at Gateway Two. The second is external wall build-up in principle, because material and finish are matters the planning authority determines on appearance as well as safety.

Structural fire protection and loading interact with the frame, so where the scheme adds storeys to an existing building the structural evidence and the fire strategy have to be written together. The Structural Survey and the fire documents should not reach different conclusions about the frame.

Matters properly left to later gateways

Gateway Two sits before construction and is where the detailed design is assessed by the Building Safety Regulator. Gateway Three sits at completion. A planning stage statement that attempts the detailed design invites comments it cannot resolve and creates a document the applicant will have to contradict later.

So leave out cavity barrier details, specific product selections, sprinkler and detection design, fire door specifications and compartmentation drawings. Reference them as matters for the later gateways and move on. A short paragraph saying which items are reserved and to which gateway is a sign of a competent statement rather than an omission.

The deeper strategy document, a Fire Safety Strategy written to the relevant British Standard, is the vehicle for that detail, and it is a fire engineering document in its own right.

Author competence and the declaration

The form asks who prepared the statement and what their competence is. Give the name, the organisation, the professional membership and a short statement of relevant experience with buildings of this type. Fire engineering competence is a legal requirement here rather than a preference: the statement supports a decision under the Building Safety Act 2022 framework, and a licensed or competent professional is legally required for this document. An AI-assisted draft is a starting point for that professional, never a substitute.

Where a building sits just under the threshold, the temptation is to submit nothing. The reasoning for and against that is set out in the note on fire evidence for a building just below the threshold.

How the regulator responds

HSE as the Gateway One consultee reviews the statement and returns comments to the planning authority within the consultation period. The comments are advice to the authority rather than an approval, and they commonly ask for specific items: a dimensioned access plan, confirmation of hydrant flow, or clarity on the evacuation strategy.

Answering those requests well is largely a matter of having drawn the information in the first place. Where escape from below ground accommodation is involved, the reasoning in the note on safe egress from habitable basement rooms applies in the same way.

Draft the supporting documents for a relevant building on PlanScope, then send the fire statement to a competent fire engineer for review and sign-off before submission.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

Which applications need a fire statement?

Article 9A of the Development Management Procedure Order 2015 requires one for applications involving a relevant building: one containing two or more dwellings, or educational accommodation, with seven or more storeys or a height of 18 metres or more. The requirement has applied since 1 August 2021 and the statement is made on the published prescribed form.

How is the 18 metre height measured?

To the floor surface of the top storey, measured from ground level, with rooftop plant normally excluded. That means a building which looks taller than 18 metres may not be a relevant building, and one which looks shorter may be. Draw the dimension on a section, state the datum used, and let the consultee check the figure.

Who can write a fire statement?

Someone with the necessary fire engineering competence. The form asks for the author's name, organisation, professional membership and relevant experience. Because the statement supports a decision within the Building Safety Act 2022 framework, a competent professional is legally required, and any AI-assisted draft is a starting point for that professional rather than a substitute.

What should be left out of a fire statement?

Detailed design that belongs to Gateway Two: cavity barrier details, product selections, sprinkler and detection design, fire door specifications and compartmentation drawings. Note which items are reserved and to which gateway. Including them invites comments the planning process cannot resolve and creates statements the applicant later has to contradict.

Does the Health and Safety Executive approve the statement?

No. HSE is the statutory consultee at Planning Gateway One and returns comments to the planning authority within the consultation period. Those comments are advice to the decision maker, not an approval. They commonly ask for a dimensioned access plan, confirmation of available hydrant flow, or clarity on the evacuation strategy.

Sources and further reading

fire statementgateway onebuilding safety acthsehigh riseevacuation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements6 min read

External wall information at Planning Gateway One

The planning-stage question on external walls is narrower than full compliance: can the building as drawn be built within the restrictions that apply to it. What to state, and how to keep conditions workable.

Read article →
Fire, Structural and Basements7 min read

Sequencing site investigation before an application

Ground investigation after the design is fixed tells you what went wrong. The order that works, what the desk study should assemble, and why monitoring sets the submission date.

Read article →
Fire, Structural and Basements7 min read

Geotechnical assessment and Eurocode 7 in planning

Planning needs feasibility and risk, not a finished foundation design. How Eurocode 7 and BS 5930 shape the investigation, and how to split the deliverables between planning and construction.

Read article →
Fire, Structural and Basements8 min read

Party wall and planning overlap for basement works

Planning permission does not authorise excavation next to a neighbour, and a party wall award does not authorise development. On a basement the notice periods are fixed by statute and usually decide the programme.

Read article →
Fire, Structural and Basements7 min read

Common basement policy restrictions in London boroughs

London basement schemes are governed by the borough's adopted local plan rather than national policy. The limits on depth, garden coverage and light wells follow a consistent pattern even though the numbers differ.

Read article →
Fire, Structural and Basements7 min read

Fire Statement for a change of use application

Converting an office block over 18m into flats creates a relevant building and triggers the article 9A Fire Statement requirement, even with no external alteration. The fire issues on a conversion are inherited rather than designed.

Read article →