Fire, Structural and Basements

Fire statements for the conversion of an existing block

8 min readBy PlanScope Editorial Team

On a conversion you are describing a building nobody has seen inside since it was built. What to survey, which existing constraints shape the strategy, and how to present residual uncertainty.

A fire statement for an existing building conversion is a harder document than one for a new build, and the reason is simple: on a new build you know what you are specifying, and on a conversion you are describing a building whose construction nobody has seen since it was finished. The Building Safety Regulator will read your statement knowing that, and the submissions that work are the ones that say plainly what has been surveyed, what has been assumed and what will be opened up before the next gateway.

The submissions that fail are the ones that describe the existing block with the same confidence as a new design.

Whether a conversion engages the duty

The Gateway One consultation duty in Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015 covers development involving a relevant building, which includes work to an existing one. A relevant building contains two or more dwellings or educational accommodation and has at least seven storeys or is at least 18 m high.

Three conversion scenarios engage it, and one of them surprises people.

An existing residential block above the threshold being refurbished or extended engages the duty straightforwardly. A building that is pushed over the threshold by the proposal, typically by added storeys, engages it from the moment the proposal is drawn. And an existing non-residential building above the threshold, such as an office block, being converted to flats engages the duty even though it contains no dwellings today, because the relevant building is the one that will exist.

That third case is the one that catches office-to-residential schemes. Measure the height from existing ground level to the floor surface of the proposed top storey, excluding storeys that will consist exclusively of plant, and do it before the design is fixed.

Where a conversion proceeds by prior approval rather than by planning application, the consultation duty operates differently and the position should be confirmed with the authority at the outset. The building control gateways under the Building Safety Act 2022 apply either way, so nothing is avoided by the route chosen.

Surveying what the building actually is

Record drawings are a starting point and not evidence. Buildings of the relevant era were altered, re-serviced, re-clad and sub-divided, often without a trace in the building control file.

The survey questions that the fire statement depends on are these. What is the structural frame and what is its fire protection. Where is the compartmentation and is it continuous, particularly at floor junctions and around risers. How are services penetrating compartment walls and floors sealed. What is the stair enclosure built from and how is it ventilated. What is the external wall build-up, layer by layer. Where are the cavity barriers, if any.

None of those can be answered by inspection from a corridor. They need opening up, which means a programme of intrusive investigation, access agreements with existing occupiers if the building is tenanted, and making good. Budget it and programme it, because it takes weeks and it frequently changes the scheme.

A structural appraisal runs alongside the fire survey and uses much of the same access. Commission them together. The structural survey and the fire investigation both want the same ceilings down, and doing them in sequence doubles the disruption for no benefit.

Constraints the existing structure imposes

The existing building limits the fire strategy in ways a new build does not, and the statement should name the constraints rather than designing around them silently.

Floor-to-floor height constrains the depth available for services, which constrains how smoke control ductwork can be routed. Existing core positions constrain travel distances, and a core that served an open-plan office at 20 m centres may not serve a residential layout at all. Structural capacity constrains what can be added. Existing risers may be too small for a firefighting shaft of the required dimensions, and enlarging a riser through every floor plate is a structural operation.

Existing constraint What it limits Typical consequence
Floor-to-floor height Service zone depth Smoke control routing, ceiling heights
Core position and size Travel distances, shaft dimensions Unit layout, net to gross
Floor plate structure Added loads, new openings Feasibility of a new stair or riser
Existing stair width Escape capacity Occupancy limits per floor
Window and opening positions Smoke ventilation, external spread Facade alterations needing consent

Each of those is a planning issue as well as a fire engineering one, because resolving it usually means altering the external envelope, and altering the envelope is what the planning permission controls. That is the reason the fire statement has to be developed with the planning drawings rather than after them.

Single stair buildings and the conversion question

Many existing blocks above 18 m have a single staircase, built to the standards of their day. Government has announced an expectation of a second staircase in new residential buildings above 18 m, with the detail delivered through the statutory guidance and with transitional arrangements.

How that expectation applies to the conversion of an existing building is the question to settle first, and it is one to settle with the Regulator and the building control body rather than to assume. As at the date of this article the position on existing buildings has continued to develop, so verify it against the current published guidance before the design is committed.

What is clear either way is the design consequence. Inserting a second stair into an existing frame costs floor area on every level, needs new openings in every floor plate, and often forces a change to the core position that ripples through the whole layout. If there is any prospect of it being required, test the layout with and without it at feasibility stage. Discovering the requirement after planning permission means a fresh application, not a variation.

External wall construction in an existing block

The external wall is where conversion schemes most often stall. For relevant buildings, the restriction on combustible materials in external walls introduced into the Building Regulations in 2018 governs what can be in the wall, and the practical question on an existing block is what is in it already.

A fire risk appraisal of the external wall construction, carried out to the code of practice published for that purpose, is the recognised route to understanding an existing facade. It requires intrusive opening up at a sufficient number of locations to characterise the build-up, including the insulation, the cavity arrangement and the cavity barriers.

Three outcomes are possible and all three need a planning answer. The wall may be acceptable as it stands, in which case say so and reference the appraisal. It may need remediation, in which case the remediation is external work that the planning application should include rather than leave to a later application. Or it may need replacement, in which case the elevations change and the planning submission is a different scheme.

Balconies deserve separate attention. Existing balconies on a converted block are a known route for external fire spread and their construction is often undocumented, so they belong in the opening-up programme.

Evidence where the records have gone

Record searches are worth more effort than most teams give them. Try the local authority building control file, which may hold the original approved drawings. Try the authority's planning file, which often holds elevations and sections not kept elsewhere. Try the original design practice if it still exists. Try the asbestos survey archive, because an intrusive asbestos survey records construction details incidentally.

Where the records cannot be found, say so and describe the search carried out. A statement that lists the archives searched and the dates searched is credible. One that simply asserts the construction is unknown is not.

The documentation held on a planning file also matters for the long-term record, and the question of what the planning file should hold on structural warranties applies to fire documentation in exactly the same way.

Presenting residual uncertainty honestly

This is the part that separates a statement that passes Gateway One from one that does not.

State the survey work completed, with dates and locations. State the assumptions made and why each one is reasonable. State the further investigation programmed before the building control application, with what it will test. And state what the design would need to change to if an assumption proves wrong, at least in outline.

A reviewer reading that has something to assess. A reviewer reading a confident description of an unsurveyed wall has nothing to assess and will say so.

The full fire engineering work belongs in the fire safety strategy prepared to BS 9991 or BS 9999, not in the planning-stage statement, and what the planning-stage document covers is set out on the fire statement page. A Fire Statement is a report type where a professional with the necessary fire engineering competence is legally required, and an AI-assisted draft is a starting point for that professional rather than a substitute.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required. You can enter the building postcode to see which fire and structural reports a conversion is likely to need.

Frequently asked questions

Does converting an office block to flats engage Gateway One?

Yes, where the resulting building will contain two or more dwellings and has at least seven storeys or is at least 18 m high. The relevant building is the one that will exist, not the one that exists today. Measure from existing ground level to the floor surface of the proposed top storey, excluding plant-only storeys.

Are record drawings enough for a fire statement?

No. Buildings of the relevant era were altered, re-serviced, re-clad and sub-divided, often without a trace in the building control file. The statement depends on answers about the frame, its protection, compartmentation continuity, service penetrations, stair enclosure and external wall build-up, and those need intrusive opening up.

Do existing single stair buildings need a second staircase on conversion?

Government has announced an expectation of a second staircase in new residential buildings above 18 m, delivered through statutory guidance with transitional arrangements. How it applies to conversions of existing buildings is a question to settle with the Regulator and the building control body, and the current published guidance should be checked.

How is an existing external wall assessed?

Through a fire risk appraisal of the external wall construction carried out to the published code of practice, with intrusive opening up at enough locations to characterise the build-up, insulation, cavity arrangement and cavity barriers. Existing balconies are a known route for external fire spread and belong in the same programme.

What if the original construction records cannot be found?

Search the authority's building control file, its planning file, the original design practice and the asbestos survey archive, which records construction details incidentally. Then state which archives were searched and when. A documented search is credible; an unexplained assertion that construction is unknown is not.

Should facade remediation be included in the planning application?

Yes, where the appraisal shows remediation is needed. Remediation is external work that the planning permission controls, so including it avoids a second application later. If the wall needs full replacement, the elevations change and what you are submitting is a materially different scheme.

Sources and further reading

fire statementconversiongateway oneexisting buildingsexternal wallsdevelopers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements6 min read

Working on a pavement vault beneath the footway

The highway authority consents cellars and vaults under a street separately from planning. Ownership of the subsoil is usually unresolved until you look.

Read article →
Fire, Structural and Basements6 min read

Basement car parks beneath residential blocks

Excavation, ventilation and a ramp buy you spaces that most urban transport policy now wants fewer of. Test the parking count against the evidence first.

Read article →
Fire, Structural and Basements7 min read

Roof terraces on tall buildings and escape provision

Amenity policy pushes communal space onto the roof of tall residential buildings. The fire strategy decides whether it can be built as drawn.

Read article →
Fire, Structural and Basements7 min read

Firefighting shafts in a single core apartment plan

The firefighting shaft is the largest fixed element on a residential floor plate. Five checks that take an hour each and decide whether the massing works.

Read article →
Fire, Structural and Basements7 min read

Bin stores, chutes and fire separation in plan

Five requirements compete for the same few square metres next to the entrance. How carrying distances, collection access and fire separation are reconciled.

Read article →
Fire, Structural and Basements7 min read

Car park ventilation and charging bays in a layout

Open-sided, naturally ventilated or mechanically ventilated is a planning-stage decision, not a technical design one. How it fixes elevations, plant and layout.

Read article →