Flood risk activity permits and the 8 metre byelaw distance
A permit under the Environmental Permitting Regulations 2016 is a separate consent from planning permission, and the 8 metre line should shape the layout from the first sketch.
If you are building, excavating or placing anything within 8 metres of the top of the bank of a main river, you need a flood risk activity permit from the Environment Agency as well as planning permission. The flood risk activity permit main river regime sits in the Environmental Permitting (England and Wales) Regulations 2016, and it is a separate consent with its own application, its own fee and its own grounds for refusal. A planning permission does not carry it, and a council cannot grant it.
The 8 metre figure is the one to remember. It applies from the top of the bank of a main river, and the same distance applies either side of a flood defence structure and either side of a culverted main river.
Which watercourses count as main rivers
Main rivers are designated and shown on the statutory main river map published by the Environment Agency. Everything else is an ordinary watercourse.
The distinction is not about size. A modest urban brook can be a main river where it carries a designated flood risk function, and a substantial field ditch can be an ordinary watercourse. Check the map rather than judging by the width of the channel.
For an ordinary watercourse the consenting body is the lead local flood authority, or an internal drainage board inside its district, under section 23 of the Land Drainage Act 1991. That is a different application with different timescales, covered in land drainage consent for works to an ordinary watercourse. Getting the two confused is the most common way a site loses six weeks.
Culverted main rivers catch people out most. A main river that has been piped beneath a car park is still a main river, and the 8 metre distance still applies to ground either side of it, even where there is nothing visible on the surface.
The 8 metre byelaw distance
Within 8 metres, the activities that need a permit cover more than building. Excavation, raising ground levels, placing a structure, planting, erecting a fence with posts, storing materials and driving plant can all require consent depending on the detail.
The reasons behind the distance are conveyance, defence integrity and access. The Environment Agency needs to be able to bring plant along the bank to maintain the channel and any defence, and it needs the floodplain and the channel to keep working hydraulically. A new building hard against the top of bank blocks all three.
| Location | Consenting body | Instrument |
|---|---|---|
| In, over, under or within 8 m of a main river | Environment Agency | Environmental Permitting Regulations 2016 |
| Within 8 m of a main river flood defence or culvert | Environment Agency | Environmental Permitting Regulations 2016 |
| In or near an ordinary watercourse | Lead local flood authority or internal drainage board | Land Drainage Act 1991 section 23 |
| On or near a sea defence | Environment Agency | Environmental Permitting Regulations 2016 |
Exclusions, exemptions and permits
The regime is tiered, which is worth knowing before you assume the worst.
- Excluded activities need nothing. These are low risk works that the regulations put outside the regime altogether.
- Exempt activities need registration with the Environment Agency rather than a permit, provided the activity meets every condition of the exemption. Registration is normally free and quick.
- Standard rules permits apply to defined activities that can be carried out to published rules. The application is simpler and the determination faster.
- Bespoke permits are needed for anything that does not fit a standard rules set, including most new buildings and most works to a defence.
Read the current published lists of exclusions and exemptions rather than relying on a precedent from an earlier scheme, because they are revised. Where an activity nearly fits an exemption but breaches one condition, the whole activity needs a permit, so check each condition individually.
Applying, and how long it takes
Applications go to the Environment Agency with drawings, a method statement, a hydraulic justification where the works affect the channel or floodplain, and the fee set out in the current environmental permitting charging scheme. The scheme is revised, so check the current figure rather than budgeting from last year's.
Determination periods differ sharply between standard rules and bespoke applications, and the Environment Agency publishes its target periods. Treat a bespoke permit as a matter of months rather than weeks, and build it into the programme at the point you fix your start on site date, not afterwards.
Two things shorten the process. A pre-application discussion with the local Environment Agency team, which is normally charged but worth it on anything touching a defence. And a method statement that already answers the maintenance access question, because that is the point on which bespoke applications are most often sent back for more information.
Flood defences and maintenance access
Where the site adjoins a raised defence, an embankment, a wall or a sheet pile line, the permit application is really about the defence rather than about your building.
The Environment Agency will want to know what loading the works impose on the defence, whether excavation could affect its stability or its seepage path, how the defence will be monitored during construction, how it will be reinstated, and how it will be reached for inspection and repair afterwards for the whole design life. An access strip clear of permanent structures, with a route for tracked plant and a hard standing to work from, is usually a condition rather than a negotiation.
Design the development to leave that strip from the first sketch. Retro-fitting an 8 metre maintenance corridor into a consented layout means losing plots.
Sequencing against the planning application
The permit and the planning permission are independent, and neither guarantees the other. The order that works in practice is this.
Establish the main river designation and the 8 metre line at the feasibility stage, before the layout is drawn. Prepare the Flood Risk Assessment with the permit requirement identified in it, so the Environment Agency's consultation response on the planning application and its permitting view are consistent. Hold a pre-application discussion covering both. Submit the planning application with the layout already respecting the byelaw distance. Then apply for the permit once the layout is settled, and before any works start.
Councils often attach a condition requiring evidence of the permit, or of the Environment Agency's confirmation that none is needed, before development begins. That condition is reasonable and easy to discharge if you have planned for it.
The permitting position also interacts with the surface water design, since an outfall into a main river is itself a permitted activity. Set out the outfall detail in the Drainage Strategy rather than leaving it to a later technical submission, because the headwall, the invert level and the scour protection are what the permit will control.
Where the development sits in the floodplain rather than only near the channel, resilience measures and safe access become part of the same conversation, and the approach to those is set out in residual flood risk and property flood resilience measures.
Where a permit will not be granted
Some proposals do not get through, and it is better to know which before you design around them.
Culverting an open watercourse faces a strong policy presumption against it, and the justification has to be more than convenience of layout. Building over an existing culvert is resisted for the same reasons of access and structural risk. Loss of floodplain storage without level for level, volume for volume compensation on the same site is normally refused, and compensation on land you do not control is not compensation. Works that obstruct conveyance in the channel, that impede access along the bank, or that put additional loading on a defence without an engineered solution will not be permitted.
One honest note. The Environment Agency's position on a specific defence depends on asset records and condition data you cannot see from outside, so the only reliable way to know whether a scheme is permittable is to ask, early, with drawings.
Browse all 66 PlanScope report types to see which flood and drainage documents a site beside a main river is likely to need.
PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is the 8 metre byelaw distance?
It is the distance from the top of the bank of a main river within which works need a flood risk activity permit from the Environment Agency. The same 8 metres applies either side of a main river flood defence structure and either side of a culverted main river, including where the channel is piped beneath a surfaced area.
How do I know whether a watercourse is a main river?
Check the statutory main river map published by the Environment Agency. Designation has nothing to do with channel width, so a small urban brook can be a main river while a large ditch is an ordinary watercourse. Ordinary watercourses are consented by the lead local flood authority or an internal drainage board instead.
Does planning permission cover the permit?
No. The two consents are independent, and neither guarantees the other. A council cannot grant a flood risk activity permit and the Environment Agency does not grant planning permission. Councils often condition evidence of the permit, or of confirmation that none is needed, before development begins.
How long does a flood risk activity permit take?
It depends on whether the activity fits a standard rules set or needs a bespoke permit. Standard rules applications are determined considerably faster. Treat a bespoke permit as a matter of months rather than weeks, check the Environment Agency's published target periods, and build it into the programme before fixing a start on site date.
Can I build over a culverted main river?
It is resisted. The reasons are access for inspection and repair, structural risk to the culvert and the consequences of failure. Culverting an open channel faces a strong presumption against it as well, and convenience of layout is not accepted as justification. Design the scheme on the assumption that the culvert corridor stays clear.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.