Greenfield runoff rate and why it sets the discharge limit
The greenfield runoff rate describes how a site would drain if nothing had been built on it. It sets the discharge ceiling under the national sustainable drainage standards, and the storage volume follows from it.
The greenfield runoff rate is the rate at which rainwater would leave a site if nothing had ever been built on it. It matters because the national technical standards for sustainable drainage use it as the ceiling: for a greenfield site, the peak rate discharged to a sewer, highway drain or watercourse should not exceed the greenfield rate for the same rainfall event. Every attenuation tank, every flow control and a good deal of the drainage budget follows from that single number, which is why it is worth understanding before a consultant hands you one.
What the rate is meant to represent
Undeveloped land absorbs, stores and slowly releases rainfall. Roofs and tarmac do not. The greenfield rate is the benchmark that describes the natural condition, and the design task is to make a developed site behave as though it were still in that state at the point of discharge.
The rate is usually expressed in litres per second, sometimes per hectare. It is estimated rather than measured, because nobody gauges a two-hectare field, and the estimate rests on catchment characteristics: area, soil type and its permeability classification, average annual rainfall, and a hydrological method.
The mean annual flood flow, often written as QBAR, is the common starting point. Longer return period rates are then derived from it using growth factors. Two consultants using different methods on the same field will not produce the same figure, which is why the method has to be stated rather than assumed.
The return periods that get assessed
Three events do most of the work in a drainage submission, and the standards address each.
The 1 in 1 year event governs the everyday condition and stops frequent small discharges scouring a watercourse. The 1 in 30 year event is the one most drainage authorities use for no-flooding-of-the-network. The 1 in 100 year event, with a climate change allowance added to the rainfall, is the design case for no flooding of property.
Climate change allowances are published by the Environment Agency by river basin district and time period, and they are revised. Use the current figures, name the allowance you applied and say which epoch it covers, because a drainage engineer reviewing the submission will check that first.
How the rate is estimated on a small site
The recognised hydrological methods were developed for catchments much larger than a housing plot, and applying them to half a hectare involves extrapolation. That is not a reason to avoid them, but it is a reason to state the assumptions.
A calculation submitted for review should show the catchment area used and whether it is the whole site or only the developed part, the soil classification and its source, the average annual rainfall figure, the method and the version, and the resulting rates for each return period.
Two arguments recur. The first is whether the rate should be calculated on the whole site or only on the area being developed, which on a large plot with a small building makes a substantial difference. The second is the minimum practical discharge. Flow control devices have a lower limit below which blockage becomes likely, commonly quoted around 2 litres per second, and where the calculated greenfield rate falls below that limit the authority has to accept a higher figure or a device it is content to maintain. Agree it rather than assume it.
Previously developed land and betterment
On a brownfield site there is no natural condition to return to, so the standards work differently. The discharge should be as close as reasonably practicable to the greenfield rate, and in any event must not exceed the existing rate for the same event.
In practice most lead local flood authorities look for betterment, a reduction against the existing positively drained rate. The percentage sought varies between authorities and is set out in local guidance rather than nationally, so check the local standard before designing the storage.
Establishing the existing rate needs evidence: a measured impermeable area from a survey or aerial imagery, the existing connection size and its recorded invert, and any historic drainage plans. An assumed existing rate based on the whole site being impermeable is the claim most often challenged.
Attenuation volume is the consequence
Lower the discharge rate and the storage volume rises, not proportionately but steeply. That relationship is the reason the rate is negotiated rather than simply accepted.
The volume has to go somewhere. On a tight urban site it becomes a tank under the car park or an oversized pipe, both of which carry cost and maintenance. On a larger site it can be a basin or a swale, which is usually less costly and delivers biodiversity and amenity alongside. Above-ground storage also gets counted in the biodiversity metric, which underground tanks do not.
So fix the rate early. Changing it after the layout is set means finding storage in a scheme that has no room for it, and that is how drainage ends up under the only area of public open space.
Agreeing the rate with the drainage authority
The lead local flood authority is the statutory consultee on surface water drainage for major development, and its drainage team will review the calculation. The sewerage undertaker has its own interest where the discharge is to a public sewer, and the Environment Agency where it is to a main river.
Get the rate agreed in principle at pre-application stage, in writing. A short technical note with the calculation and the proposed rate, sent before the layout is fixed, costs very little and settles the biggest variable in the Drainage Strategy.
Note that the sustainable drainage approval regime under Schedule 3 to the Flood and Water Management Act 2010 has not been brought into force, so approval currently runs through the planning system and the consultee arrangements rather than through a separate approving body. Check the position at the time you apply, because that change has been under discussion for some years and would add an approving body with its own timetable.
Evidence to submit
The drainage submission should let a reviewer reproduce the number without asking a question.
- The calculation output with all inputs shown, including method and version.
- A plan showing the contributing catchment area used.
- The soil classification source and the average annual rainfall figure.
- Existing impermeable area evidence where the site is previously developed.
- The proposed discharge rate for each return period, and the flow control device selected.
- The climate change allowance applied, with the epoch and the river basin district.
- Storage volume calculations following from the rate, with the critical duration identified.
Where the site is also in a flood zone, the discharge rate sits alongside the wider assessment in a Flood Risk Assessment, and the two documents must use the same climate change allowance. And if they do not, that inconsistency is the first thing a drainage officer will notice.
Browse all 66 PlanScope report types and start a draft to see which drainage and flood documents your site is likely to need.
This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
What is the greenfield runoff rate?
The rate at which rainfall would leave a site in its undeveloped state, usually expressed in litres per second. It is estimated from catchment area, soil classification, average annual rainfall and a hydrological method rather than measured. The national sustainable drainage standards use it as the ceiling for discharge from a greenfield development.
Which return periods have to be assessed?
Commonly the 1 in 1 year event for everyday discharge, the 1 in 30 year event for flooding of the drainage network, and the 1 in 100 year event with a climate change allowance for flooding of property. State which Environment Agency allowance you used, for which epoch and river basin district, because reviewers check that first.
Does the rate apply to brownfield sites?
Differently. On previously developed land the discharge should be as close as reasonably practicable to the greenfield rate and must not exceed the existing rate for the same event. Most lead local flood authorities look for betterment against the existing positively drained rate, and the percentage is set in local guidance rather than nationally.
What if the calculated rate is very small?
Flow control devices have a practical lower limit below which blockage becomes likely, often quoted around 2 litres per second. Where the greenfield rate falls below that, the authority has to accept a higher discharge or a device it is prepared to see maintained. Agree the figure with the drainage team rather than assuming it.
Who agrees the discharge rate?
The lead local flood authority is the statutory consultee on surface water drainage for major development. The sewerage undertaker has an interest where discharge is to a public sewer and the Environment Agency where it is to a main river. Get the rate agreed in principle in writing at pre-application stage, before the layout is fixed.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.