The greenfield runoff rate caps what a developed site may discharge and drives the whole attenuation design. Here is how the estimation methods work, why small sites are a problem, and how to agree the rate with the lead local flood authority.

The greenfield runoff rate calculation sets the ceiling on what your site is allowed to discharge. Every attenuation volume, every flow control device and most of the drainage cost on a development follows from that one number, and it is agreed with the lead local flood authority rather than chosen by the designer.

The principle is straightforward. Surface water leaving a developed site should not leave faster than it would have done had the site remained undeveloped fields. Establishing that undeveloped rate on a site that has not been fields for a century, or that covers two hectares when the published methods were derived from catchments of several square kilometres, is where the difficulty starts.

Why greenfield rate is the benchmark

The non-statutory technical standards for sustainable drainage systems set the expectation. For greenfield sites, the peak runoff rate to any receiving watercourse must not exceed the greenfield rate for the same rainfall event, assessed for the 1 in 1 year and the 1 in 100 year events. For previously developed sites, the rate must be as close as reasonably practicable to the greenfield rate and must not exceed the rate for the existing developed site.

Those two sentences carry most of the design. The 1 in 1 year event governs everyday performance and the behaviour of the flow control. The 1 in 100 year event, with a climate change allowance applied, governs storage volume.

Local policy sits on top. Many lead local flood authorities require a stated reduction below the existing rate on brownfield land, and some apply a minimum standard of betterment regardless. Check the authority's own published standards before assuming the national position is the whole test.

The estimation methods

Three approaches appear in practice.

Method Where it fits Main limitation
IH124 Small rural catchments, the default for most development sites Derived from catchments larger than typical development sites
FEH statistical Larger catchments with usable descriptors Needs reliable catchment descriptors, less suited to very small areas
ReFH2 Rainfall runoff modelling for larger or more complex catchments More assumptions, more scope for disagreement

IH124 remains the workhorse. It estimates the mean annual flood, usually written QBAR, from the catchment area, the standard average annual rainfall and a soil index derived from national soil mapping. Rates for other return periods follow by applying regional growth factors to QBAR.

The method was developed from gauged catchments substantially larger than a housing site. Applying it to a 1.5 hectare plot is extrapolation, and every party to the discussion knows it.

Catchment descriptors and where they come from

Three inputs dominate.

Catchment area, which for a development site is the area draining to the discharge point, not the red line boundary. Get this right first, because it is the input most often taken carelessly and it scales the whole answer.

Standard average annual rainfall, taken from national datasets for the site's location. This varies enormously across England and is the reason an identical site produces different rates in Cumbria and in Essex.

The soil index, derived from national soil and hydrology mapping, which reflects how readily the soil sheds water. Where the mapping disagrees with what the site investigation found, say so and explain which you have used and why. Infiltration testing on the site is relevant evidence here.

Record the source and date of every descriptor in the appendices. A drainage consultee who cannot reproduce your inputs will not accept your output.

Small site limitations

This is the practical heart of the subject. The published methods were not derived from sites of the size most developments occupy, and applying them directly to a very small area produces rates so low that no flow control can reliably deliver them.

The convention that has emerged is to calculate the rate for a nominal minimum area, commonly 50 hectares, and then scale the result to the actual site area. It is a pragmatic fix rather than a scientific one, and different authorities apply it differently. Ask the lead local flood authority which convention it expects before you model anything.

Be explicit in the report about which convention you used. A drainage strategy that quietly applies a scaling rule without naming it invites a challenge, and the challenge usually arrives late.

Minimum discharge rates and blockage

A calculated greenfield rate of 0.8 litres per second on a small site is arithmetically fine and physically impractical. Delivering it needs an orifice small enough to block on a leaf.

Authorities therefore usually accept a minimum controlled discharge, commonly around 5 litres per second per outfall, on the basis that anything smaller cannot be maintained reliably. Vortex flow controls can hold lower rates with a larger aperture and are widely used where the calculated rate is very low, at the cost of a more complex device and a maintenance obligation.

Whichever route, the flow control needs a maintenance regime attached to it and somebody to carry it out. Long-term responsibility for these assets is a planning question in its own right, and our note on SuDS adoption and maintenance sets out who ends up holding it.

Betterment on previously developed land

On brownfield sites the existing rate is usually far above greenfield, sometimes by an order of magnitude, because the site is largely impermeable and drains straight to a sewer.

The national standard asks for a rate as close as reasonably practicable to greenfield. In practice authorities negotiate a percentage reduction from the existing rate, and the number depends on the site constraints, the receiving system's capacity and how much space is available for storage.

Evidence the existing rate properly. That means the impermeable area from a measured survey rather than an estimate, the existing drainage arrangement including any positive connection to a sewer, and the capacity of that connection. An assumed existing rate based on the whole site being impermeable will be challenged, and rightly.

Agreeing the rate with the consultee

Do this early, in writing, and before the layout is fixed.

  1. Read the lead local flood authority's published standards and any local guidance on methods and minimum rates.
  2. Establish the discharge point and the receiving system, and confirm the water company or riparian owner position on a connection.
  3. Prepare the calculation with inputs and sources shown, and the convention used for small sites named.
  4. Submit it at pre-application rather than with the planning application, and ask for confirmation of the rate in writing.
  5. Feed the confirmed rate into the storage design, then check that the storage fits the layout before the layout is agreed.

The rate feeds directly into the Drainage Strategy and, where the site is in a flood zone or exceeds one hectare, into the Flood Risk Assessment as well. Both documents should quote the same figures and reference the same calculation. The wider expectations of the drainage consultee are set out in our guide to what the lead local flood authority checks.

One honest uncertainty: Schedule 3 of the Flood and Water Management Act 2010, which would introduce a separate SuDS approval regime in England, has been subject to repeated statements about implementation. Until it takes effect the planning route remains the mechanism, and the current position is worth checking rather than assumed, as covered in our note on where Schedule 3 SuDS approval stands.

Enter your postcode on PlanScope to see which drainage and flood documents your site is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

What is QBAR?

The mean annual flood, the flow expected on average once a year from a catchment. It is the base figure in the IH124 method, estimated from catchment area, standard average annual rainfall and a soil index. Rates for other return periods, such as the 1 in 30 or 1 in 100 year event, are derived by applying regional growth factors to it.

Which events does the discharge rate have to be checked for?

The non-statutory technical standards for sustainable drainage systems require the peak runoff rate to the receiving watercourse to be checked for the 1 in 1 year and the 1 in 100 year events. The first governs everyday performance and flow control behaviour, the second, with a climate change allowance, governs the storage volume required.

Why are small sites a problem for these methods?

The published estimation methods were derived from gauged catchments much larger than a typical development site, so applying them directly to a few hectares is extrapolation. The common convention is to calculate the rate for a nominal minimum area, often 50 hectares, and scale it to the actual site. Authorities apply that differently, so ask first.

Is there a minimum discharge rate in practice?

Yes, for maintenance reasons. A calculated rate below about 5 litres per second per outfall generally needs an orifice small enough to block easily, so authorities commonly accept around that figure as a practical minimum. Vortex flow controls can hold lower rates with a larger aperture, at the cost of complexity and a maintenance obligation.

What rate applies on a brownfield site?

The standard asks for a rate as close as reasonably practicable to the greenfield rate, and in any event no higher than the existing developed rate. Authorities usually negotiate a percentage reduction from the existing figure. Evidence the existing rate from a measured impermeable area and the actual drainage connection, not from an assumption.

Sources and further reading

greenfield runoffsudsdrainageqbarflood riskattenuation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Blue roofs in the drainage calculation

The hydraulics of roof attenuation are straightforward; getting the volume credited is not. This covers storage depth against structural loading, flow control modelling, failure modes and the drawings reviewers expect.

Read article →
Flood, Drainage and SuDS7 min read

Choosing between the central and upper end climate allowance

The Environment Agency publishes bands rather than a single climate uplift. This explains how vulnerability classification, flood zone and catchment select the allowance, and how to document the choice so a reviewer can check it.

Read article →
Flood, Drainage and SuDS8 min read

Local resilience forums and flood emergency planning

Flood emergency planning sits with local resilience forums under the Civil Contingencies Act, not with the planning system. Here is how the two meet.

Read article →
Flood, Drainage and SuDS8 min read

Sewerage design standards and sewer adoption approval

Adoptable sewers are designed to the sewerage undertaker's standards, not the council's. Here is what governs the layout, how the application runs and where the programme slips.

Read article →
Flood, Drainage and SuDS6 min read

Flood Re and what buyers will ask about

Homes built on or after 1 January 2009 cannot use Flood Re, so new build insurance rests on the open market. What to hand over at completion and what not to promise.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens and the liability they create

Screens protect a culvert and introduce a new flood risk upstream. How blockage is modelled, which designs degrade gracefully, and who maintains the structure afterwards.

Read article →