Hazardous substances consent: the fee and the triggers

6 min readBy PlanScope Editorial Team

Hazardous substances consent is separate from planning permission, with its own fee and decision maker. The trigger is presence at or above a controlled quantity, aggregated across the site.

Hazardous substances consent is needed when a hazardous substance is present at or above its controlled quantity on, over or under land, and it is a separate consent from planning permission with its own application, its own fee and its own decision maker. A restaurant with bottled gas in a rear store will not normally need it. A cold store with an ammonia charge, a plant nursery holding fertiliser, a chemical blender or a fuel depot may well.

The fee is set in regulations rather than negotiated, and it is a flat figure rather than one scaled by site area or tonnage. Check the current schedule before you budget, because the fees in this area are revised alongside the wider planning fee regulations.

The regime sits in the Planning (Hazardous Substances) Act 1990 and the Planning (Hazardous Substances) Regulations 2015. Schedule 1 to the 2015 Regulations does the work: it lists named substances and generic categories, each with a controlled quantity expressed in tonnes. Present the substance at or above that quantity and consent is required before the substance arrives.

Three points catch operators out.

The first is that the trigger is presence, not use. Storage counts. Material in transit through the site counts once it is there. The second is that consent attaches to the land, so buying a site does not automatically bring the consent with you in the way a planning permission would. The third is that the quantities are lower than people expect for some common materials, particularly oxidising agents, flammable liquids and toxic gases.

Controlled quantities and how they are counted

Counting is where most errors happen. Substances falling within the same category are aggregated across the whole of the land in the applicant's control, not assessed tank by tank. A site with four separate 8 tonne vessels of the same flammable liquid is a 32 tonne site.

There is a de minimis rule. Quantities below a small proportion of the controlled quantity may be disregarded where they are located so that they cannot act as the initiator of a major accident elsewhere on the site, which is a judgement about separation distances and bunding rather than a simple arithmetic exemption. Where different categories are present together, the Regulations set out a summation rule so that a site holding several substances each below its own threshold can still cross the line.

A short worked illustration. A distribution unit holds 12 tonnes of a Category 2 flammable liquid, 4 tonnes of an oxidising substance and a 6 tonne ammonia vessel serving a chill room. None is obviously at its own controlled quantity, but the summation rule may still bring the site into the regime, and the ammonia figure alone will be the one to check first. This example is illustrative only.

The fee and what the application must contain

The application goes to the hazardous substances authority on the prescribed form, with the fee. Content required includes the substance, the maximum quantity to be present, the manner in which it is to be kept and used, a plan of the land identifying where the substance will be, and details of the site and surrounding land.

Element Who sets it Where to check
The fee Regulations The current fees schedule on legislation.gov.uk
The form and required content Planning (Hazardous Substances) Regulations 2015 The hazardous substances authority
Consultation with the safety regulator The authority, not the applicant The authority's consultation record
Determination period Regulations Confirm at submission

Budget for the technical work rather than the fee. Establishing the maximum quantity, describing containment, and producing a site plan that a safety adviser will accept is where the cost sits, and it usually sits with a process safety consultant.

The hazardous substances authority and the safety regulator

For most sites the hazardous substances authority is the district, borough or unitary council: the same body that determines planning applications, though acting under different legislation. There are exceptions where another body takes the role, so confirm it rather than assuming.

The authority consults the Health and Safety Executive, which advises on the risk to people in the surrounding area, and the Environment Agency where the environment is in question. The safety regulator's advice on separation distances is the part that most often reshapes a scheme, because it can rule out a proposed vessel location that works perfectly well in operational terms.

Conditions, revocation and continuation

Consent may be granted with conditions, including conditions on how a substance is kept. It may also be revoked or modified by the authority, and in defined circumstances compensation is payable, which is a meaningful difference from the planning permission regime.

The one that catches buyers and tenants is continuation. Where there is a change in the person in control of all or part of the land, the consent can be revoked unless the new controller applies for the consent to continue within the period the legislation allows. Missing that window means starting again with a fresh application, and the site may be operating without consent in the meantime. On any acquisition of a site holding controlled substances, that check belongs in the first week of due diligence.

How it interacts with the planning application

The two consents are independent. You can hold planning permission for a building and still be unlawful in storing what you intend to store in it, and you can hold hazardous substances consent for a substance in a building you have no permission to erect.

In practice the sequencing works best when both applications run together, because the same site plan, the same containment description and the same separation distances feed both. Where the planning application involves development near an existing hazardous installation, the HSE consultation distances around that installation become a constraint on your scheme rather than a matter for your own consent, and the authority will consult on that basis. A Planning Statement drafted for a site handling controlled substances should say plainly which consents are held, which are applied for and which are not needed, with the quantities that lead to that conclusion.

Budgeting for a site handling controlled substances

Set aside four cost lines, not one. The statutory fee, which is small. The process safety input to establish quantities and containment, which is not. Any redesign forced by separation distances. And the recurring cost of keeping the consent aligned with operations as substances and volumes change.

Sites with controlled substances also tend to carry ground risk from historic use, so read the hazardous substances work alongside the cost of a contaminated land investigation programme rather than treating them as separate budgets. Utility capacity is the other early cost that bites on this sort of site, and the note on utility connection costs sets out where those charges land.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. For specialist technical reports, qualified professional input may be required.

See PlanScope pricing: one free report, £50 per report, or Professional for unlimited reports. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

When is hazardous substances consent required?

When a hazardous substance is present on, over or under land at or above the controlled quantity set for it in Schedule 1 to the Planning (Hazardous Substances) Regulations 2015. The trigger is presence rather than use, so storage and material held in transit both count. Consent must be in place before the substance arrives on the land.

How much is the fee for a hazardous substances consent application?

The fee is a flat amount fixed in regulations rather than scaled by site area or tonnage, and it is revised periodically alongside other planning fees. Check the current figure in the fees schedule on legislation.gov.uk or with the hazardous substances authority before budgeting, and expect the technical work behind the application to cost far more than the fee.

Are quantities added together across a site?

Yes. Substances within the same category are aggregated across the whole of the land in the applicant's control, so four separate vessels count as one total. Where different categories are present, a summation rule can bring a site into the regime even though no single substance reaches its own controlled quantity on its own.

Who decides a hazardous substances consent application?

For most sites the hazardous substances authority is the district, borough or unitary council, acting under the Planning (Hazardous Substances) Act 1990 rather than the planning Acts. Some sites fall to a different body, so confirm it. The authority consults the Health and Safety Executive on risk to people nearby and the Environment Agency where relevant.

Does consent transfer when a site is sold?

Not automatically. Where the person in control of all or part of the land changes, the consent can be revoked unless the new controller applies within the period the legislation allows for the consent to continue. Missing that window means a fresh application, so put the check into the first week of site due diligence.

Do I need planning permission as well?

The two consents are independent and you may well need both. Planning permission for a building does not authorise storing a controlled substance in it, and hazardous substances consent does not authorise building anything. Running the applications together usually costs less, because the site plan, containment description and separation distances serve both.

Sources and further reading

hazardous substancesfeescommercialchange of useconsentsbudgeting

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

What verified views cost on a tall building scheme

Rendering a photomontage is quick. Surveying the camera position, registering the model to surveyed targets and documenting the chain is what makes a view verified, and what sets the fee.

Read article →
Costs, Fees and Budgeting7 min read

What a wind microclimate assessment really costs

The cost of wind microclimate work is set by how many configurations go through the tunnel. Scoping the measurement points, the mitigation variant and the cumulative schemes decides the fee before anyone is appointed.

Read article →
Costs, Fees and Budgeting7 min read

What drives the cost of a basement impact assessment

Ground investigation and monitoring dominate basement impact assessment fees, not the writing. A single-storey basement within the existing footprint can end the process at the screening stage.

Read article →
Costs, Fees and Budgeting7 min read

What drives the cost of a coal mining risk assessment

The desk study is the modest part. Mine entries, zones of influence and intrusive drilling are what move a coalfield site budget and programme.

Read article →
Costs, Fees and Budgeting7 min read

Costing a water neutrality offset where policy requires one

Water neutrality cannot be met by efficient fittings alone. Here is how the demand calculation works and what drives the cost of offsetting the shortfall.

Read article →
Costs, Fees and Budgeting6 min read

Budgeting the statutory metric and the biodiversity gain plan

The metric and the biodiversity gain plan are two separate pieces of work billed separately. Here is what drives the cost of each, and where the exemptions sit.

Read article →