Licences to occupy the highway during construction

7 min readBy PlanScope Editorial Team

Highway occupation charges accrue whether or not work is happening, and they sit outside the planning fee and the building control charge. On an urban site they run for the whole programme.

Highway licence construction costs sit outside the planning fee, outside the building control charge and usually outside the first cost plan. They are charged by the highway authority, they are priced by area and duration, and on a tight urban site they can run for the whole build programme. A scaffold on a footway for eleven months, a hoarding on two frontages and a skip bay is a four figure monthly commitment on many authorities, and nobody tells you that at planning stage.

The licences are also consents in their own right, with refusal and conditions attached. Getting planning permission does not entitle you to stand anything on the public highway.

Which activities need a licence

The Highways Act 1980 is the main instrument, and the pattern is simple: if the activity obstructs or occupies the highway, which includes the footway and the verge, it needs the authority's permission.

Activity Usual statutory basis Typical lead time
Scaffolding over the footway Highways Act 1980, section 169 Two to six weeks
Hoarding around a site Highways Act 1980, section 172 Two to six weeks
Builder's skip on the carriageway Highways Act 1980, section 139 One to two weeks
Materials or plant deposited on the highway Highways Act 1980, section 171 Two to six weeks
Temporary footway or road closure Road Traffic Regulation Act 1984, sections 14 and 16A Six weeks to three months
Apparatus placed in the street New Roads and Street Works Act 1991, section 50 Several weeks
New or altered vehicle crossing Highways Act 1980, section 184 Weeks, plus works programming

Section 172 is the one people get backwards. It is not permissive. Where building work is to be done on a building within a street, the authority may require a hoarding or fence to be erected before the work begins, and doing the work without one where it has been required is an offence. So the hoarding is often a duty and a licensed activity at the same time.

Scaffolding, hoarding and skip permits

A scaffold licence application normally needs a drawing showing the footprint on the footway, the remaining clear pedestrian width, the proposed duration, and evidence that the scaffold is designed and will be inspected properly. Authorities commonly ask for a design in accordance with the recognised scaffolding guidance, and a handover certificate from the scaffolder.

The clear width left for pedestrians is where applications get refused or reduced. Authorities work to a minimum effective footway width and will insist on a protected walkway under the scaffold, or a signed diversion with tactile paving and ramps, rather than simply allowing the footway to be blocked.

Skip permits are quicker and more heavily conditioned than people expect. The skip has to be marked and lit in accordance with the marking regulations, positioned away from junctions and crossings, and removed promptly when full. Authorities often cap the duration at a few days and charge per skip per period, which makes a muck away strategy relying on a permanent skip bay a poor plan.

Hoarding licences bring the advertising question with them. Advertising on a site hoarding may need advertisement consent under the Town and Country Planning (Control of Advertisements) (England) Regulations 2007, separately from the highway licence, and the two are administered by different teams in the same building.

Footway closures and temporary traffic orders

A full footway or carriageway closure is a different order of magnitude. A temporary traffic regulation order under the Road Traffic Regulation Act 1984 requires advertisement, a notice period and, in many authorities, a three month lead time for a planned closure.

Short notice powers exist for emergency and urgent works, and they are not available for a contractor who failed to programme. Assume the long route.

The cost structure here changes too. Alongside the authority's administration charge, you are usually paying for the advertisement, the traffic management design, the signage and barriers, and traffic marshals where pedestrians are diverted across a carriageway. On a town centre site, closure costs frequently exceed the licence fee by a wide margin.

Charges by duration and area

There is no national schedule. Each highway authority sets and publishes its own charges, which means the only reliable figure is the one on the authority's current fees page. Check the current schedule for the authority covering your site before putting a number in the cost plan.

The structures in common use are:

  • a fixed application or administration fee per licence
  • a periodic occupation charge per square metre of highway occupied, usually weekly or monthly
  • a banded charge by street category, with higher rates on principal roads and in town centres
  • a per item charge for skips and for each renewal
  • a deposit or bond against damage to the highway surface and kerbs
  • a separate charge for the inspection regime

Two features of that structure matter for the programme. Occupation charges accrue whether or not work is happening, so a scaffold left up through a six week delivery delay is pure cost. And renewals are usually charged at the full rate, so a licence period that underestimates the programme costs more than one that overestimates it.

Insurance requirements

Every licence will require public liability insurance naming the authority's interest, and the indemnity limit is set by the authority rather than by convention. Limits of £5 million and £10 million are both in use. Check what the authority specifies and check that the policy actually covers highway occupation, because some contractor policies exclude it.

The authority will also normally require an indemnity in favour of itself against claims arising from the licensed activity, and will want the licence holder identified clearly. That matters when the contractor changes mid-build. A licence held by a contractor who leaves the site does not transfer automatically, and a new application may be needed.

Interaction with the construction management plan

Most permissions of any size carry a condition requiring approval of a construction management plan or a construction traffic management plan before works begin. The sensible approach is to design the highway occupation once and use it for both purposes.

A Construction Traffic Management Plan that shows the hoarding line, the scaffold footprint, the pedestrian diversion, the delivery bay and the vehicle routing is also most of the supporting material for the highway licences. A Construction Management Plan covers the wider site management, working hours, dust and noise controls and neighbour liaison.

Where the two documents disagree, the highway authority notices. Submitting a plan showing a footway closure that the highway team has already said it will not grant is a reliable way to lose a month on condition discharge.

Programming applications before start

Work backwards from the date the scaffold goes up, not forwards from the date of the planning decision.

  1. Identify every highway occupation the build needs, including temporary ones such as a crane lift closure.
  2. Confirm the authority's current charges and conditions, and the application lead time for each licence.
  3. Submit the construction management plan for condition discharge first, so the highway licence applications are consistent with it.
  4. Apply for the long lead items, chiefly any temporary traffic regulation order, at least three months ahead.
  5. Apply for scaffold, hoarding and skip permits once the contractor's programme is fixed, with durations that include contingency.
  6. Diarise the renewal dates, because an expired licence stops the work and the authority can require immediate removal.

The budget line to carry through the appraisal is the occupation charge over the full programme, not the application fee. It is the recurring item that surprises people. For the other statutory costs that sit alongside it, see the building control charges that run alongside the planning fee and how planning fees are indexed each April.

This is general guidance, not legal advice. Highway licensing is administered locally and the charges and conditions vary. Check the position with the highway authority for your site or a qualified professional before relying on it.

See PlanScope pricing if you are budgeting the application documents alongside these costs: one free report, £50 per report, or Professional for unlimited reports. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Do I need a licence for scaffolding over the pavement?

Yes. A scaffold licence under section 169 of the Highways Act 1980 is needed wherever scaffolding stands on or over the highway, including the footway. Applications normally require a footprint drawing showing the remaining clear pedestrian width, the duration, a design to recognised scaffolding guidance and a handover certificate.

Is a site hoarding optional?

Not always. Under section 172 of the Highways Act 1980 the authority may require a hoarding or fence before building work begins on a building within a street, and carrying out the work without one where it has been required is an offence. So the hoarding is frequently both a duty and a licensed activity.

How much do highway licences cost?

There is no national schedule. Each highway authority sets and publishes its own charges, usually combining an application fee with a periodic occupation charge per square metre, banded by street category, plus deposits and inspection charges. Check the current fees schedule for the authority covering your site.

How long does a temporary road closure take to arrange?

A planned temporary traffic regulation order under the Road Traffic Regulation Act 1984 requires advertisement and a notice period, and many authorities work to a three month lead time. Short notice powers exist for urgent and emergency works and are not available to a contractor who failed to programme.

Does a highway licence transfer if the contractor changes?

Not automatically. Licences identify the holder, and a licence held by a contractor who leaves the site may need to be reapplied for by the incoming party. The insurance position needs checking at the same time, because some contractor policies exclude highway occupation.

Sources and further reading

highway licencescaffoldinghoardingconstruction costshighways actconstruction management

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

The cost of changing from outline to full application

Switching from outline and reserved matters to a single full application costs a fresh fee, a rerun of parts of the technical baseline and possibly a renegotiated section 106.

Read article →
Costs, Fees and Budgeting7 min read

What an Article 4 direction does to a conversion appraisal

Withdrawing a permitted development right changes the consent route, the documents, the timetable and the unit mix. Four places an Article 4 direction belongs in a conversion appraisal.

Read article →
Costs, Fees and Budgeting8 min read

Rights of light risk on an urban infill

Rights of light sit outside the planning system. The remedy is an injunction or damages based on development value, which makes this a project risk rather than a cost line.

Read article →
Costs, Fees and Budgeting8 min read

Flood modelling where no published model exists

Published flood mapping covers main rivers in detail and ordinary watercourses barely at all. On those sites the choice is bespoke modelling or a defensibly conservative approach.

Read article →
Costs, Fees and Budgeting8 min read

Electricity capacity enquiries and connection costs

Distance to the nearest cable is not what prices an electricity connection. The nominated point of connection and any reinforcement behind it are, and a free budget estimate tells you early.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a second ecological season after a lapse

Ecology data has a working shelf life of roughly one to three years. When a permission lapses or a licence expires, the difference between an update visit and a second full season decides the budget.

Read article →