Viability, Obligations and Commercial

Local labour and apprenticeship clauses in section 106

7 min readBy PlanScope Editorial Team

Employment and skills clauses are easy to agree and hard to deliver. The drafting choices that matter are the target basis, the default payment and who reports.

Local labour and apprenticeship clauses are secured through a section 106 agreement, usually as an obligation to submit and implement an employment and skills plan before works start. The drafting questions that decide whether the clause works are narrow: how the target is expressed, who owns it once the contractor is appointed, what counts as compliance, and what happens if the number is missed.

Developers tend to negotiate the quantum and accept the mechanics. That is the wrong way round. A modest target with a hard default payment and monthly reporting is far more onerous in practice than a large target measured on best endeavours.

What authorities ask for and why

Authorities justify these obligations on local plan policies about economic benefit, inclusive growth and access to employment. The ask usually has three parts.

A plan, submitted and approved before works start, setting out how the construction phase will recruit and train locally. Numeric commitments, expressed as apprenticeship starts, work placements, local jobs or person-weeks of employment. And a monitoring and default mechanism.

Some authorities also seek commitments for the end use rather than the construction phase, meaning jobs in the completed offices, hotel or retail units. Those are harder to deliver, because the developer rarely controls the occupier, and harder to justify on the statutory tests.

Be clear which phase is being discussed, because the two get conflated in negotiation and then conflict in the drafting.

Employment and skills plans as a conditioned document

The plan itself is better handled as an approved document than as a set of numbers in the agreement body.

That structure gives both sides room. The agreement requires a plan meeting stated objectives, submitted before works start and approved in writing. The plan carries the detail: recruitment routes, the authority's employment brokerage, advertising arrangements, site induction and progression, and the reporting format.

Two drafting points to insist on. First, approval should be deemed given if the authority has not responded within a stated period, because a plan awaiting approval can block the start on site. Second, the plan should be capable of variation by agreement in writing without a deed of variation, since the contractor will change the delivery arrangements at least once.

Where an obligation later becomes pointless, there is a statutory route to modify it, and we cover that in discharging a section 106 obligation that no longer serves.

Numeric targets against best endeavours

This is the central negotiation, and the options are not symmetrical.

Basis How it is measured Risk to the developer
Best endeavours Evidence of effort, advertising and engagement Low, but authorities resist it
Numeric target with default payment Counted starts or person-weeks against a figure Quantified, and insurable through the build contract
Numeric target with no default Breach of obligation, enforceable by injunction Open-ended and unattractive

Numeric targets are commonly derived by formula, expressed per million pounds of construction value or per unit of floorspace, with the figure set out in the authority's own guidance. Ask for the guidance and check how the formula treats demolition, enabling works and fit-out, because including them inflates the target for no additional labour.

Best endeavours wording is not the soft option it looks like. An obligation to use best endeavours is a real obligation, and the evidence needed to show compliance is sometimes more burdensome than counting apprentices.

The combination worth aiming for is a numeric target, a clear measurement definition, and a stated default payment that caps the exposure.

Whether the clause meets the statutory tests

Two hurdles. The obligation has to fall within the purposes in section 106 of the Town and Country Planning Act 1990. And it has to satisfy regulation 122 of the Community Infrastructure Levy Regulations 2010, meaning necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind.

Construction phase training obligations generally clear the second and third limbs. The labour is employed on this site, so the link is direct, and a formula tied to construction value scales with the development.

Necessity is where the argument lives. An obligation is necessary to make the development acceptable only if the development would otherwise be unacceptable, and it is not always obvious that a scheme is unacceptable for want of apprenticeships. Authorities answer that with a local plan policy requiring the contribution, which is usually enough in practice.

End-use employment clauses are weaker on all three limbs. Clauses that seek to control who an unknown future occupier employs are the most vulnerable of all.

One further point. A requirement to employ people from a defined area has to be drafted so it does not discriminate unlawfully under the Equality Act 2010, which is why these clauses are framed around advertising, recruitment routes and travel-to-work areas rather than residence tests. The Public Services (Social Value) Act 2012 is sometimes cited in support, though it concerns public procurement rather than planning, so it carries no weight on the statutory tests.

Monitoring, reporting and default payments

The mechanics determine the burden.

  • Reporting frequency. Quarterly is manageable. Monthly on a two year build is 24 returns, each needing data from the contractor.
  • Who reports. Name the developer, with the contractor's obligations flowed down through the building contract, rather than naming the contractor in the agreement.
  • What counts. Define an apprenticeship start, a work placement and a local resident, with the definitions in the agreement rather than left to the plan.
  • The default payment. Expressed per unachieved apprenticeship or per person-week, payable on practical completion, with a cap.
  • Bonds. Authorities occasionally ask for a bond or deposit for the maximum default. Resist it where the default payment is already capped and the developer is solvent.

Define the measurement period too. A target measured over the whole construction period is deliverable. The same target measured in each quarter is not, because recruitment does not follow a straight line.

Practical delivery through the contractor

The developer carries the obligation and the contractor does the work, so the building contract has to carry it across.

Include the employment and skills plan as a contract document. Put the reporting obligation in the contractor's scope with a named person responsible. Price it, because supervision, induction and placement coordination cost real money and a contractor who has not priced it will not do it. And put the default payment risk where it belongs, which is with whoever controls the recruitment.

Engage the authority's employment brokerage early if it has one. These teams exist to fill exactly these targets, and a developer who uses them has evidence of compliance even where the numbers fall short.

Construction logistics and the workforce arrangements overlap, so the Construction Management Plan and the employment plan should be written by people who have read each other's drafts.

Negotiating achievable wording

Four asks that authorities usually grant.

A target measured across the whole construction period rather than by quarter. A capped default payment in place of an open-ended obligation. Deemed approval of the plan after a stated period. And exclusion of demolition and enabling works from the construction value used in the formula.

Two asks that are harder. Removing end-use employment obligations, which depends on how firmly they sit in the local plan. And reducing the quantum, which is where a viability case may be needed, and where an inspector can revisit the position on appeal, as we discuss in when an inspector reopens viability at appeal.

Where the scheme's wider employment benefits are part of the planning case, set them out properly in an Economic Impact Assessment rather than asserting them. Councils expect a suitably qualified author for that work, and professional review is advisable. And on which instrument secures which obligation across a development, section 278, section 38 and section 106 sets out the distinctions.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This is general guidance rather than legal advice, so check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

Do local labour clauses satisfy the statutory tests?

Construction phase training obligations usually clear the directly related and fairly related limbs of regulation 122, because the labour is employed on the site and formulae scale with construction value. Necessity is the weaker limb, and authorities answer it with a local plan policy. End-use employment clauses are more vulnerable on all three.

Is best endeavours wording better than a numeric target?

Not necessarily. An obligation to use best endeavours is a real obligation, and proving compliance through evidence of advertising and engagement can be more burdensome than counting apprenticeship starts. A numeric target with clear definitions and a capped default payment usually gives the developer more certainty.

Can a section 106 require employment of local residents?

It has to be drafted carefully to avoid discriminating unlawfully under the Equality Act 2010, which is why these clauses are framed around local advertising, recruitment routes and travel-to-work areas rather than residence requirements. The Public Services (Social Value) Act 2012 concerns public procurement and carries no weight on the planning tests.

How are default payments calculated?

Usually per unachieved apprenticeship start or per person-week of local employment, payable on practical completion. Negotiate a cap on the total, define the measurement period as the whole construction phase rather than each quarter, and resist a bond where the default payment is already capped and the developer is solvent.

Who should hold the obligation, the developer or the contractor?

Name the developer in the agreement and flow the obligations down through the building contract, including the employment and skills plan as a contract document and the reporting duty in the contractor's scope with a named person. Price it, because a contractor who has not priced induction and placement coordination will not deliver it.

Sources and further reading

section 106employment and skillsapprenticeshipsplanning obligationsdevelopers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Viability, Obligations and Commercial

View all →
Viability, Obligations and Commercial8 min read

Marriage value and site assembly in a viability appraisal

Assembly costs are real, but most of them do not reduce what a scheme can contribute. Where acquisition costs, ransom premiums and created marriage value each belong in the appraisal.

Read article →
Viability, Obligations and Commercial7 min read

Varying a planning obligation after five years

After the five year relevant period, a statutory application under section 106A replaces negotiation, and a refusal can be appealed under section 106B. What the authority can decide and what it cannot.

Read article →
Viability, Obligations and Commercial7 min read

Social infrastructure contributions and how they are justified

Contribution requests are built from a yield factor, a capacity claim and a published cost. The arithmetic is usually right, so the argument belongs on the capacity evidence and the statutory tests.

Read article →
Viability, Obligations and Commercial7 min read

Pooling restrictions and clawback in planning obligations

Regulation 123 and the five obligation pooling cap went in September 2019. What remains is the statutory test in regulation 122, the infrastructure funding statement, and careful drafting against duplication.

Read article →
Viability, Obligations and Commercial8 min read

Indexation of section 106 contributions and which index applies

The index family and the base date decide how far an indexed contribution moves. Name the series exactly, set the base date to the prices the figure is expressed in, and recalculate every demand.

Read article →
Viability, Obligations and Commercial8 min read

Phasing a scheme to manage section 106 triggers

Phasing moves when obligations fall due rather than how much they total. Define phases by land parcel, build in a revised phasing plan mechanism, and tie affordable delivery to occupation within each phase.

Read article →