Constraints and Designations

Marine licensing where a site reaches the tideline

7 min readBy PlanScope Editorial Team

A site that reaches the foreshore sits in two consent regimes at once. Planning permission runs to the low water mark, while marine licensing starts at mean high water springs.

If any part of your works falls below mean high water springs, you need a marine licence as well as planning permission. A marine licence for development at the tideline is granted by the Marine Management Organisation under Part 4 of the Marine and Coastal Access Act 2009, and the local planning authority has no power over it. The two consents overlap in a narrow strip of foreshore, and schemes come unstuck when the applicant assumes planning permission settles the question.

The strip matters more than its width suggests. Slipways, outfalls, revetments, piling, scour protection and even the temporary deposit of material during construction can all sit below the line.

Where planning jurisdiction ends

A local planning authority's area extends seaward to the low water mark, so the Town and Country Planning Act 1990 still applies across the intertidal zone. Marine licensing starts higher up, at mean high water springs. Between those two lines both regimes operate, and both consents are needed.

Above mean high water springs, planning permission alone is normally enough. Below mean low water, the marine licence does the work and planning permission is not required, although the authority will often still be consulted. In the overlap, the sequencing question becomes real: which application do you make first, and what does each decision-maker assume about the other.

The answer in practice is to run them in parallel and to make each application acknowledge the other. A planning committee that is told the marine licence is outstanding can still resolve to grant. One that discovers the point from an objector cannot.

Finding the boundary on the ground and on the drawings

Mean high water springs is a tidal datum, not a visible feature, and the mark on an Ordnance Survey plan is a generalisation surveyed at a point in time. On a soft or mobile shoreline it can be some distance from where the water actually reaches.

Three sources are worth having before the drawings are fixed. Admiralty tidal data for the nearest standard or secondary port gives the predicted levels. A topographic survey tied to Ordnance Datum Newlyn lets you plot those levels as contours on the site plan. And the local harbour authority or the Crown Estate will often hold a boundary position of its own, since ownership of most of the foreshore and the seabed rests with the Crown Estate and a lease is needed regardless of consents.

Show the line on the submitted drawings with the datum and the source stated. An application that plots mean high water springs as a dashed line with no explanation invites the Marine Management Organisation to disagree with it.

Activities that need a licence

Section 66 of the 2009 Act describes licensable marine activities, and the list is broader than most people expect. It includes depositing any substance or object in the sea or on or under the sea bed, constructing, altering or improving any works, dredging, and removing substances or objects from the sea bed.

The breadth catches construction method as well as permanent works. Temporary cofferdams, barge moorings, the discharge of concrete washings, and material placed on the foreshore to form a working platform are each capable of being licensable. So is maintenance dredging to keep an existing berth usable, which is a recurring obligation rather than a one-off consent.

Marine works also have their own environmental assessment regime. The Marine Works (Environmental Impact Assessment) Regulations 2007 sit alongside the terrestrial regime, so a scheme can require screening twice, on different criteria, for the same project. Where the terrestrial side is already heading towards an Environmental Impact Assessment, coordinate the two rather than running them as separate workstreams, and remember that an environmental statement must be prepared by competent experts.

Exemptions and the lighter routes

Not every activity below the line needs a full licence. The Marine Licensing (Exempted Activities) Order 2011, as amended, exempts a long list of low-risk activities, usually subject to conditions and often subject to notifying or registering with the Marine Management Organisation first.

Typical exemptions cover small-scale maintenance of existing structures, certain navigational aids, scientific sampling and some emergency works. The organisation operates a self-service route for registering qualifying exempt activities, which is quicker and costs less than a licence application and is the right starting point for minor foreshore work.

Read the conditions attached to each exemption carefully. Most are drafted narrowly, and an activity that exceeds a volume, an area or a timing restriction loses the exemption entirely rather than partially.

Marine plan policies and how they are applied

England's marine plans cover the whole inshore and offshore area, and under section 58 of the 2009 Act public authorities must take authorisation decisions in accordance with the relevant marine plan unless relevant considerations indicate otherwise. The UK Marine Policy Statement sits above them.

In substance the plans work much like a local plan. They allocate priority for certain activities, protect others, and contain policies on coastal change, access, seascape, fisheries, aggregate resources and designated sites. An application that cites the relevant plan policies by number and explains compliance reads considerably better than one that treats the marine side as a technical formality.

Designated sites drive most refusals and most conditions. Marine Special Areas of Conservation and Special Protection Areas require assessment under the Habitats Regulations, and the citation for the site tells you which features matter, in the same way described in our note on Special Protection Area citations and qualifying features. Marine Conservation Zones bring a separate duty. An intertidal Site of Special Scientific Interest often overlaps the works, and reading the notified features in the citation is the quickest way to understand what the objection will be.

The consultee list on a coastal scheme

Coastal applications attract a long consultee list, and the planning officer will not chase all of it for you.

  • The Marine Management Organisation on the licence and on any planning application affecting the marine area.
  • Natural England on designated sites, protected species and marine conservation.
  • The Environment Agency on flood risk, coastal defence and any environmental permit for works affecting a main river or sea defence.
  • The Maritime and Coastguard Agency and Trinity House on navigation, lighting and marking.
  • The local harbour or port authority, which may also hold its own works licensing powers.
  • Historic England on the marine historic environment, including wrecks and submerged landscapes.
  • The Crown Estate as landowner of most foreshore and seabed.

A Flood Risk Assessment is almost always needed as well, because a site at the tideline is in Flood Zone 3 and usually within a coastal flood risk area. Climate change allowances for sea level rise and the design life of the structure are the two figures the Agency will test, and both should be taken from the current published allowances rather than from an earlier report.

Sequencing the consents

The practical order of work on a tideline scheme looks like this.

  1. Establish ownership and secure agreement in principle with the Crown Estate or other landowner.
  2. Survey the site and plot mean high water springs against Ordnance Datum.
  3. Work out which elements fall below the line and whether any exemption applies.
  4. Pre-application engagement with both the local planning authority and the Marine Management Organisation, separately.
  5. Commission the survey work that both regimes need, particularly benthic and intertidal ecology, which has its own seasonal constraints.
  6. Submit the planning application and the marine licence application in parallel, each cross-referring to the other.
  7. Allow for the organisation's published determination period and consultation stages when programming, and check its current service standards rather than relying on an earlier project.

The honest uncertainty here is timing. Coastal schemes with designated site issues take longer than the service standards suggest, because the assessment work often has to be redone once the regulator has seen the first draft. Build that into the programme rather than discovering it.

This is general guidance rather than legal advice. Check the position with the Marine Management Organisation, your local planning authority or a qualified professional before relying on it.

Browse all 66 PlanScope report types and start a draft to see which supporting documents a coastal or estuarine scheme is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

Where exactly does a marine licence become necessary?

At mean high water springs. Below that line, licensable activities under section 66 of the Marine and Coastal Access Act 2009 need a marine licence from the Marine Management Organisation. Local planning authority areas extend to the low water mark, so between the two lines both planning permission and a marine licence are required for the same works.

Does planning permission remove the need for a marine licence?

No. The two regimes are independent, with different decision-makers, different tests and different appeal routes. A planning permission that covers works below mean high water springs does not authorise them, and starting work without the licence is an offence. Apply for both in parallel and cross-refer each application to the other.

Are small foreshore works ever exempt?

Often yes. The Marine Licensing (Exempted Activities) Order 2011, as amended, exempts a list of low-risk activities, usually subject to conditions and frequently subject to registering with the Marine Management Organisation first. The conditions are drafted narrowly, so exceeding a volume, area or timing limit removes the exemption completely rather than partly.

How do I find mean high water springs on my site?

Combine Admiralty tidal predictions for the nearest port with a topographic survey tied to Ordnance Datum Newlyn, then plot the level as a contour. The line shown on an Ordnance Survey plan is a generalisation and can be well away from the real position on a mobile shoreline. State the datum and source on the submitted drawings.

Do marine plans carry the same weight as a local plan?

Section 58 of the 2009 Act requires public authorities to take authorisation decisions in accordance with the relevant marine plan unless relevant considerations indicate otherwise. In substance that works much like the plan-led system on land, so cite the relevant marine plan policies by reference and explain compliance in the application.

Sources and further reading

marine licencetidelinecoastal developmentmean high water springsconstraints

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Constraints and Designations

View all →
Constraints and Designations7 min read

Nominating a building to a local heritage list

A locally listed building is a non-designated heritage asset, so applications affecting it attract a balanced judgement. What a nomination needs and what the listing does not do.

Read article →
Constraints and Designations7 min read

Veteran tree identification and who can confirm it

Ancient and veteran trees are irreplaceable habitats in national policy whether or not they are mapped or covered by a Tree Preservation Order. How status is established and challenged.

Read article →
Constraints and Designations7 min read

Policies map notations that are not designations

Regulation 9 of the 2012 Local Planning Regulations makes the policies map an illustration of policy, not a free-standing instrument. How to tell a designation from an indicative annotation.

Read article →
Constraints and Designations7 min read

When a conservation area appraisal is out of date

Conservation area appraisals carry no statutory review interval, so many predate the current local plan. What weight an old appraisal holds, and how to test a description that no longer matches the street.

Read article →
Constraints and Designations7 min read

Plantation on an ancient woodland site and its protection

A plantation on an ancient woodland site is still ancient woodland, because the designation attaches to soil continuity rather than to the trees standing on it.

Read article →
Constraints and Designations7 min read

A designations checklist before exchanging contracts

Standard searches cover local land charges, not environmental designations. The constraints that stop a self-build plot being developable usually have to be looked up directly.

Read article →