Nomination agreements and the affordable housing condition
The section 106 says how many affordable units. The nomination agreement says who lives in them. Developers who find out late find out two weeks before occupation.
A nomination agreement affordable housing arrangement decides who actually lives in the affordable units on your scheme. It sits between the local housing authority and the registered provider, and it is a separate document from the planning obligation that required the units in the first place. Developers who discover it late usually discover it at the worst moment, two weeks before first occupation, when the provider cannot let and the authority has not yet signed.
The planning side and the housing side of the same scheme run on different paperwork. The section 106 agreement says how many units, what tenure, what size and when they transfer. The nomination agreement says how tenants are selected for them. Neither document does the other's job.
What a nomination agreement does
The agreement gives the local housing authority the right to nominate households from its housing register to tenancies in specified units, and it sets out how that right operates in practice.
Typical content covers the units it applies to, the proportion of lettings the authority may nominate, the information the provider must give the authority when a unit becomes available, the time the authority has to put forward a nomination, what happens if no suitable nomination is made, the grounds on which the provider may reject a nomination, and the arrangements for reporting and review.
For affordable rent and social rent units the agreement is the normal route. For shared ownership the mechanism is different, because the provider is selling an interest rather than letting, and eligibility is usually controlled through the planning obligation and the provider's own marketing process instead. First Homes are controlled through the obligation and the national eligibility criteria rather than through nominations.
Who the parties are and who is not
The parties are the local housing authority and the registered provider. The developer is generally not a party, which is the source of most of the confusion on site.
What the developer normally has instead is an obligation in the section 106 agreement requiring that the affordable units be transferred to a registered provider approved by the authority, and frequently requiring that the provider has entered into a nominations agreement before first occupation of the private units. That is the hook that makes the housing paperwork a developer problem, and reading it carefully before the agreement is signed matters, because the trigger point varies.
Three practical questions to settle while the obligation is still in draft.
- Is the trigger first occupation of any private dwelling, a stated percentage of the private dwellings, or practical completion of the affordable units.
- Does the obligation name a specific provider, or does it allow any provider approved by the authority, which gives you room if the first deal falls over.
- Does the authority's approval of the provider have a deemed consent period, so that silence does not become a veto.
Local connection criteria and their limits
Authorities frequently want local connection criteria applied to nominations, and in rural areas that preference can be very strong. The legal framework constrains how far it can go.
Allocation of social housing is governed by the authority's allocation scheme under Part 6 of the Housing Act 1996, which must give reasonable preference to the statutory categories and must comply with the public sector equality duty under the Equality Act 2010. A local connection cascade in a nomination agreement operates within that scheme, not outside it.
Cascades are the usual drafting solution: connection to the parish first, then to adjoining parishes, then to the district, then the wider area, with each tier opening only after a stated marketing period produces no eligible household. Rural exception sites commonly carry a tighter cascade secured through the planning obligation itself.
Where the cascade is too tight, units stand empty, which serves nobody and creates its own planning problem when the authority asks why the affordable housing is not occupied. Where it is too loose, the local political support the scheme relied on can evaporate. This is a negotiation worth having early with the housing officer rather than the planning officer, because they are the ones who will have to make it work.
First lettings and subsequent re-lets
Nomination rights are usually stronger on first lettings than on re-lets. The common pattern is that the authority nominates to all of the initial lettings and to a proportion of subsequent vacancies, with the proportion set locally and recorded in the agreement.
The reason for the distinction is practical. On first lettings the authority is populating a new scheme from its register. On re-lets the provider is managing a standing portfolio, needs some flexibility for transfers within its own stock, and has management reasons for matching households to particular units.
Two clauses are worth attention in the re-let provisions. The void period after which the provider may let outside the nomination arrangements, because a short period protects the provider and a long one protects the authority's access to the stock. And whether the proportion is calculated per unit, per annum across the scheme, or across the provider's whole stock in the district, which can produce very different outcomes on a small scheme.
How the arrangement is secured in planning terms
The planning obligation is the enforceable instrument, and the nomination agreement sits alongside it rather than inside it. A well-drafted obligation defines the affordable housing by tenure, number, size and location on a plan, requires transfer to an approved registered provider, requires a nominations agreement to be in place before a stated trigger, restricts occupation of the units to persons eligible under the authority's allocation scheme, and provides for the affordable housing to remain affordable in perpetuity with the usual mortgagee exclusion provisions.
Conditions have a narrower role. A condition can restrict occupation of identified units to affordable housing, and it can require a scheme to be submitted and approved, but the detailed tenure, transfer and nomination machinery belongs in the obligation because it needs covenants that bind successors in title.
Where viability drove the affordable offer down, the obligation will often also carry a review mechanism, and the interaction between the review and the nomination arrangements needs thinking through: a late-stage review that increases the affordable requirement after the nomination agreement is signed means reopening the housing paperwork too. The inputs that drive those appraisals, including unit sizes and accessibility standards, are covered in space standards and accessible housing as appraisal inputs, and the Viability Assessment is where the offer is justified in the first place.
The Affordable Housing Statement submitted with the application should describe the intended tenure mix, the proposed provider arrangement and the approach to nominations in outline. Officers read it as a test of whether the applicant has engaged with the housing team at all.
Timing against practical completion
The sequence that avoids a stalled handover runs backwards from occupation.
Identify the registered provider and agree heads of terms for the acquisition well before practical completion, because the provider's board approval and due diligence take time. Get the authority's approval of the provider in writing. Have the provider and the authority negotiate the nomination agreement in parallel with construction rather than after it, since the authority's legal team has its own queue. Then confirm the agreement is executed before the obligation's trigger date, and keep the evidence, because the obligation is enforceable against the land and a breach can block occupation of the private units.
Where the provider changes late, which happens, check whether the obligation requires a fresh approval and whether the existing nomination agreement transfers. Often it does not, and the clock restarts.
When allocations go wrong
The recurring disputes are about suitability and voids. The authority nominates a household the provider considers unsuitable for the unit, or no nomination arrives within the period and the provider lets outside the arrangement, or the cascade produces no eligible household for a unit in a rural scheme.
Good agreements handle this with a short escalation route and a shared record: a named contact on each side, a stated period to resolve, and quarterly reporting of lettings against nominations so that patterns surface before they become arguments. Where the authority's own allocation scheme has changed since the agreement was signed, which happens over the life of a scheme, a review clause avoids the agreement becoming unworkable.
Where the scheme's equality implications were assessed, an Equalities Impact Assessment can also be the place where the approach to allocation was recorded, which is useful if the criteria are later challenged.
You can see which reports a residential scheme is likely to need and draft the affordable housing and viability documents from your own scheme details before the obligation is negotiated.
This is general guidance, not legal advice. Allocation schemes, nomination practice and obligation drafting differ between authorities, so take advice from a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Who signs a nomination agreement?
The local housing authority and the registered provider. The developer is generally not a party, but the section 106 agreement usually requires that a nomination agreement be in place before a stated trigger such as first occupation, which makes it a developer problem in practice even though the developer does not sign it.
Is affordable housing secured by condition or by obligation?
Mainly by a section 106 planning obligation, because the tenure, transfer and perpetuity provisions need covenants binding successors in title. A condition can restrict occupation of identified units to affordable housing or require a scheme to be approved, but it cannot carry the transfer and nomination machinery.
Can local connection criteria be applied to nominations?
Within limits. Allocation is governed by the authority's allocation scheme under Part 6 of the Housing Act 1996, which must give reasonable preference to the statutory categories and comply with the public sector equality duty. Cascades starting at parish level and widening after stated marketing periods are the usual drafting solution.
Do nomination rights apply to re-lets as well as first lettings?
Usually both, with stronger rights on first lettings. The common pattern is that the authority nominates to all initial lettings and to a proportion of later vacancies, with the proportion set locally. Check the void period after which the provider may let outside the arrangement, and how the proportion is calculated.
When should the nomination agreement be negotiated?
In parallel with construction, not after it. Identify the registered provider and agree acquisition heads of terms well before practical completion, obtain the authority's written approval of the provider, and have the agreement executed before the obligation's trigger. A breach of that obligation can block occupation of the private units.
Sources and further reading
This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.