Fire, Structural and Basements

Party wall awards and basement consents compared

6 min readBy PlanScope Editorial Team

Permission says whether you may build a basement. An award says how you may excavate beside your neighbour. What each controls and how to sequence them.

Planning permission says whether you may build a basement. A party wall award says how you may excavate next to your neighbour's building and who pays if something goes wrong. Neither one substitutes for the other, and a party wall award basement planning sequence that runs them in the wrong order is the most common reason a householder basement project stalls after permission is granted.

Two regimes with different jobs

The planning system is public law. The council decides whether development is acceptable in the public interest, weighing the local plan, amenity, heritage, trees and drainage. The decision is published, anyone can comment, and the council can enforce against a breach.

The Party Wall etc. Act 1996 is private law, and it applies in England and Wales. It governs the relationship between two landowners when one wants to work on a shared structure or excavate close to the other's building. The council has no role. There is no public register, no consultation, and nobody enforces it except the parties themselves through the courts.

The practical result is that you can have planning permission and still be unable to lawfully start, and you can be fully compliant under the 1996 Act and still be building without permission.

What planning controls on a basement

A basement dug wholly within the footprint of a house, with no external change, has commonly been treated as permitted development under Part 1 of Schedule 2 to the General Permitted Development Order 2015. Add a light well in front of the principal elevation, an external stair or a visible vent and you are usually into a planning application.

What the council looks at is the effect on the street scene, on neighbouring amenity, on trees, on drainage and surface water, and on any heritage asset. Several authorities require a Basement Impact Assessment by local policy, dealing with groundwater, ground movement and the effect on adjoining structures. That report looks at your neighbour's building, but it is produced for the council, not for the neighbour, and it does not discharge anything under the 1996 Act.

Flats are outside Part 1 altogether, so a basement to a flat or maisonette needs a planning application whatever its extent.

What the party wall process controls

Three sections do most of the work on a basement project.

Section 2 covers works to a party structure itself, such as cutting into a party wall, underpinning it or raising it. Notice is two months.

Section 1 applies where you want to build a new wall on the line of junction between the two properties. Notice is one month.

Section 6 is the one that catches basements. It applies where you excavate within three metres of a neighbouring structure and to a depth lower than its foundations, and also where you excavate within six metres and the excavation cuts a line drawn downwards at 45 degrees from the bottom of the neighbour's foundations. Notice is one month, and the notice has to be accompanied by plans and sections showing the proposed excavation.

Almost every habitable basement next to a terraced or semi-detached property triggers section 6, and many trigger section 2 as well.

Sequencing the two

Run planning first, then party wall, then building control, with one overlap.

  1. Settle the design and obtain planning permission or confirm permitted development, because the depth and footprint are what the party wall notices describe.
  2. Commission the structural and temporary works design to the point where the excavation sequence is defined.
  3. Serve notices under the relevant sections, with drawings. Allow the full notice period plus time for dissent.
  4. Appoint surveyors and obtain the award if the adjoining owner dissents or does not respond within 14 days, which counts as deemed dissent.
  5. Submit the full plans application to building control, which can run in parallel with step four.

Serving notices before the design is fixed wastes the notice period, because a material change to the excavation means serving again. Leaving them until the contractor is appointed costs the programme, since an award on a contested basement can take two to three months once surveyors are instructed.

The condition survey of the neighbouring property, done before any work, serves both regimes. The same reasoning applies as on larger schemes, where a Structural Survey of what is being retained is the starting point, and structural surveys for a scheme relying on retention covers the method. Photograph everything, including cracks that were already there.

Surveyors, awards and security for expenses

If the adjoining owner dissents, each side either agrees a single surveyor or appoints their own, with a third surveyor selected to resolve disagreement between them. The award records the works permitted, the method and sequence, working hours, access arrangements, the condition survey and who pays the surveyors' fees. Fees normally fall on the building owner, which is to say you.

Section 12 lets an adjoining owner require security for expenses before the works start, usually a sum held in an escrow account or by a solicitor, calculated against the cost of making good if you stop part way through. On a basement that figure can be substantial, and it is a cash flow item people fail to budget.

An award can be appealed to the county court within 14 days of service. That is rare and expensive, and it is usually a symptom of a neighbour relationship that was mishandled at the start.

Where a planning condition touches the neighbour

Conditions cannot require you to comply with the 1996 Act, because the Act applies regardless and a condition duplicating other legislation is not normally justified. What conditions do instead is control the things planning can control.

Issue Controlled by
Whether the basement is acceptable in principle Planning permission or permitted development
Hours of construction and site management Planning condition
Highway occupation by hoarding or skips Highway authority licence
Method and sequence of excavation next to a neighbour Party wall award
Structural adequacy and escape Building Regulations approval
Compensation for damage to the neighbour's building Party Wall etc. Act 1996, sections 7 and 11

Where scaffolding, hoarding or a skip occupies the footway, that is a separate licence from the highway authority, and the process for a scaffold licence and highway occupation runs on its own timetable. The temporary propping design that the award will describe is a designer duty in its own right, covered in temporary works design and designer duties.

Misunderstandings that cause delay

Four come up repeatedly.

That the neighbour can stop the basement. They cannot. Dissent leads to an award setting conditions on how you work, not to a veto. Only the planning system can refuse the development.

That planning permission authorises the excavation. It authorises the development in land use terms. Entering onto or undermining a neighbour's land needs the 1996 Act procedure.

That a basement impact assessment satisfies the party wall surveyor. It informs the discussion and will usually be requested, but the award is based on the structural and temporary works design, not the planning report.

That an objection to the planning application is the neighbour's only chance to be heard. The party wall process gives them a surveyor, a condition survey and a right to compensation, which is often more useful to them than an objection letter. Saying so early tends to lower the temperature considerably.

This is general guidance, not legal advice. The Party Wall etc. Act 1996 is a private law regime and disputes under it are matters for the parties and the courts, so take advice from a party wall surveyor and your local planning authority before relying on anything here. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can my neighbour stop my basement under the Party Wall Act?

No. Dissenting to a notice leads to an award that sets out how the works are carried out, the sequence, hours and access, together with a condition survey and a right to compensation for damage. It does not give a veto. Only the planning system can refuse the development itself, and only on planning grounds.

Which party wall notice applies to a basement?

Usually section 6, which covers excavation within three metres of a neighbouring structure to a depth below its foundations, and excavation within six metres cutting a 45 degree line down from the bottom of those foundations. Notice is one month and must include plans and sections. Section 2 applies as well where you cut into or underpin the party wall itself, with two months' notice.

Do I need planning permission for a basement under my house?

Not always. Excavation wholly within the existing footprint with no external change has commonly been treated as permitted development for a house under Part 1 of the General Permitted Development Order 2015. A light well, external steps or a new opening to the front usually needs an application. Flats are excluded from Part 1 entirely.

What is security for expenses?

Section 12 of the Party Wall etc. Act 1996 allows an adjoining owner to require money to be held before works start, to cover the cost of making their property safe if you stop part way through. On a basement the sum can be substantial, and it is commonly overlooked in a householder cash flow. It is released when the works are complete.

Does a basement impact assessment deal with the party wall issues?

It informs them but does not discharge them. The assessment is produced for the council and looks at groundwater, ground movement and effects on neighbouring structures in planning terms. A party wall award is based on the structural and temporary works design, and the appointed surveyors will want that detail rather than the planning report.

Sources and further reading

party wallbasementhouseholderpermitted developmentneighboursbuilding regulations

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements6 min read

Working on a pavement vault beneath the footway

The highway authority consents cellars and vaults under a street separately from planning. Ownership of the subsoil is usually unresolved until you look.

Read article →
Fire, Structural and Basements6 min read

Basement car parks beneath residential blocks

Excavation, ventilation and a ramp buy you spaces that most urban transport policy now wants fewer of. Test the parking count against the evidence first.

Read article →
Fire, Structural and Basements7 min read

Roof terraces on tall buildings and escape provision

Amenity policy pushes communal space onto the roof of tall residential buildings. The fire strategy decides whether it can be built as drawn.

Read article →
Fire, Structural and Basements7 min read

Firefighting shafts in a single core apartment plan

The firefighting shaft is the largest fixed element on a residential floor plate. Five checks that take an hour each and decide whether the massing works.

Read article →
Fire, Structural and Basements7 min read

Bin stores, chutes and fire separation in plan

Five requirements compete for the same few square metres next to the entrance. How carrying distances, collection access and fire separation are reconciled.

Read article →
Fire, Structural and Basements7 min read

Car park ventilation and charging bays in a layout

Open-sided, naturally ventilated or mechanically ventilated is a planning-stage decision, not a technical design one. How it fixes elevations, plant and layout.

Read article →