Costs, Fees and Budgeting

Planning fees for prior approval applications

7 min readBy PlanScope Editorial Team

Prior approval fees are flat or per dwelling charges set by permitted development class, not discounted planning fees. What drives the real cost of the route.

A prior approval fee is not a discounted planning fee. It is a separate charge set by class in the fees regulations, and the amount depends on which permitted development right you are using rather than on the scale of the works. A householder prior approval for a larger rear extension, an agricultural building notification and a Class MA conversion of a shop to flats sit at three different points on the scale.

Because every figure in the fee schedule is indexed and revised, this article deals with structure rather than amounts. Check the current schedule through the Planning Portal fee calculator before you budget, and check it again if the application slips past 1 April.

How prior approval fees differ from full application fees

A full planning application fee is calculated from the development: the number of dwellings, the floorspace created, or the site area. Prior approval fees are set as flat amounts by class, with some classes charging per dwelling.

Three consequences follow.

The relationship between fee and scheme size breaks down. A prior approval for one flat and a prior approval for a larger scheme under the same class can attract very different totals, depending on whether that class charges per unit.

The fee buys a narrower decision. The authority is not assessing the principle of development, only the matters the class reserves for its consideration, which might be transport and highways, contamination, flooding, noise and the impact on the local shopping provision. Anything outside that list is not a reason for refusal.

And a refused prior approval does not credit anything towards a subsequent full application. You pay twice.

Fees by permitted development class

The classes a landlord or investor meets most often each have their own basis.

Route Fee basis What the authority is deciding
Larger home extension, Part 1 Flat fee, householder scale Whether neighbours object on amenity grounds, following notification
Agricultural development, Part 6 Flat fee, lower band Siting, design and external appearance, where prior approval is required
Commercial to residential, Class MA Per dwellinghouse in most cases The reserved matters for that class, including transport, contamination, flooding, noise and natural light
Agricultural building to dwellings, Class Q Per dwellinghouse in most cases Transport and highways, noise, contamination, flooding, location and siting, design and external appearance
Telecommunications, Part 16 Flat fee Siting and appearance

Read the current fees regulations rather than relying on that table for amounts, because bands and multipliers have changed several times since 2023 and annual indexation now applies.

Two points that catch people. Some classes require a fee for the prior approval application and a further fee for any subsequent application to discharge conditions attached to the prior approval. And where the class requires the developer to apply for a determination as to whether prior approval is required, that application attracts the fee even if the answer is that approval is not required.

The determination period and the effect of missing it

Prior approval periods are short and they carry a consequence that ordinary applications do not.

Larger home extensions run to 42 days. Class MA and Class Q run to 56 days. Agricultural prior approvals under Part 6 run to 28 days. Each period runs from receipt of a valid application with the required information and fee.

If the authority does not notify a decision within the period, the development may generally proceed in accordance with the submitted details. That is the real value of the route and the reason validation matters so much: an authority that treats an application as invalid stops the clock, and a developer who assumes the clock is running may build unlawfully.

Protect the position with three habits. Submit everything the class lists, in the form it lists. Get written confirmation of the validation date. And diarise the expiry, then write to the authority on the day the period ends confirming your understanding rather than starting work silently.

Where the authority refuses within the period, appeal rights exist, and the appeal is against the refusal of prior approval rather than against a refusal of planning permission.

Where a prior approval refusal leads to a full application

A refusal is not the end, but it changes the arithmetic.

The full application fee is calculated on the ordinary basis, so a conversion refused under Class MA becomes a change of use application charged at the standard rate. The assessment also widens: the authority can now consider the principle of the development, the loss of the existing use, design, amenity and everything else, and local plan policies apply in full.

Sometimes that is an advantage. A scheme that fails a narrow technical test in the class, such as a natural light requirement, may succeed on its merits as a full application with a different internal layout. Sometimes it is fatal, because the local plan protects the existing use.

Decide which before paying the second fee. Read the refusal notice carefully: a refusal on a matter the class reserves tells you something different from a refusal on the ground that the right was never available.

Fees where multiple units are proposed

Where a class charges per dwellinghouse, the fee scales with the scheme and it can be substantial on a larger conversion.

Two practical points. Count the units the way the regulations count them, which is by dwellinghouse created rather than by bedroom or by habitable room. And where a scheme is phased, splitting it into separate applications does not reduce the total fee, and it does introduce the risk that the later phase is assessed against a changed policy position.

A related trap on Class Q is the limit on the number of dwellings and the floorspace that may be converted within an agricultural unit. Earlier conversions on the same unit consume that allowance, and an application that exceeds it is not a fee question, it is a refusal.

Costs of the supporting information required

The fee is usually the smallest line in a prior approval budget. The supporting information is the rest.

For Class MA, the reserved matters commonly require a transport and highways note, a contamination assessment, a flood risk position where the site is in a flood zone, a noise assessment where the site adjoins a commercial use, and evidence on natural light to habitable rooms. That last item has ended more Class MA schemes than any policy argument, because rooms with no window cannot be made compliant by drafting.

For Class Q, expect structural evidence that the building can be converted without substantial rebuilding, together with transport, noise, contamination and flooding material.

A Planning Statement setting out how each reserved matter is addressed, cross-referenced to the supporting documents, makes the officer's job straightforward and reduces the chance of a validation query. The report index shows which technical reports the reserved matters usually call for.

Budgeting a prior approval route end to end

Build the budget in five lines rather than one.

  1. The prior approval fee, taken from the current schedule and multiplied by units where the class charges per dwelling.
  2. Drawings, including existing and proposed floor plans and elevations at the scale the authority requires.
  3. Technical reports for each reserved matter, which is usually the largest line.
  4. Condition discharge fees after approval, plus the cost of the information those conditions require.
  5. A contingency for a full application if the prior approval fails, at the standard fee rate.

Then compare the total against a full application from the outset. On a marginal Class MA scheme where several reserved matters are difficult, the prior approval route can cost more than a change of use application and deliver a narrower permission. The pricing page sets out what an AI-assisted draft of each supporting report costs against a consultant appointment.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How is a prior approval fee calculated?

By class rather than by scheme size. Some classes carry a flat fee and others charge per dwellinghouse created. The amounts sit in the fees regulations and are indexed annually, so check the current schedule through the Planning Portal fee calculator before budgeting, and check again if the application slips past 1 April.

What happens if the council misses the determination period?

For most prior approval classes the development may then proceed in accordance with the submitted details. Larger home extensions run to 42 days, Class MA and Class Q to 56 days, and Part 6 agricultural notifications to 28 days. The period runs from receipt of a valid application, so confirm the validation date in writing.

Does a refused prior approval reduce the fee for a full application?

No. The full application fee is charged on the ordinary basis, so you pay twice. The compensation is that the assessment widens: the authority can consider the principle, design and amenity, so a scheme that failed a narrow technical test in the class may succeed on its merits with a different layout.

Which reserved matter causes most Class MA refusals?

Natural light to habitable rooms. Rooms without a window cannot be made to comply by redrafting the application, so the layout has to change or the scheme has to shrink. Transport, contamination, flooding and noise are the other reserved matters, and each usually needs its own supporting document.

Can I split a scheme into phases to reduce the fee?

Not usefully. Where a class charges per dwellinghouse the total is the same across separate applications, and phasing introduces the risk that the later phase is assessed against a changed policy position. On Class Q, earlier conversions on the same agricultural unit also consume the allowance for units and floorspace.

Sources and further reading

prior approvalplanning feesclass maclass qpermitted developmentbudgeting

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting8 min read

Costing a stopping up order for a highway or footpath

Public rights do not lapse through disuse and planning permission does not override them. This covers the section 247 and 257 routes, what objectors actually argue about, and how to keep the order off the critical path.

Read article →
Costs, Fees and Budgeting7 min read

Costing an affordable housing review mechanism

Early and late stage review mechanisms are decided by their definitions, not their headline percentages. This covers the inputs that move the answer, who pays for the review and the caps to secure before signing.

Read article →
Costs, Fees and Budgeting7 min read

Costing an employment land assessment for an allocated site

On an allocated employment site the fee sits in evidence gathering, not analysis. This covers the marketing records councils expect, the suitability tests that decide it, and how to sequence the work.

Read article →
Costs, Fees and Budgeting7 min read

Costing an odour assessment for a kitchen or waste use

The fee for an odour assessment depends on whether the council accepts a qualitative risk based appraisal or expects dispersion modelling. Here is what sits behind each, and how to scope the work before you commission it.

Read article →
Costs, Fees and Budgeting6 min read

Costing a telecommunications compliance declaration for a mast

An ICNIRP declaration is produced by the operator's own radio engineers and closes the health issue. Siting and appearance are the only matters the council can decide on.

Read article →
Costs, Fees and Budgeting6 min read

Costing an equalities impact assessment for a public applicant

The public sector equality duty is continuing, so an equalities impact assessment has to be revisited at every material change. Budgeting for one document is the common mistake.

Read article →