Radon affected areas and what the maps mean for a new build

6 min readBy PlanScope Editorial Team

Radon protection is decided by a property-specific report and Approved Document C, not by the planning application. Getting the report early changes the foundation design, not just the paperwork.

A radon affected area is a place where the mapping predicts that one per cent or more of homes exceed the radon action level. If your plot sits in one, the new dwelling will need radon protective measures built in, and the level of protection depends on a property-specific report rather than on the colour of the area on a national map.

The thing most self-builders get wrong is timing. Radon protection interacts with the floor construction, the ground bearing slab or beam and block design, the service penetrations and the sub-floor ventilation. Finding out after the foundations are poured means retrofitting a sump, which is doable and irritating.

How radon affected areas are mapped

Radon occurs naturally from the decay of uranium in rocks and soils, and concentrations vary with geology. The joint mapping produced by the UK Health Security Agency and the British Geological Survey estimates the probability that a home in a given area exceeds the action level of 200 becquerels per cubic metre. A separate target level of 100 becquerels per cubic metre is the figure at which action is worth considering in existing homes.

The published maps are indicative and work at a grid scale. They are not a substitute for a report on your plot, because geology changes over short distances and the mapping shows probability rather than a measured value at your site.

Mapped probability bands determine the level of protection required, and the bands are set out in the guidance that accompanies the maps. What you need is the report for the specific address or grid reference.

Obtaining a radon risk report for a site

A property-specific radon report can be ordered against a postal address or a grid reference, and it states whether the property is in a radon affected area and which level of protection, if any, is required for new construction. The report is the document building control will ask for.

Order it at feasibility stage, alongside the desk study. On a plot with no postal address yet, the grid reference version is what you need, and the surveyor setting out the plot can give you the coordinates.

Radon is also routinely covered in the ground gas section of a Phase 1 desk study, so if you are already commissioning a Contaminated Land Assessment for another reason, ask for the radon position to be stated explicitly rather than mentioned in passing. Where mining, landfill or made ground is present, the ground gas regime and the radon regime interact, and the protection measures may need to serve both.

Basic and full protective measures

Approved Document C to the Building Regulations 2010 sets out the guidance, which in turn draws on the published protective measures guidance for new buildings.

Basic protection is, in essence, a radon-resistant barrier across the whole footprint of the building, including at junctions, service entries and cavity trays, and sealed at every penetration. The workmanship matters more than the specification, because a barrier with an unsealed soil pipe is not a barrier.

Full protection is the barrier plus an active or passive means of depressurising the ground beneath the building. On a ground bearing slab that normally means a radon sump connected to a vent pipe taken to a suitable termination, capable of being fitted with a fan later. On a suspended floor it can be achieved by cross-ventilating the underfloor void instead.

Protection level Typical components When it applies
None Standard damp proof membrane Outside a radon affected area
Basic Continuous radon barrier, sealed at all penetrations Lower probability bands within an affected area
Full Radon barrier plus sump and vent pipe, or a ventilated void Higher probability bands within an affected area

The property report tells you which row applies. Do not infer it from a neighbour's build or from a map extract.

Where the requirement sits in Building Regulations

Requirement C1(2) of Schedule 1 to the Building Regulations 2010 deals with resistance to contaminants from the ground, and radon falls within it. Approved Document C is the guidance on how to meet it.

This is a building control matter, which has two practical consequences. Building control will want to inspect the barrier before it is covered, so build the inspection into the programme rather than treating it as paperwork. And a planning permission granted with no mention of radon says nothing at all about whether protection is needed.

Planning does have a residual interest where ground conditions are a policy issue in their own right, and where a site has both radon and a contamination history a Geotechnical Assessment and a ground gas risk assessment may be conditioned. The distinction is that planning conditions deal with site suitability and remediation, while the radon measures themselves are delivered through building control.

Basements and extensions in affected areas

Basements need particular care. A below-ground room has a larger surface area in contact with the ground, poorer natural ventilation and a tendency to accumulate gas, so the measures that suffice for a ground floor may not be adequate. Where a basement is proposed in a radon affected area, get specific advice rather than applying the standard detail, and consider a design that allows a fan to be added to the sump.

Extensions to existing homes in affected areas are covered by the guidance as well, and the answer depends on the size of the extension relative to the existing house and on whether the existing dwelling has been tested. An extension that seals the ground beneath a previously vented area can raise levels in the existing house even where the extension itself is protected.

Conversions of existing buildings to dwellings, including permitted development conversions, sit in the same territory. A structural survey will tell you about the building, and the radon report will tell you about the ground, and both are needed. Where the conversion involves a historic structure, a Structural Survey and the radon detailing often have to be reconciled, because a continuous barrier is harder to achieve in a building with solid walls and no damp proof course.

Testing after completion

Protective measures reduce risk. They do not guarantee a result, and the only way to know the level in the finished house is to measure it.

Testing uses passive detectors left in place for three months, normally in a living room and a bedroom, and the result is adjusted to an annual average. Three months is the standard period because radon levels fluctuate daily and seasonally, and short-term readings are unreliable.

If the result exceeds the action level in a house built with full protection, the usual answer is to fit a fan to the existing sump, which is why leaving the sump accessible and the vent pipe correctly sized matters at construction stage. In a house with basic protection only, remediation is more involved.

Keep the test result with the house papers. Buyers increasingly ask, and a measured figure is worth more than a statement that the building was constructed to the guidance.

One caution on interpreting results. A reading just under the action level in a house with basic protection is not a reason to relax, because levels vary year to year with weather and with how the house is ventilated. If the figure is close to the threshold, repeat the test in a different year before deciding to do nothing.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required. Enter your postcode on PlanScope to see which ground and contamination documents your site is likely to need.

Frequently asked questions

Does radon affect my planning application?

Generally not directly. Radon protective measures are delivered through the Building Regulations, specifically requirement C1(2) and Approved Document C, rather than through planning conditions. Planning becomes involved where ground conditions raise a wider issue, such as contamination or mining legacy, in which case a ground gas assessment may be conditioned.

How do I find out if my plot is in a radon affected area?

Order a property-specific radon report against the postal address or the grid reference. The national maps produced by the UK Health Security Agency and the British Geological Survey are indicative and work at a grid scale, so they are a screening tool rather than evidence for building control.

What is the difference between basic and full radon protection?

Basic protection is a continuous radon barrier across the building footprint, sealed at every junction and service penetration. Full protection adds a means of depressurising the ground below, normally a sump and vent pipe on a ground bearing slab or a cross-ventilated void under a suspended floor. The property report states which is required.

Do I need to test for radon after the house is built?

Testing is not mandatory for a new dwelling, but it is the only way to know the level achieved. Passive detectors are left in place for three months, usually in a living room and a bedroom, and the result is adjusted to an annual average. Keep the result with the house papers.

Does an extension in a radon affected area need protection?

It can, and the position depends on the size of the extension relative to the existing dwelling and on whether the existing house has been tested. Sealing ground that was previously ventilated can raise levels in the existing house, so treat the whole property rather than the extension alone when assessing what is needed.

Sources and further reading

radonnew buildapproved document cbuilding regulationsground gasself build

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Constraints and Designations

View all →
Constraints and Designations7 min read

Correcting an error in a published constraints layer

A case officer cannot move a flood zone or redraw a listing. This sets out which body holds each primary record, what a correction request needs, and how to submit an application while one is pending.

Read article →
Constraints and Designations7 min read

When a designation boundary runs through part of a site

Split sites are assessed under two policy regimes at once. This covers establishing the boundary from the primary record, placing built form clear of it, and dealing with setting effects across the line.

Read article →
Constraints and Designations7 min read

Protected views and viewing corridors: testing a tall building

A protected view is defined geometry, so a tall building either intrudes on it or does not. Wireline studies from agreed assessment points answer that before any rendering is paid for.

Read article →
Constraints and Designations6 min read

Water neutrality: the constraint that stopped a housing market

Water neutrality requires a development to add nothing to total abstraction in its area. The duty arises under the Habitats Regulations, so it cannot be negotiated away.

Read article →
Constraints and Designations7 min read

Scheduled monuments: consent, setting and works that need it

Works to a scheduled monument need consent from the Secretary of State, not the council, and doing them without it is an offence. Development in the setting is a planning question instead.

Read article →
Constraints and Designations7 min read

Bathing and shellfish waters as a planning constraint

Bathing water and shellfish water designations bite on drainage rather than land use. How to find them, what the Environment Agency and your undertaker will say, and the conditions to expect.

Read article →