Flood, Drainage and SuDS

Raised access roads and refuge platforms on flood sites

8 min readBy PlanScope Editorial Team

Safe access is where flood affected schemes fail. Here is how hazard rating works along a route, what raising land does to levels elsewhere, and when refuge is defensible.

A raised access road flood site design is the answer to a question the flood risk assessment has already asked and failed: can people get in and out safely during the design event. National policy requires development to be safe for its lifetime, and safe access and escape is one of the things a council and the Environment Agency will not compromise on. Where the existing ground offers no dry route, raising the road, or providing a refuge, is the physical response. Both come with consequences that need to be designed rather than asserted.

The order of preference is worth stating plainly. Dry access first. Then access where the flood hazard along the route is low enough to be safe. Then, only where neither is achievable, refuge with an agreed evacuation plan. Moving down that list gets progressively harder to defend.

When raising the access is the only option left

Raising an access road makes sense on a site where the building platform can be kept dry but the route to it crosses a shallow flow path, and where the volume of fill involved is modest. A 60 metre stretch of driveway raised 400 millimetres to keep it above the design level is a proportionate solution.

It stops making sense in three situations. Where the route crosses the deeper part of the floodplain, because the fill volume and the flood storage loss become substantial. Where the road is the only conveyance route for flood flow, so raising it acts as a dam. And where the raised route has to connect to a public highway that itself floods, which achieves nothing beyond a dry first 60 metres.

Check the receiving highway before you design anything. The route has to work all the way to land outside the flood extent, and a modelled depth on the adopted road two junctions away defeats the whole strategy.

The depth and velocity criteria the route must meet

Safety along a route is assessed on the combination of depth and velocity rather than depth alone, because 200 millimetres of fast water is more dangerous than 400 millimetres of still water. The hazard rating approach from Defra and Environment Agency research combines flood depth with velocity and a debris factor to produce a hazard value, with bands running from caution through danger for some, danger for most, and danger for all.

Condition along the route Typical position
Dry in the design event including climate change allowance Acceptable, and the outcome to aim for
Shallow, slow water with a low hazard rating Often acceptable for less vulnerable uses with a flood warning and evacuation plan
Depths or velocities in the danger for most band Not acceptable as an access route
Any depth over a route used by more vulnerable occupiers Resisted, because evacuation assumptions do not hold

Present the assessment along the route, not at a single point. A section along the centreline with modelled water levels for each return period, and a table of depth, velocity and hazard rating at intervals, is what a consultee can check. The vulnerability classification of the development matters too, because what is acceptable for a warehouse is not acceptable for housing, and housing for older or less mobile occupiers is treated more strictly again.

What raising land does to flood levels elsewhere

Fill placed in a floodplain displaces water. A raised causeway also alters where water can flow, which can raise levels upstream and concentrate flow at the ends of the embankment.

Three things belong in the design. Flow openings, sized by the model rather than by rule of thumb, so the raised road does not sever the floodplain. Compensation for the storage volume lost, provided level for level where the authority requires it. And an assessment of the effect on third party land, because an increase in flood level on a neighbour's property is the objection that ends applications.

Scour at the ends of an embankment and at the flow openings needs detailing, and the raised surface itself needs drainage that does not simply discharge into the floodplain at a concentrated point. Both details belong in the Drainage Strategy rather than being left to the contractor.

Where the scheme is in Flood Zone 3a and the exception test applies, the access strategy is part of the safety limb of that test, so the argument in the Exception Test has to be consistent with what the levels drawings show.

Refuge platforms and their limits

A refuge platform is a raised area within or adjacent to the site where people and vehicles can wait above the flood level until the event passes. It is a genuine solution in a narrow set of circumstances and an oversold one in many others.

What makes a platform work: an area large enough for the number of people and vehicles it serves, a dry route to it from every building, a level above the design flood level with freeboard, and an agreement with the emergency planning function that it forms part of a workable plan. What undermines it: no shelter, no services, no toilets, no arrangement for how long people might be there, and the simple human fact that people do not walk to a platform in the dark and the rain when their instinct is to drive out.

Refuge is not normally acceptable as the strategy for more vulnerable development. A care home or a school on a site where the only strategy is refuge is unlikely to be supportable, whatever the plan says, because evacuation of less mobile occupiers cannot be assumed.

Vertical refuge inside the building, meaning an upper floor above the flood level, is sometimes offered. Treat it as a residual measure for a rapid event, not as a substitute for access, and expect the Environment Agency to say the same.

Levels, freeboard and drainage of the raised surface

Get the levels arithmetic in one place and keep it consistent across every drawing. The chain runs: modelled flood level for the design event, plus the relevant climate change allowance, plus freeboard, giving the minimum finished level.

Freeboard requirements vary, with 300 millimetres above the design level a common expectation and some authorities asking for more. State the figure you have used and its source. Then check the finished floor levels, the raised road crest, the refuge platform level and the site drainage against the same datum, because a mismatch between the flood risk assessment and the levels drawing is one of the most common reasons a scheme goes back round the loop.

Raised surfaces also change the surface water design. A raised road sheds water to its edges, and the receiving swale or ditch has to have capacity when the floodplain itself is full, which is precisely when it cannot discharge. Basements on the same site add another layer of difficulty, as set out in basement development and flood risk.

Landscape and accessibility consequences

A causeway 600 millimetres above the surrounding land, with a retaining edge and a handrail, is a structure. On a rural site next to a river it is often the most visible element of the whole scheme.

Design it as landscape. Graded slopes rather than vertical retaining walls where space allows, planting that settles the edges, alignment that follows a hedge line or field boundary rather than cutting across it, and levels that tie back into existing ground rather than stopping abruptly at the boundary.

Accessibility is the constraint architects hit last and should consider first. An accessible approach needs gradients within the limits in the Building Regulations guidance, which on a 600 millimetre rise means a considerable length of ramp or a carefully designed profile. Steps with a separate ramped route often fit better than a single compromise gradient. Where a refuge platform is part of the strategy, the route to it has to be usable by the people who would need it.

The evidence to submit

A submission that gets through consultation without a holding objection usually contains the same package.

  1. A topographical survey tied to Ordnance Datum, showing existing levels across the site and along the access route to the point where it leaves the flood extent.
  2. Hydraulic modelling outputs giving depth and velocity along the route for the design event with the climate change allowance, and for a more extreme event as a sensitivity check.
  3. A hazard rating assessment along the route, presented as a table and a plan.
  4. Levels drawings showing the raised road crest, finished floor levels, refuge platform level and freeboard, all to the same datum.
  5. A flood storage compensation calculation where land is being raised, with the volume accounting by elevation band.
  6. A flood warning and evacuation plan, with evidence that the emergency planning function has been consulted where refuge is relied on.

Pull the narrative together in the Flood Risk Assessment and keep the figures identical to those on the drawings. Pre-application engagement with the Environment Agency and the lead local flood authority is worth the fee on any site where the access strategy is finely balanced, because a holding objection after submission costs far more time than the pre-application response does.

This is general guidance, not legal advice. Check the position with your local planning authority, the Environment Agency and a qualified engineer before relying on it.

Enter your postcode on PlanScope to see which flood and drainage reports your site is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

What counts as safe access on a flood affected site?

Dry access in the design event including the climate change allowance is the outcome to aim for. Where that is not achievable, a route with a low flood hazard rating may be accepted for less vulnerable development with a flood warning and evacuation plan. Refuge is a last resort.

How is flood hazard along an access route assessed?

By combining modelled depth with velocity and a debris factor to produce a hazard rating, using the approach from Defra and Environment Agency research. The bands run from caution through danger for some, danger for most and danger for all, and the assessment should be presented along the route rather than at one point.

Does raising an access road need flood storage compensation?

Yes, where the fill sits in the floodplain. Placed fill displaces water, so the lost volume has to be replaced, normally level for level, and the design also needs flow openings sized by the model so the raised road does not sever the floodplain or raise levels upstream.

Is a refuge platform acceptable for housing?

Only in narrow circumstances, and it is normally resisted for more vulnerable development such as care homes or schools. A workable platform needs capacity for the people and vehicles it serves, a dry route from every building, freeboard above the design level and agreement with the emergency planning function.

How much freeboard is required above the design flood level?

Requirements vary between authorities, with 300 millimetres above the design level including the climate change allowance a common expectation and some asking for more. State the figure used and its source, and apply the same datum to floor levels, the road crest and any refuge platform.

What if the public highway outside the site also floods?

Then raising the internal access achieves little. The route has to work all the way to land outside the flood extent, so check the modelled depths on the adopted highway beyond the site boundary before designing the levels. A dry first 60 metres is not safe access.

Sources and further reading

flood risksafe accesssite levelsrefugearchitecture

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Blue roofs in the drainage calculation

The hydraulics of roof attenuation are straightforward; getting the volume credited is not. This covers storage depth against structural loading, flow control modelling, failure modes and the drawings reviewers expect.

Read article →
Flood, Drainage and SuDS7 min read

Choosing between the central and upper end climate allowance

The Environment Agency publishes bands rather than a single climate uplift. This explains how vulnerability classification, flood zone and catchment select the allowance, and how to document the choice so a reviewer can check it.

Read article →
Flood, Drainage and SuDS8 min read

Local resilience forums and flood emergency planning

Flood emergency planning sits with local resilience forums under the Civil Contingencies Act, not with the planning system. Here is how the two meet.

Read article →
Flood, Drainage and SuDS8 min read

Sewerage design standards and sewer adoption approval

Adoptable sewers are designed to the sewerage undertaker's standards, not the council's. Here is what governs the layout, how the application runs and where the programme slips.

Read article →
Flood, Drainage and SuDS6 min read

Flood Re and what buyers will ask about

Homes built on or after 1 January 2009 cannot use Flood Re, so new build insurance rests on the open market. What to hand over at completion and what not to promise.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens and the liability they create

Screens protect a culvert and introduce a new flood risk upstream. How blockage is modelled, which designs degrade gracefully, and who maintains the structure afterwards.

Read article →