Relevant buildings and the Article 9A fire statement duty

7 min readBy PlanScope Editorial Team

A relevant building contains two or more dwellings or educational accommodation and is 18 metres or seven storeys. Here is how to measure it before you submit.

Whether your scheme is a relevant building fire statement case turns on a single definition in Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015. A relevant building is one that contains two or more dwellings or educational accommodation and meets the height condition: 18 metres or more in height, or seven or more storeys. Hit that and the application cannot be validated without a fire statement on the published form. Miss it and no fire statement is required at planning stage at all, whatever the building control position.

The definition is mechanical, which is useful, because it means you can settle the question on the drawings before you submit rather than discovering it when the validation officer writes back.

What Article 9A requires

Article 9A was inserted into the 2015 Order to give effect to Planning Gateway One. Where an application for planning permission relates to development involving one or more relevant buildings, it must be accompanied by a fire statement in the form published by the Secretary of State. The Health and Safety Executive is a statutory consultee on those applications, acting through the Building Safety Regulator function.

Two points are frequently misread. The duty attaches to the application, not to the building's eventual use, so an outline application capable of delivering a relevant building engages it. And the fire statement is a planning document about the matters planning can influence: site layout, access and water supplies for the fire service, the position of the building relative to others, and the principles of the emergency evacuation strategy. It is not the building control fire strategy in miniature.

The consultee response can shape the layout materially, which is why the statement belongs in the design conversation and not at the end of it. The product page on the Fire Statement sets out what the document covers.

The height condition, measured properly

Height is measured from ground level to the floor surface of the topmost storey, ignoring any storey that is a roof-top machinery or plant area or consists exclusively of machinery or plant rooms. That definition is the same one used across the higher-risk building regime, and it is not the same as the height to the ridge or to the top of a parapet.

Ground level for this purpose is taken at the lowest part of the surface of the ground adjacent to the building, which matters on a sloping site. A building that is six storeys on the uphill side and seven on the downhill side is measured from the low point.

Measurement Included Excluded
Height Ground level to top storey floor surface Parapets, roof, plant enclosures above top storey
Storeys Storeys containing accommodation Roof-top plant-only storeys, below-ground storeys in defined cases
Ground level Lowest adjacent ground surface Made-up levels not yet formed

Counting storeys without getting it wrong

Storey counting is the part that generates disagreement. A mezzanine may or may not be a storey depending on its area relative to the storey it sits in. A basement or lower ground floor may or may not count depending on its relationship to ground level. A plant-only top level is excluded.

The safe approach on a marginal scheme is to set out the count on a section drawing with each level named and a note explaining the treatment of any level you have excluded. Do that in the design and access statement as well as in the fire statement, because two readers will check it. Where the count genuinely sits at six or seven, assume the authority will take the higher reading unless your drawing removes the doubt.

A scheme that adds a storey during design development crosses the threshold silently. Put a check on the change control list.

Residential units, mixed use and student accommodation

The duty applies to buildings containing two or more dwellings and to those containing educational accommodation. In practice that covers blocks of flats, and it covers student accommodation and boarding accommodation where it falls within the educational accommodation description.

Mixed use buildings engage the duty when the residential element brings the building within the definition, so a tall building with commercial floors below and flats above is a relevant building. The commercial floors still count towards the height and storey figures, because the measurement is of the building rather than of the residential part.

Buildings containing a single dwelling do not engage it however tall they are. Hotels, offices and hospitals do not, which surprises people, because the higher-risk building definition for building control purposes does not map exactly onto the Article 9A planning definition. Two regimes, two definitions, both worth checking separately.

What falls outside the duty

Some applications relating to a relevant building do not require a fire statement. Applications for outline permission where fire safety is reserved, applications under section 73 or section 96A, applications for approval of reserved matters, applications for permission in principle and applications for technical details consent are treated differently, and the drafting in the Order sets out which are excluded.

Householder applications, changes of use not involving building work, and applications relating to buildings below the threshold are outside it entirely. Do not submit a fire statement where none is required. A document that is not a validation requirement still gets read and still attracts comments, and an unnecessary one can generate a consultation response the scheme did not need.

Where the building falls below the threshold but fire service access is still a planning issue, the right home for that is the design and access statement and the access strategy, not a form designed for a different purpose.

Where the duty overlaps with building control

Gateway One sits at planning. Gateway Two sits before construction begins and Gateway Three before occupation, both administered under the Building Safety Act 2022 framework by the Building Safety Regulator. The planning stage deals with what planning can control, and the later gateways deal with the detailed fire engineering.

The practical risk is inconsistency. A fire statement describing a single stair with an evacuation lift, followed by a Gateway Two submission describing something different, invites questions at the worst possible moment. Keep one version of the evacuation strategy and update both documents from it. Where a full Fire Safety Strategy to BS 9991 or BS 9999 is being developed in parallel, the planning statement should be a subset of it rather than a separate account.

Structural and ground matters run on the same programme and it is worth checking early whether the scheme also needs a Geotechnical Assessment, particularly where basement levels affect the storey count.

Checking the position before validation

Five minutes of checking saves a fortnight of invalidation.

  1. Take the height from the lowest adjacent ground level to the top storey floor surface, on a dimensioned section.
  2. Count the storeys, annotating any level you have excluded and why.
  3. Confirm the accommodation type: two or more dwellings, or educational accommodation.
  4. Confirm the application type, because some routes are treated differently under the Order.
  5. Check the authority's published validation checklist, since some list the fire statement explicitly and some rely on the Order.
  6. Where the answer is yes, use the published form rather than a bespoke document, because a non-standard format is a validation risk.

A fire statement must be prepared by someone with the necessary fire-engineering competence. This is one of the report types where a qualified professional is legally required rather than merely advisable, and an AI-assisted draft is a starting point for that professional and never a substitute for them. Reviewers who sign off documents of this kind can be approached through the professional directory.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is a relevant building for a fire statement?

Under Article 9A of the Town and Country Planning (Development Management Procedure) (England) Order 2015 it is a building containing two or more dwellings or educational accommodation that meets the height condition of 18 metres or more, or seven or more storeys. Applications relating to such a building must be accompanied by a fire statement on the published form.

How is the 18 metre height measured?

From the lowest part of the ground surface adjacent to the building to the floor surface of the topmost storey, excluding any storey that consists only of machinery or plant rooms. It is not the height to the ridge or the parapet. On a sloping site the measurement is taken from the low point, which can push a scheme over the threshold.

Do hotels and offices need a fire statement at planning stage?

No. Article 9A applies to buildings containing two or more dwellings or educational accommodation. Hotels, offices and hospitals fall outside it however tall they are, even though the higher-risk building definitions used for building control purposes are drawn differently. Check both regimes separately.

Does an outline application need a fire statement?

The Order treats several routes differently, including outline applications, reserved matters, section 73 and section 96A applications, permission in principle and technical details consent. Check the current wording of the Order and the authority's validation checklist rather than assuming, and do not submit a statement where none is required.

Who can prepare a fire statement?

Someone with the necessary fire-engineering competence. This is a report type where a qualified professional is legally required rather than recommended, and the Health and Safety Executive is a statutory consultee through the Building Safety Regulator function. An AI-assisted draft is a starting point for that professional, never a replacement.

Sources and further reading

fire statementgateway onedmpobuilding safety actvalidation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements8 min read

Piling near a railway, tunnel or sewer: asset protection

The asset owner's consent sits outside the planning permission. What triggers a separate process, what the agreement covers, and why it is usually the critical path.

Read article →
Fire, Structural and Basements8 min read

Retaining an existing frame: the retrofit appraisal

Where a plan expects reuse before demolition, the appraisal has to quantify capacity, condition and adaptability, and use the same assumptions as the carbon assessment.

Read article →
Fire, Structural and Basements7 min read

Basement under a protected tree: roots and consent

Cellular confinement spreads load above undisturbed roots and does nothing for an excavation. What actually decides whether a basement under a protected tree is possible.

Read article →
Fire, Structural and Basements6 min read

Basement waterproofing grades and what to show

The grade of internal environment drives the whole waterproofing design, and pump resilience is the part a planning officer will press hardest on.

Read article →
Fire, Structural and Basements6 min read

Basement impact assessment: the three strands councils want

A basement impact assessment is a framework, not a document. Three strands, three stages, an independent audit, and the strand applicants usually underestimate.

Read article →
Fire, Structural and Basements7 min read

Measuring height for the 18 metre fire statement threshold

Height for a fire statement is measured from the lowest adjacent ground level to the floor surface of the top storey, excluding roof-top plant. The storey count is a separate test and either one triggers the requirement.

Read article →