Responding to a GLA stage one report on a London scheme

7 min readBy PlanScope Editorial Team

A stage one report gives you a dated list of London Plan objections and a window to answer them before the borough decides. Here is how to use that window, and what the Mayor can do at stage two.

A stage one report is the Mayor of London's formal view on a planning application of potential strategic importance, issued within six weeks of the borough referring it, and it tells you exactly which London Plan policies the Greater London Authority thinks your scheme fails. Getting the stage 1 report response right matters because the same officers write the stage two advice, and unresolved stage one issues are what the Mayor later uses to direct refusal or take the application over. Treat the report as a negotiating document with a deadline, not as a verdict.

The referral itself is automatic. Applications caught by Schedule 1 to the Town and Country Planning (Mayor of London) Order 2008 must go to City Hall, and the familiar triggers are 150 or more houses or flats, buildings above 30 metres outside the City of London, and development on Green Belt or Metropolitan Open Land. Check the Order rather than working from memory, because the categories are longer than most people remember and a missed referral is a validation problem for the borough rather than for you.

What a stage one report actually says

The report runs through the scheme against the London Plan policy by policy, then ends with a paragraph confirming that the application does not yet fully comply and setting out what would need to change. That closing paragraph is the operative part. Everything above it is reasoning you can argue with.

Officers write to a standard sequence: principle of development, housing and affordable housing, urban design and tall buildings, heritage, inclusive design, sustainable development, and transport. Each section either confirms compliance, asks for information, or states an objection. The distinction between the three is worth marking up in the margin on your first read, because a request for information is quick to answer and an objection on principle is not.

The report also records whether the Mayor would be minded to allow the borough to determine the application. That sentence is not a commitment. It is a statement of position as at the date of the report.

Reading the strategic issues it raises

Sort the issues into three piles. The first is arithmetic: affordable housing percentage by habitable room and by unit, play space provision against the ten square metres per child standard, carbon reduction against the Be Lean, Be Clean, Be Green hierarchy, cycle parking against the London Plan minimums. These are answerable with a revised schedule and a short note.

The second pile is design judgement. Density, massing, dual aspect ratios and the design-led approach to capacity sit here, and they are usually where the GLA and the borough disagree with each other rather than with you. If your capacity argument was built properly, the material for the response already exists in your design and access work on optimising site capacity under policy D3.

The third pile is land use principle. Loss of industrial floorspace, loss of a public house, loss of office space, development on protected open land. These rarely soften. On industrial sites the no net loss position set out in London Plan industrial land policy is applied fairly literally by GLA officers, and a scheme that cannot demonstrate reprovision or intensification is in real trouble at stage two.

Responding before the borough decides

You have whatever time remains before the borough's committee or delegated decision, which in practice is often eight to sixteen weeks. Use it.

  1. Ask the GLA case officer for a meeting. Stage one reports name the officer and the GLA holds post-stage-one meetings as a matter of course for larger schemes.
  2. Send a written response that answers each numbered paragraph of the report in order, using the report's own paragraph numbers as headings.
  3. Submit revised drawings and revised technical documents to the borough, not only to City Hall, and tell both in writing that you have done so.
  4. Where you disagree, say so plainly and give the policy reading you rely on. Officers prefer a reasoned disagreement to silence.
  5. Ask the borough to record in its committee report which stage one matters have been resolved and how.

That last step is the one agents skip. The stage two report leans heavily on the borough's committee report, so a committee report that works through the stage one issues one by one does half your arguing for you.

Daylight and sunlight is the exception to the "answer everything" rule. GLA officers generally defer to the borough on neighbour amenity, so a dense-site assessment prepared on the approach described in BRE 209 guidance for dense London sites is better aimed at the borough's case officer.

Stage two and the Mayor's three options

When the borough has resolved what it intends to do, it refers the application back. The Mayor then has fourteen days to choose between three courses.

Option What happens Where it sits in the Order
Allow the borough to determine The borough issues its own decision notice Article 5 notification
Direct refusal The borough must refuse the application Article 6
Take over as local planning authority The Mayor determines it himself Article 7

Fourteen days is short. The stage two report is drafted from the stage one report plus the borough's committee report plus anything you have sent in between, so material arriving in the second week of that fortnight is unlikely to change anything.

Direction to refuse and taking the application over

A direction to refuse is the simpler of the two interventions. The Mayor directs, the borough refuses, and the applicant can then appeal to the Secretary of State in the usual way.

A takeover is different and the threshold is higher. Article 7 requires the Mayor to be satisfied that the development would have a significant impact on implementation of the London Plan, that it has effects reaching beyond the host borough, and that there are sound planning reasons to intervene. All three have to be met. Where the Mayor does take over, he becomes the decision maker, holds a public representation hearing, and the borough's resolution falls away.

Takeovers are most often associated with schemes a borough has resolved to refuse where the Mayor supports the housing output. That is why a borough refusal is not the end of a referable application, and why the stage one report is repays reading for signs of Mayoral support as well as Mayoral objection.

What changes between the two stages

Three things usually move. The borough's position hardens into conditions and a section 106 package. The technical evidence base is complete rather than indicative. And the policy backdrop may have shifted, because the London Plan is supplemented by guidance that is updated between stages more often than people expect.

What does not change is the stage one list. If an objection in the stage one report has not been answered on paper by the time of the stage two referral, assume it survives. Fire safety is a good example of an issue that cannot be deferred: Planning Gateway One requires the fire statement to be submitted with the application, and a Fire Statement that is still described as forthcoming at stage two invites an objection the Mayor does not need to argue hard for.

Programming both stages into the timetable

Build the referral into the programme at the point you agree a validation date with the borough, not later. Allow six weeks for the stage one report from referral, then your response period, then fourteen days from the stage two referral. For a major London scheme that means the Mayor's involvement adds roughly two months of fixed procedural time on top of the thirteen-week statutory determination period, before any extension of time agreement.

An illustrative sequence for a 220-unit scheme in an outer London borough: validation in week one, referral in week two, stage one report in week eight, applicant response and revised drawings in weeks nine to fourteen, committee in week twenty, stage two referral the following week, Mayoral decision a fortnight after that. Nothing about that programme is unusual, and it is still five months from validation to decision notice.

Diary the fourteen-day stage two window as soon as the committee date is fixed. It is the only part of the process where you have almost no time to react.

PlanScope can draft the supporting statements behind a referable application, including the Planning Statement and the Energy Statement, structured to UK planning policy and ready for a consultant to edit. Enter your postcode on PlanScope to see which reports your site is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How long does the Mayor have to issue a stage one report?

Six weeks from the date the borough refers the application. The report is published on the Greater London Authority's planning decisions pages and names the case officer dealing with it. If the six weeks pass without a report, the borough may proceed, but in practice boroughs wait for the Mayor's advice before taking a scheme to committee.

Which applications have to be referred to the Mayor?

Those caught by Schedule 1 to the Town and Country Planning (Mayor of London) Order 2008. Common triggers include 150 or more houses or flats, buildings above 30 metres outside the City of London, and development on Green Belt or Metropolitan Open Land. The Schedule contains further categories covering floorspace, waste and departures from the development plan, so read it rather than relying on the familiar triggers.

Can the Mayor refuse my application himself?

Only if he takes the application over under article 7 of the 2008 Order, which requires effects on London Plan implementation, effects beyond the host borough and sound planning reasons to intervene. The more common intervention is a direction to refuse under article 6, where the borough issues the refusal notice and the applicant can appeal to the Secretary of State.

Is there any point responding to a stage one report?

Yes. The same GLA officers write the stage two advice, and anything left unanswered at stage one is assumed to still apply. A written response that works through the report paragraph by paragraph, backed by revised drawings sent to both the borough and City Hall, is the most reliable way to shorten the stage two report.

How much time does a Mayoral referral add to the programme?

Roughly two months of fixed procedure: six weeks for the stage one report after referral and fourteen days for the Mayor's stage two decision after the borough resolves. That sits on top of the thirteen-week determination period for a major application and any extension of time agreed with the borough.

Sources and further reading

london plangla referralmayor of londonplanning processmajor applications

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in London

View all →
London7 min read

Wind microclimate assessment for a London tower

A usable wind assessment names its test locations, states the criteria and season for each, and includes consented but unbuilt neighbours in a cumulative scenario.

Read article →
London7 min read

Energy strategy: Be Lean, Be Clean, Be Green, Be Seen

The London energy hierarchy is four steps, and the fourth commits you to reporting metered performance for years after occupation. Here is what each stage has to evidence.

Read article →
London7 min read

Play space on a London podium: making the deck work

Podium play space is judged on whether it functions, not on whether it measures 10 m2 per child. Here is how supervision, loading, drainage and wind shape the deck.

Read article →
London7 min read

Housing design standards: space, aspect and dual aspect

London residential schemes are tested against the national space standard, a tighter ceiling height, a dual aspect expectation and limits on units per core. Those four together decide whether a layout works.

Read article →
London7 min read

Fire safety and policy D12 in a London application

Policy D12 of the London Plan asks every development to meet the highest standards of fire safety and asks major schemes for a statement from a suitably qualified independent assessor. It overlaps with Planning Gateway One without replacing it.

Read article →
London6 min read

Water consumption targets and how to reach 105 litres

The 105 litre target in London is delivered through the optional requirement in Part G of the Building Regulations, imposed by planning condition. Here is how the calculator works and which fittings actually get you there.

Read article →