Resubmit or appeal after refusal: comparing real costs

6 min readBy PlanScope Editorial Team

The free second application and the appeal both cost nothing to lodge. Where the money really goes, and how to read a refusal reason to pick the right route.

After a refusal you have two routes, and the fee position makes them look closer in cost than they are. A second application of the same character on the same site, by the same applicant, within 12 months of the refusal is normally free of fee under the Fees Regulations. An appeal to the Planning Inspectorate carries no fee at all. So on paper both options cost nothing, which is how people end up choosing badly.

The real costs are professional time, holding costs and the value of the months each route takes. Those differ sharply, and the refusal reason usually tells you which route the evidence supports.

The fee position for each route

The free second application, often called the free go, has conditions attached. Broadly: the earlier application must have been refused or withdrawn, the new one must be for development of the same character or description on the same site by the same applicant, and it must be submitted within 12 months of the decision on the earlier one. The earlier application must not itself have been a free go, and only one free application is available.

Change the character of the development substantially and the exemption falls away, which matters if the refusal pushes you towards a materially different scheme. A smaller version of the same extension qualifies. A loft conversion instead of a rear extension probably does not.

Appeals carry no fee. The Inspectorate does not charge for written representations, a hearing or an inquiry, and a householder appeal uses an expedited written procedure. What you pay for is the preparation.

Cost head Fresh application Appeal
Application or appeal fee Nil if the free go applies, otherwise the standard fee Nil
Drawings Revised drawings needed Usually none, you appeal what was refused
Written case Short covering statement Full statement of case addressing each refusal reason
Further technical reports Likely, if information was the issue Only if already before the council
Elapsed time to a decision Eight weeks from validation, plus design time Months, with the current figures published by the Inspectorate
Holding cost Shorter Longer

Timescales and the holding cost

A resubmission runs on the same eight-week clock as any householder or minor application, plus however long the redesign takes. An appeal runs on the Inspectorate's timetable, and the householder appeal service is quicker than the full written representations route but still measured in months.

Check the Inspectorate's published timeliness figures rather than relying on anyone's recollection, because they move. Then price the delay: finance on the plot, rent on a property you cannot yet move into, a contractor's quotation that expires, materials inflation over a build pushed into the next year. On a householder project the holding cost is often the largest single number in the comparison and the one nobody writes down. Building control charges sit alongside all of this on a separate timetable, as set out in building control charges alongside the planning fee.

What a refusal reason tells you about the odds

Read the reasons as a diagnosis.

A reason about missing or inadequate information points to resubmission. The council has not rejected the scheme, it has rejected the evidence, and the cure is a report or a drawing.

A reason about a detail of the design, scale or materials also points to resubmission, because the officer has effectively told you what to change. One honest caveat: the officer's report sometimes reveals that the detail was the polite reason and the real objection is the principle.

A reason that turns on policy interpretation points to appeal. If the dispute is whether the Green Belt exception applies, or whether harm to a heritage asset is less than substantial, no amount of redesign resolves it and an inspector is the person who decides.

A reason about neighbour amenity sits in the middle. Sometimes a metre of setback fixes it. Sometimes the objection is to the development existing at all.

When the free go applies to a resubmission

The free go is a reason to resubmit, not a reason to resubmit badly. Two mistakes recur.

The first is submitting the same scheme with a cover letter arguing the council was wrong. That is an appeal dressed as an application, and it tends to produce a second refusal in the same terms.

The second is using the free go too early. You get one. If the revised scheme is a guess at what the officer wants, you have spent it. Ask for a meeting or pre-application advice on the revision first, pay for that advice if it is charged, and then submit something the officer has already indicated they can support.

Risk of a second refusal on the record

A second refusal does three things. It confirms the authority's position in writing, which makes a later appeal slightly harder because the inspector reads two sets of reasons rather than one. It sits on the planning register, where a purchaser or a lender will find it. And it uses up the free go, so the third attempt costs the full fee.

Costs awards in appeals run on unreasonable behaviour rather than on the outcome, so an unsuccessful appeal does not ordinarily cost you the council's expenses. But repeatedly appealing the same refused scheme without addressing the reasons is the kind of conduct a costs application is made about.

Cases where only an appeal will do

Four situations where redesign is not the answer.

  1. A policy interpretation dispute, where the question is what the development plan or national policy means rather than what the building looks like.
  2. A refusal against officer advice, where the professional assessment on the file already supports the scheme.
  3. A refusal on a point of fact you can prove, such as a measurement, a lawful use or an established boundary.
  4. A condition you cannot live with, where an appeal under section 78 against the condition leaves the permission intact.

Non-determination is a fifth route rather than a reason: where the authority has missed the statutory period and will not agree an extension, an appeal against non-determination is available, though it hands the decision to an inspector without the benefit of an officer report.

Making the decision on evidence

Work through it in this order.

Read the officer's report, not only the decision notice, because the report says what the officer actually thought. Identify which of the reasons are curable by design and which are matters of principle. Price both routes including the holding cost. Ask whether pre-application advice on a revision is available and what it costs. Then choose.

And write the case properly whichever route you take. A Planning Statement that answers each refusal reason in turn, with the policy reference and the change made, does more work than a long document restating the merits of the scheme. For the fee position on applications that fall outside the exemption, see how planning fees are indexed each April, and for the cost of the documents themselves, PlanScope pricing.

Appeal decisions on comparable schemes are indicative of how inspectors have approached an issue rather than binding precedent, so use them to frame an argument rather than to predict a result.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is a second planning application after refusal free?

Normally yes, under the Fees Regulations, provided it is for development of the same character on the same site by the same applicant and submitted within 12 months of the earlier decision. Only one such application is available, and the earlier application must not itself have been a free one. Changing the character of the proposal substantially removes the exemption.

Does an appeal cost anything?

There is no fee to appeal to the Planning Inspectorate, whether by written representations, hearing or inquiry. The cost is preparation: a statement of case answering each refusal reason, and professional input where the dispute is technical. Costs awards between the parties are made for unreasonable behaviour, not simply for losing.

How long does a householder appeal take?

The householder appeal service uses an expedited written procedure and is quicker than full written representations, but it is still measured in months rather than weeks. The Inspectorate publishes current timeliness figures, which move, so check those rather than relying on a figure quoted from a previous case.

Can I appeal just one condition?

Yes. An appeal under section 78 of the Town and Country Planning Act 1990 can be made against a condition, leaving the permission itself in place while the condition is reconsidered. Take care where a condition must be discharged before works start, because an appeal does not pause the permission's time limit for implementation.

Will a second refusal hurt a later appeal?

Slightly. The inspector reads two sets of reasons rather than one, and the authority's position is on the record twice. The second refusal also appears on the planning register where purchasers and lenders will see it, and it uses up the fee exemption, so a third attempt costs the full application fee.

Sources and further reading

refusalappealplanning feesresubmissionhouseholdercosts

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting7 min read

Licences to occupy the highway during construction

Highway occupation charges accrue whether or not work is happening, and they sit outside the planning fee and the building control charge. On an urban site they run for the whole programme.

Read article →
Costs, Fees and Budgeting7 min read

Commuted sums for open space maintenance explained

Councils price open space maintenance as area by annual rate by commutation period, then ask for it as a lump sum in the section 106 agreement. Here is how the figure is built and how the drafting changes what you pay.

Read article →
Costs, Fees and Budgeting7 min read

Budgeting a public exhibition for a major scheme

An exhibition that produces a photograph of a full room and no analysis has spent money without buying anything. The budget should follow what the statement has to prove.

Read article →
Costs, Fees and Budgeting8 min read

Certificate C and D: notice and advertising costs

Certificates C and D are the only ownership certificates that require advertising, and the newspaper notice decides your submission date rather than the other way round.

Read article →
Costs, Fees and Budgeting9 min read

Nutrient credits and what drives their price

A nutrient credit buys a legally secured, monitored reduction held for the lifetime of your development in the same catchment. Price follows from land value, duration and the budget calculation.

Read article →
Costs, Fees and Budgeting8 min read

Hazardous waste consignment costs on a demolition

On a demolition budget the line that moves most is the classification of the material, not the tonnage. Here is how consignment notes, tax bands and on-site reuse change the total.

Read article →