Flood, Drainage and SuDS

Section 104 sewer adoption and the standards behind it

6 min readBy PlanScope Editorial Team

A section 104 agreement transfers your new sewers to the water company. Here is what it covers, the design standards applied, where sustainable drainage falls outside it, and how to sequence it against the build programme.

A section 104 adoption agreement is the contract under which a sewerage undertaker agrees to take over the foul and surface water sewers you are about to build, so that on a date after completion they stop being your liability and become the water company's. It is made under section 104 of the Water Industry Act 1991, it is negotiated before construction starts, and it is backed by a bond. Get it wrong and you hand a management company a drainage network it cannot afford, or you hold a maintenance liability on a site you sold years ago.

What the agreement actually covers

The agreement covers gravity sewers, rising mains, pumping stations and, in some circumstances, lateral drains that serve more than one property. It does not cover private drains inside a plot boundary, highway drainage adopted by the highway authority, or watercourses.

Three parties matter. The undertaker signs the agreement and inspects the works. The developer builds to the approved design and pays the fees. The surety, usually a bank or a bond provider, stands behind the bond so that if the developer fails the undertaker can complete the works.

A well-run agreement has a technical approval stage, a construction stage with inspections at defined hold points, a vesting date when the sewers transfer, and a maintenance period before the bond is released. Programme it backwards from the first plot sale, because a plot that discharges to an unadopted sewer with no agreement in place is difficult to sell and harder to mortgage.

The design and construction standards applied

Since 1 April 2020 sewer adoption in England has run on a single national code of practice rather than the patchwork of company standards that preceded it. The design and construction guidance sets out pipe sizes, gradients, cover depths, manhole spacing, materials, testing regimes and the minimum information an application must contain.

Expect the technical reviewer to check the same short list every time:

  1. Pipe gradients against the self-cleansing velocity for the design flow, with any shallow runs justified.
  2. Manhole positions at every change of direction, gradient or diameter, and at defined maximum spacings.
  3. Cover levels and depth to invert, including where a sewer runs outside adoptable highway and needs an easement.
  4. Hydraulic design for the design storm, with no flooding of the network at the return period the code requires.
  5. Structural design of the pipe under the loading it will actually see, including construction traffic.
  6. Pumping station design, including storage for pump failure and the access arrangements for a tanker.

The separate question of how surface water leaves the site, and at what rate, belongs in the Drainage Strategy submitted with the planning application. A drainage strategy that assumed an attenuation rate the undertaker will not accept is the single most expensive thing to discover at technical approval stage.

Where SuDS components are and are not adoptable

This is where developers lose most time. A sewerage undertaker will adopt some sustainable drainage components and refuse others, and the split is not intuitive.

Broadly, piped systems, below-ground attenuation tanks, flow control devices and some permeable paving serving more than one property fall within what an undertaker will consider. Open features such as swales, basins, ponds and rain gardens are usually adopted by someone else, or by nobody, because they read as landscape rather than sewer. That leaves a maintenance gap that has to be closed by a management company, a highway authority agreement or a planning obligation.

Decide who holds each component before the layout is fixed. Our note on SuDS adoption and maintenance sets out the routes in more detail, and the position on the statutory approving body in England is still unsettled, which is covered in the piece on Schedule 3 SuDS approval.

One practical test: if a component needs a mower, a person with a rake, or a planting replacement budget, assume it is not going into the section 104 agreement.

Bonds, inspection fees and the timeline

The undertaker charges an administration and technical approval fee, an inspection fee usually calculated from the length and complexity of the network, and requires a bond set as a percentage of the estimated construction cost. Figures vary between companies and are revised annually, so take them from the current published developer services charges for your undertaker rather than from a previous scheme.

The bond is released in stages. A substantial part comes back at the vesting date, with a residue held through the maintenance period against defects found on the post-construction survey. That survey is normally a CCTV inspection of the whole network, and it is the moment a contractor's sloppy jointing becomes the developer's problem.

Timeline, realistically: technical approval takes weeks rather than days, the legal agreement runs in parallel, and neither should be started after groundworks. Build a sewer before the agreement is signed and you have built an asset the undertaker is entitled to refuse.

Interaction with the build programme

Planning conditions, the section 104 process and the housebuilding programme pull against each other. A condition requiring drainage details to be approved before work starts cannot be discharged until the design is settled, and the design cannot be settled until the undertaker has commented. Meanwhile the site needs surface water routed away from the works from week one, which is a temporary arrangement, not the adopted network.

Sequence it like this. Fix the outfall and the discharge rate during the planning application, using the Flood Risk Assessment and drainage strategy. Submit for technical approval as soon as the layout is frozen. Sign the agreement before the first pipe goes in. Keep as-built records from day one, because the undertaker will ask for them.

Common reasons a technical submission is rejected

Rejections cluster around a handful of avoidable faults. Levels that do not tie in with the highway design. Sewers routed through private gardens with no easement shown. Attenuation sized on a different storm from the one the planning drainage strategy used. Pumping stations with no adoptable access for a tanker, or sited so close to a plot that the odour and noise standoff cannot be met. Missing structural calculations for deep runs. And, frequently, a submission that simply contradicts the approved planning drawings.

The fix is boring and effective: one drainage model, one set of levels, one layout, shared between the planning consultant, the highway engineer and the drainage designer.

What happens if adoption is never completed

Sewers built without an agreement do not vanish. They may be adopted later through a different route, they may be taken on by a private management company, or they may sit with the freeholder. Each option has a cost and each affects the residents who bought the houses.

A site left in that position tends to surface years later, when a manhole collapses and nobody can establish who owns it. That conversation is much easier if the as-built drawings, the CCTV survey and the correspondence with the undertaker were kept. This is general guidance, not legal advice; check the position with your sewerage undertaker and your local planning authority before relying on it.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. Enter your postcode on PlanScope to see which drainage and flood reports your site is likely to need.

Frequently asked questions

When should a section 104 application be submitted?

As soon as the site layout and levels are frozen, and always before groundworks begin. Technical approval and the legal agreement run in parallel and both take weeks. Building sewers before the agreement is signed leaves the undertaker entitled to refuse them, which pushes the network into private ownership and complicates plot sales.

Does a section 104 agreement cover sustainable drainage?

Partly. Piped systems, below-ground attenuation, flow controls and some shared permeable paving can fall within an agreement. Open features such as swales, basins and ponds are usually excluded because they need landscape maintenance. Anything left out needs a management company, a highway agreement or a planning obligation to look after it.

What is the bond for?

The bond is security held by the sewerage undertaker so that the network can be completed if the developer fails during construction. It is set as a percentage of the estimated cost of the sewer works, released mostly at the vesting date, with a residue retained through the maintenance period against defects found on the post-construction survey.

How is section 104 different from lead local flood authority approval?

The lead local flood authority comments on surface water drainage as a consultee on the planning application and looks at flood risk and discharge rates. The sewerage undertaker decides, separately, whether it will own and maintain the pipes afterwards. A design can satisfy one and fail the other, which is why both should be resolved together.

Who adopts the drainage in an estate road?

Highway drainage serving an adoptable road normally transfers to the highway authority under a section 38 agreement, not to the sewerage undertaker. Gullies and carrier drains sit with the highway, while the sewer they discharge into may sit with the water company. Establish the adoption boundary early because it changes who maintains each length.

Sources and further reading

section 104sewer adoptiondrainagesudswater industry actdevelopers

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Blue roofs in the drainage calculation

The hydraulics of roof attenuation are straightforward; getting the volume credited is not. This covers storage depth against structural loading, flow control modelling, failure modes and the drawings reviewers expect.

Read article →
Flood, Drainage and SuDS7 min read

Choosing between the central and upper end climate allowance

The Environment Agency publishes bands rather than a single climate uplift. This explains how vulnerability classification, flood zone and catchment select the allowance, and how to document the choice so a reviewer can check it.

Read article →
Flood, Drainage and SuDS8 min read

Local resilience forums and flood emergency planning

Flood emergency planning sits with local resilience forums under the Civil Contingencies Act, not with the planning system. Here is how the two meet.

Read article →
Flood, Drainage and SuDS8 min read

Sewerage design standards and sewer adoption approval

Adoptable sewers are designed to the sewerage undertaker's standards, not the council's. Here is what governs the layout, how the application runs and where the programme slips.

Read article →
Flood, Drainage and SuDS6 min read

Flood Re and what buyers will ask about

Homes built on or after 1 January 2009 cannot use Flood Re, so new build insurance rests on the open market. What to hand over at completion and what not to promise.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens and the liability they create

Screens protect a culvert and introduce a new flood risk upstream. How blockage is modelled, which designs degrade gracefully, and who maintains the structure afterwards.

Read article →