Costs, Fees and Budgeting

Section 106 monitoring fees and what is reasonable

6 min readBy PlanScope Editorial Team

Monitoring fees in planning obligations have had a statutory footing since September 2019. Regulation 122(2A) sets the ceiling, and the calculation behind the figure is fair game.

A section 106 monitoring fee is a sum an authority asks for inside a planning obligation to cover the cost of checking that the obligation is complied with. Since 1 September 2019 the power to charge one has sat in regulation 122(2A) of the Community Infrastructure Levy Regulations 2010, and the same provision sets the ceiling: the sum must not exceed the authority's estimate of its cost of monitoring the development over the lifetime of the obligation, and it must be of a reasonable scale having regard to the development. Those two words, estimate and reasonable, are where the negotiation happens on every major scheme.

Where the power comes from

Before the 2019 amendment, monitoring fees sat in a grey area. Authorities charged them, applicants paid them, and the legal basis was argued about rather than settled. The Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019 changed that by inserting regulation 122(2A) and (2B), which permit an obligation to provide for the payment of a monitoring fee and then constrain what that fee can be.

The constraint has two limbs. The sum must not exceed the authority's estimate of its own cost of monitoring the development over the lifetime of the obligation. And the fee must be of a reasonable scale having regard to the scale and kind of the development. An authority that cannot show a costing behind the figure is in difficulty on the first limb, whatever it says about the second.

Planning Practice Guidance on planning obligations puts the same point in plainer words: monitoring fees should be proportionate, should reflect the actual cost of monitoring, and should not be used to fund the wider running of the planning service.

How authorities build the number

Most authorities that publish a methodology do one of three things. Some price each obligation individually by estimating officer time per trigger, which is the approach that survives scrutiny best because it produces a schedule you can argue with line by line. Some apply a fixed sum per obligation, often with a cap on the total. Some apply a percentage of the value of the financial contributions secured, which is the method most likely to produce a figure that has no relationship to any monitoring actually done.

The percentage approach is the weak one. A scheme with a single large education contribution paid on first occupation costs almost nothing to monitor, while a scheme with a dozen small triggers spread over 15 years costs a great deal. Charging the first and not the second gets the position backwards. If the council has applied a percentage, ask for the estimate of monitoring cost that regulation 122(2A) requires, because the percentage is not itself an estimate of anything.

Method What it prices Where it fails
Per obligation, officer time costed Each trigger, review and site visit Needs an authority to hold time records
Fixed sum per obligation, capped Administrative simplicity Blunt on long-tail obligations
Percentage of contributions The money, not the monitoring No link to actual cost, hard to defend

Testing the fee against the statutory tests

Regulation 122(2) still applies to the obligation as a whole. An obligation may only be a reason for granting permission where it is necessary to make the development acceptable in planning terms, directly related to the development, and fairly and reasonably related in scale and kind to it. A monitoring fee attached to an obligation that fails those tests falls with it.

The more useful question on a live negotiation is narrower. For each obligation in the draft deed, ask what the council will actually do to monitor it, how often, and at what officer grade. A covenant to submit a travel plan review every 12 months for five years has a real cost. A covenant to pay a commuted sum on implementation has almost none once the money is banked. The schedule that comes back from that exercise is usually shorter than the one the council opened with. The approach is the same one you would take when the section 278 highway works cost is built up line by line rather than accepted as a lump.

Challenging a fee you think is excessive

There is no appeal against a monitoring fee as such. What there is, in practice, are four routes.

  1. Ask for the calculation in writing, citing regulation 122(2A), and ask specifically for the estimate of cost over the lifetime of the obligation.
  2. Compare the fee with the authority's own published methodology or supplementary planning document, if it has one, and point out any departure from it.
  3. Offer an alternative structure: a lower fee with a mechanism for the authority to recover further reasonable costs if monitoring turns out to be heavier than estimated.
  4. Where the fee is a condition of the officer recommendation and the sum is disputed, raise it in the committee report stage rather than after resolution, because the deed is drafted to match the resolution.

Refusing to pay and appealing against non-determination is available, but the cost and delay of an appeal almost always exceeds the fee in dispute. That asymmetry is well understood on both sides of the table, which is why the argument is usually settled by correspondence.

Recording the fee in the deed

Get three things into the drafting. The fee should be a defined sum, payable on a stated trigger, rather than an open-ended indemnity for the council's costs. The deed should say what the fee covers, so the authority cannot later charge separately for the same work. And there should be a repayment or abatement provision if the permission is not implemented, because monitoring a development that never happens costs nothing.

Indexation is the other point worth watching. A fee indexed from the date of the deed to the date of payment is normal. A fee indexed and also reviewed periodically is double counting.

Budgeting for it on a major scheme

Treat the monitoring fee as part of the obligations line in the appraisal, not as a professional fee. On a scheme carrying affordable housing, education, open space, travel plan and biodiversity obligations, the fee will usually be the smallest item in that line and the one most likely to be forgotten until the deed is being engrossed. Put a placeholder in at the pre-application stage and refine it once the heads of terms are agreed.

It sits alongside the other cash calls that land between resolution and commencement, including the CIL liability calculated from the charging schedule and the commuted sum negotiated on a section 38 adoption. None of those three is a planning application fee, and all three are easy to miss in a first-pass appraisal.

For the application itself, the supporting documents are a separate budget line again. You can browse the 66 report types by category to see what a major scheme is likely to need, and PlanScope pricing sets out the free report, the £50 per report option and the Professional tier for agents producing several at once.

This is general guidance, not legal advice, and you should check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Are section 106 monitoring fees lawful?

Yes. Regulation 122(2A) of the Community Infrastructure Levy Regulations 2010, inserted with effect from 1 September 2019, expressly permits a planning obligation to provide for a monitoring fee. The sum must not exceed the authority's estimate of its monitoring cost over the lifetime of the obligation and must be of a reasonable scale for the development.

Can a council charge a percentage of the contributions as a monitoring fee?

Some do, but a percentage is not an estimate of monitoring cost and is the hardest method to defend. Ask for the underlying estimate that regulation 122(2A) requires. A scheme with one large payment on first occupation costs far less to monitor than one with many small triggers spread over years.

Is there an appeal against an excessive monitoring fee?

Not directly. The practical routes are to request the written calculation, compare it against the council's published methodology, propose an alternative structure such as a lower fee with a recovery mechanism, and raise the point before the committee resolution rather than after. Appealing non-determination usually costs more than the fee in dispute.

Is a monitoring fee refundable if the permission is never implemented?

Only if the deed says so. Ask for the fee to be payable on a commencement or implementation trigger, or for an abatement provision, because monitoring a development that never starts costs the authority nothing. This is a drafting point, not a statutory right, so it has to be negotiated into the agreement.

Does the monitoring fee count towards CIL or planning fees?

No. It is a separate sum secured inside the planning obligation, distinct from the application fee payable to the authority and from any Community Infrastructure Levy liability under the charging schedule. All three should appear as separate lines in a development appraisal.

Sources and further reading

section 106monitoring feeplanning obligationscil regulationsdevelopment appraisal

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting8 min read

Costing a stopping up order for a highway or footpath

Public rights do not lapse through disuse and planning permission does not override them. This covers the section 247 and 257 routes, what objectors actually argue about, and how to keep the order off the critical path.

Read article →
Costs, Fees and Budgeting7 min read

Costing an affordable housing review mechanism

Early and late stage review mechanisms are decided by their definitions, not their headline percentages. This covers the inputs that move the answer, who pays for the review and the caps to secure before signing.

Read article →
Costs, Fees and Budgeting7 min read

Costing an employment land assessment for an allocated site

On an allocated employment site the fee sits in evidence gathering, not analysis. This covers the marketing records councils expect, the suitability tests that decide it, and how to sequence the work.

Read article →
Costs, Fees and Budgeting7 min read

Costing an odour assessment for a kitchen or waste use

The fee for an odour assessment depends on whether the council accepts a qualitative risk based appraisal or expects dispersion modelling. Here is what sits behind each, and how to scope the work before you commission it.

Read article →
Costs, Fees and Budgeting6 min read

Costing a telecommunications compliance declaration for a mast

An ICNIRP declaration is produced by the operator's own radio engineers and closes the health issue. Siting and appearance are the only matters the council can decide on.

Read article →
Costs, Fees and Budgeting6 min read

Costing an equalities impact assessment for a public applicant

The public sector equality duty is continuing, so an equalities impact assessment has to be revisited at every material change. Budgeting for one document is the common mistake.

Read article →