Section 62A applications: applying direct to the Inspectorate
Where a council is designated as underperforming, section 62A allows an application to go straight to the Planning Inspectorate. The route is category specific and costs you the right of appeal.
A section 62A application is one made directly to the Planning Inspectorate instead of to the local planning authority, and it is available only where the government has designated that authority as underperforming. The power sits in section 62A of the Town and Country Planning Act 1990, inserted by the Growth and Infrastructure Act 2013. It is a narrow route, used rarely, and the decision is taken by an inspector rather than by the council.
Designation is not a judgement about whether a council is pleasant to deal with. It is a statistical exercise against published criteria, and it applies to a category of development rather than to every application the authority handles.
What section 62A allows
Where an authority is designated, an applicant may submit a relevant application directly to the Secretary of State, in practice the Planning Inspectorate, and the Inspectorate determines it. The procedure is set out in the Town and Country Planning (Section 62A Applications) (Procedure and Consequential Amendments) Order 2013.
The route covers applications for planning permission in the designated category and certain connected applications, including some approvals of details and applications to vary conditions on a permission granted through the same route. The council does not decide the application, though it is consulted and its development plan still applies. Section 38(6) of the Planning and Compulsory Purchase Act 2004 is unaffected, so the inspector determines the application in accordance with the development plan unless material considerations indicate otherwise.
Choosing the route is the applicant's decision. Designation does not compel anyone to bypass the council, and most applicants in a designated area continue to apply locally.
How an authority becomes designated
The government publishes designation criteria and assesses authorities against them, separately for major development and for non-major development. Two measures are used.
- Speed: the proportion of decisions made within the statutory period or an agreed extension of time
- Quality: the proportion of decisions overturned on appeal, measured against the authority's total decisions in the category
The specific percentage thresholds have been revised several times since 2013, and the assessment periods move each year, so read the current published criteria rather than relying on figures from an older article. Designations are announced by the department, reviewed periodically, and lifted when performance recovers.
The Levelling-up and Regeneration Act 2023 contains powers relating to the measurement of planning authority performance, and the detail of how they will be used sits in secondary legislation. Verify the position as at the date you are advising, because commencement has been staged.
Which applications can use the route
The category matters. An authority designated for major development does not open the route for a householder extension, and the reverse is equally true.
| Designation category | Applications that may use section 62A |
|---|---|
| Major development | Major applications as defined in the Development Management Procedure Order, in that authority's area |
| Non-major development | Applications below the major thresholds, excluding those outside the scope of the route |
Certain applications stay with the council whatever the designation. Listed building consent, advertisement consent and applications for a lawful development certificate are separate consent regimes. Where a proposal needs both planning permission and another consent, it is usually a poor idea to split the two between the Inspectorate and the council, because the decisions then run on unconnected timetables.
Applications under the route are not appeals, so the question of what an authority may lawfully take into account is the same as in a local application. That is a different question from the narrow scope of a prior approval, where the council may consider only specified matters.
How the Planning Inspectorate handles them
The Inspectorate validates the application, publicises it, consults the local planning authority and statutory consultees, and takes representations from neighbours and interested parties. An inspector then determines it, usually on the papers, with a site visit.
Local consultation is not lost. The council responds as a consultee and will normally set out how the proposal sits against its adopted policies. Parish councils, neighbours and amenity groups can make representations in the ordinary way. What changes is who weighs them.
There is no right of appeal against a section 62A decision under section 78, because the decision has already been taken at national level. The remaining challenge is judicial review on a point of law, which is a high bar and a short deadline. That asymmetry is worth weighing before choosing the route, since a refused local application leaves a full appeal available.
Fees and timescales
A fee is payable to the Secretary of State rather than to the council, calculated under the current planning fees regulations. Fees are indexed and change, so take the figure from the current schedule at the point of submission.
Determination periods follow the familiar pattern for the category of development, with the statutory clock running from validation. In practice the timetable depends on the Inspectorate's caseload, and the honest position is that the route has not been used often enough to give anyone reliable expectations about speed. Some applicants have found it quicker than a designated council, and others have not.
There is also a softer cost. A case officer in a local authority will often pick up the telephone about a drawing discrepancy or an ambiguous red line. A national case file is handled at arm's length, and the instinct is to write rather than to ring.
What to do instead in a slow authority
Designation is a signal, and acting on the signal locally is often the better move. Three tools exist and all of them are underused.
An agreed extension of time removes the pressure that makes a case officer refuse a scheme simply to beat the clock. A planning performance agreement sets a written timetable with named officers and agreed milestones, and larger authorities will enter one for a fee on a scheme of any size. And a properly used pre-application service settles the contested points before validation, which is where the time actually goes.
None of that helps where the authority will not engage at all. That is the situation the route was designed for, and in that narrow case it does the job.
Whether the route is worth using
Four considerations decide it in my experience.
- Whether the authority's poor performance affects your category of application at all, since designation is category specific.
- Whether your scheme depends on local negotiation, because planning obligations are harder to negotiate with a decision maker who has no ongoing relationship with the site.
- Whether the loss of the section 78 appeal right matters, which it does on a marginal scheme.
- Whether a section 106 agreement is needed, since the council remains the body that enforces obligations relating to its area.
Schemes that suit the route are policy compliant, evidentially complete and unlikely to need negotiation. Schemes that need a conversation about affordable housing tenure or a design compromise usually do better locally, even in a slow authority, where an agreed extension of time and a planning performance agreement are available.
The other practical point is that the evidence base has to be finished on submission. An inspector reading a national case file will not chase a missing report in the way a case officer sometimes does, so the supporting documents need to be complete and internally consistent. Where a scheme turns on a housing land supply argument, the numbers in the standard method for local housing need need to be set out properly, and where a permission is later varied the drafting questions covered in the note on when part of a permission survives apply in the same way.
Whichever route you choose, the submission pack is the same. Browse the planning report types to see what a complete application looks like for your category of development.
This is general guidance, not legal advice, and designation status changes. Check the current designation list and criteria on gov.uk, or take advice from a qualified professional, before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.
Frequently asked questions
Which councils can section 62A be used against?
Only those the government has designated as underperforming, and only for the category of development covered by the designation. Designation is assessed separately for major and non-major development against published speed and quality criteria. The list is announced by the department and reviewed periodically, so check the current position before planning a submission.
Is a section 62A application an appeal?
No. It is a first instance application for planning permission, decided by an inspector instead of by the council. The development plan still applies under section 38(6) of the Planning and Compulsory Purchase Act 2004, and the council is consulted. Because the decision is already taken nationally, there is no further right of appeal under section 78.
Can I use the route for a listed building?
Listed building consent is a separate consent regime and stays with the local planning authority. Splitting a scheme so that planning permission is decided nationally and listed building consent locally puts the two decisions on unconnected timetables, which rarely helps. Where both are needed, applying locally for both is usually the more practical course.
What does a section 62A application cost?
A fee is payable to the Secretary of State rather than the council, calculated under the current planning fees regulations. Fees are indexed and revised, so take the figure from the current schedule at the point of submission. Budget on the basis that the application itself has to be evidentially complete, since there is no informal chasing of missing documents.
Does the local community still get consulted?
Yes. The Planning Inspectorate publicises the application, consults the local planning authority and statutory consultees, and accepts representations from neighbours, parish councils and amenity groups. The consultation itself is not reduced. What changes is that an inspector rather than the council weighs the responses and determines the application.