Sequential Test or Exception Test for flood risk

6 min readBy PlanScope Editorial Team

Two flood tests, in a fixed order. Here is what triggers the exception test, what its two limbs require, and why each test usually fails.

The sequential test vs exception test flood question is easiest to hold onto as a sequence rather than a comparison. The sequential test asks whether the development could go somewhere at lower flood risk. Only if it cannot, and only for certain combinations of flood zone and vulnerability, does the exception test ask whether it should nonetheless be permitted here. You cannot reach the second without clearing the first, and passing the first does not remove the second.

Consultants lose weeks by running them together, or by producing an exception test for a scheme that never needed one.

The order the two tests run in

The sequential test comes first and applies to development in areas at risk of flooding. It is applied by the local planning authority on evidence the applicant supplies, and its outcome is binary: either reasonably available sites at lower risk capable of accommodating the development exist, or they do not.

If they do, the application should be refused and the exception test never arises. If they do not, the sequential test is passed, and attention turns to whether the zone and vulnerability combination triggers the exception test.

A Sequential Test (Flood Risk) may be produced as a standalone document or as a section within a wider Flood Risk Assessment. Either is acceptable. What is not acceptable is a report that describes site flood risk in detail and then asserts the sequential test is passed without showing any search.

The area of search is where the sequential test is usually won or lost.

The starting point is the whole administrative area of the authority. Narrowing it needs a reason that comes from the development rather than from the applicant, such as an operational requirement to be near an existing facility, a defined catchment for a school or health use, or the geography set by a development plan allocation.

Ownership, cost and the applicant's preferred trading area are not reasons. Nor is an area drawn tightly enough to exclude the sites that would otherwise appear.

Set out the search date, the site size range, the development type the alternatives must accommodate and the sources searched. Sources normally include the strategic housing and employment land availability assessments, local plan allocations, the brownfield land register and commercial listings at a stated date.

When the exception test is triggered

The exception test is not a general appeal against the flood zone. It applies to defined combinations of flood zone and vulnerability classification, which the planning practice guidance on flood risk and coastal change sets out in a table. Some combinations are acceptable without it. Some require it. Some should not be permitted at all.

Vulnerability classification is the input people get wrong. A use is classified as essential infrastructure, highly vulnerable, more vulnerable, less vulnerable or water compatible, and the classification is driven by the nature of the use rather than by its size. Basement dwellings, caravan sites for permanent residential use and emergency services facilities sit higher in the hierarchy than their floor area suggests.

Check the classification before designing anything, because a change in use mix can move the whole scheme from a combination that needs no exception test into one that does.

The two limbs, and how each is evidenced

The exception test has two limbs and both must be satisfied. They ask different questions and need different evidence.

Limb What it asks Typical evidence
Wider sustainability benefits Whether the development would provide wider sustainability benefits to the community that outweigh the flood risk Regeneration case, housing delivery contribution, brownfield reuse, access to services, employment, plan policy support
Safe for its lifetime Whether the development will be safe for its lifetime, without increasing flood risk elsewhere and, where possible, reducing risk overall Modelled levels with climate change allowances, finished floor levels and freeboard, flood resistance and resilience measures, safe access and egress, flood warning and evacuation plan, compensatory storage

The first limb is a planning argument and belongs with the policy case. The second is an engineering demonstration and belongs with the technical work. Drafting them in one section produces something that reads as neither.

Lifetime matters. Residential development is normally assessed over a long design life, which pushes the climate change allowance up and can change the finished floor level by a material amount. Check the current Environment Agency allowances for the river basin district at the time of writing, because they are revised.

Vulnerability classification and its effect

Two schemes on the same site can face different tests because of what is in them.

A single storey retail unit is less vulnerable. Flats above it are more vulnerable. A mixed scheme is assessed on the most vulnerable element it contains, which is why the ground floor commercial and upper floor residential arrangement is so common on constrained riverside sites: it puts the vulnerable use above the modelled level.

Where a scheme includes a basement with any residential use or sleeping accommodation, treat that element as the one that drives the classification, and expect the authority to look at it closely.

Exemptions, allocated sites and what does not need doing

Neither test applies to everything.

  1. Minor development and changes of use are generally excluded from the sequential test, subject to exceptions such as changes to caravan or camping sites.
  2. Householder extensions are generally excluded.
  3. Sites allocated in an adopted development plan where the sequential test was applied at plan-making stage do not usually need it reapplied, unless circumstances have changed.
  4. Development wholly in Flood Zone 1 with no risk from other sources usually needs neither test, though evidence may still be expected where surface water or other risk is recorded.

Confirm each of these against the current guidance rather than from a previous report, because the scope has been adjusted more than once and the position on other sources of flooding has tightened.

Why each test fails

The sequential test fails for reasons that are mostly about method. An area of search drawn to suit the applicant. A search with no cut-off date. A list of alternative sites with no reasons for discounting them. A search that only lists rejections, which reads as reverse engineering.

The exception test fails for reasons that are mostly about substance. Sustainability benefits asserted rather than evidenced, or benefits that would accrue anywhere and therefore say nothing about this site. Safety demonstrated for the building but not for access and egress, which is the point a lead local flood authority consultation most often lands on. Compensatory storage claimed without a volume calculation. Residual risk after mitigation left undiscussed.

One honest observation. The second limb of the exception test is the one that produces refusals at appeal, not the first. Inspectors are generally willing to accept a regeneration case. They are much less willing to accept a dry building reached along a flooded road, and a Drainage Strategy that ignores the route to the highway does not help.

Where the exception test is engaged, give it its own document or its own clearly headed section, following the Exception Test (Flood Risk) structure rather than folding it into the sequential test conclusion.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it, and verify the current flood risk guidance, climate change allowances and NPPF edition at the time of writing.

If you are working out which flood documents a site actually needs, enter your postcode on PlanScope and the constraint check will tell you. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Does passing the sequential test mean the exception test is not needed?

No. The sequential test asks whether reasonably available sites at lower flood risk exist, and passing it simply allows the application to be considered further. Whether the exception test applies then depends on the combination of flood zone and vulnerability classification set out in the planning practice guidance on flood risk and coastal change.

What are the two limbs of the exception test?

The development must provide wider sustainability benefits to the community that outweigh the flood risk, and it must be safe for its lifetime without increasing flood risk elsewhere and, where possible, reducing risk overall. Both limbs must be satisfied, and they need different evidence: a policy case and an engineering demonstration.

How is vulnerability classification decided?

By the nature of the use rather than its size, using the categories of essential infrastructure, highly vulnerable, more vulnerable, less vulnerable and water compatible. A mixed scheme is assessed on the most vulnerable element it contains, which is why ground floor commercial with residential above is common on constrained riverside sites.

Do allocated sites need a sequential test?

Usually not, where the test was applied when the site was allocated through the development plan and circumstances have not changed. That is worth confirming with the authority rather than assumed, because a site allocated some years ago may now sit in a different flood zone or face different surface water risk than when the plan was examined.

Why do exception tests fail at appeal?

Most often on the second limb rather than the first. Inspectors usually accept a regeneration or housing delivery case, but they resist schemes where safe access and egress has not been demonstrated, where compensatory storage is claimed without a volume calculation, or where residual risk after mitigation is left undiscussed.

Sources and further reading

flood risksequential testexception testplanning policyclimate change allowances

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Comparisons

View all →
Comparisons7 min read

Unilateral undertaking against a bilateral section 106 deed

Both instruments are made under section 106 and both bind the land. The difference is that a unilateral undertaking cannot contain any obligation on the authority.

Read article →
Comparisons7 min read

Householder application against a full application

The householder category is defined by what you are proposing, not chosen. It carries a different fee, lighter validation and the 12 week expedited appeal route.

Read article →
Comparisons7 min read

Prior approval against permitted development without it

Schedule 2 to the GPDO 2015 splits permitted development into rights you can simply exercise and rights suspended until prior approval. The difference governs certainty, fees and conditions.

Read article →
Comparisons6 min read

Extension of time agreement or renewing a permission

Two things that get confused. Extending the determination period is routine; extending the life of a permission is impossible, and section 73 cannot do it either.

Read article →
Comparisons7 min read

Deed of variation or a section 106A application

Two routes to change a planning obligation, with very different tests. Why section 106A is not a viability hearing, and when a fresh application beats both.

Read article →
Comparisons7 min read

Building notice or full plans application to building control

Two routes to building control approval under the Building Regulations 2010. What each involves, where a building notice is unavailable, and how completion certificates and regularisation work.

Read article →