Solar canopies and roof arrays over farm buildings

6 min readBy PlanScope Editorial Team

Class J covers solar equipment on non-domestic buildings within tight dimensional limits. A canopy over a yard is a separate structure needing permission, and roof capacity decides whether either is deliverable.

Roof-mounted solar on a farm building is usually permitted development. A solar canopy over a yard usually is not. That single distinction settles most questions about solar panels farm building planning, because Part 14 of the General Permitted Development Order 2015 grants rights for equipment installed on a building, and a canopy is a new structure in its own right.

Everything else follows from the detail of the class and from whether the building can carry the load.

The right for solar on non-domestic buildings

Class J of Part 14 permits the installation, alteration or replacement of solar photovoltaic or solar thermal equipment on the roof or wall of a non-domestic building. A farm shed, a grain store, a livestock building and a farm office all qualify.

The conditions that matter in practice are dimensional:

  • Equipment on a roof must not protrude more than 0.2 m beyond the plane of the roof slope.
  • The installation must not be higher than the highest part of the roof, excluding any chimney.
  • Siting must minimise the effect on the external appearance of the building and the amenity of the area.
  • The equipment must be removed as soon as reasonably practicable when no longer needed.

The class has been amended more than once, including changes to the capacity limits that used to apply to rooftop installations on non-domestic buildings, and prior approval requirements apply to some installations. Read the current text of Class J before relying on it rather than a secondary summary, and confirm with the authority whether prior approval is needed for the specific array.

Class K deals with standalone ground-mounted equipment within the curtilage, and its area and height limits are small enough that it suits a single array serving a building rather than a commercial installation.

Designated land and listed farm buildings

Inside a National Park, a National Landscape, a conservation area or a World Heritage Site, the class carries extra restrictions, typically on walls fronting a highway and on prominent roof slopes. Where a farmstead sits in a designated landscape, the sensible route is a short pre-application enquiry rather than an assumption.

Listed buildings are a separate regime. Solar equipment on a listed farm building, or on a building within the curtilage of a listed farmhouse, will normally need listed building consent regardless of the planning position, and the application should be supported by a Heritage Statement explaining the significance of the building and why the chosen slope causes least harm. Rear or courtyard-facing slopes hidden from the road are the usual answer.

Curtilage listing catches people out here. A modern portal frame shed put up in a listed farmstead may still be within the curtilage of the listed farmhouse depending on when it was built and how the group has been used, and the conservation officer will form a view on that before looking at the panels. Ask the question before the scaffold is booked.

Canopies over yards

A solar canopy over a feed passage, a collecting yard or a machinery area is a building. It has posts, a frame and a roof, and planning law treats it as an operational development that needs permission unless a class covers it.

Part 6 agricultural rights will not usually help. Those rights permit buildings and works reasonably necessary for the purposes of agriculture within the unit, and a structure whose primary purpose is generating electricity fails that test even where the electricity is used on the farm. Where the canopy really does provide shelter for stock or machinery and the panels are incidental to it, the argument is available and worth putting to the authority, though it turns on the facts and on how the structure is designed and used.

Design the canopy as a farm building and it will be assessed as one. Mono-pitch roofs at a normal agricultural pitch, dark cladding on the gables and a position tucked against the existing group read far better than a free-standing steel table in the middle of a yard.

For a full application, the assessment usually turns on landscape and visual effects, the relationship with existing buildings and any cumulative effect with other renewable development nearby. The evidence base for a countryside landscape case is the same as for any other rural building.

Structural capacity of existing roofs

This is where schemes fail after planning rather than during it. Farm roofs are designed for the loads they were built to carry, and many older buildings use fibre cement sheeting on widely spaced purlins with no allowance for an additional imposed load.

Get a structural appraisal before the grid application, covering:

  1. Purlin and rafter capacity with the array loading applied, including wind uplift on the panels.
  2. The condition and age of the sheeting, and whether it contains asbestos.
  3. Fixing details that transfer load to the frame rather than to the sheet.
  4. Access and edge protection for installation and later maintenance.

Fragile roof work is one of the more dangerous activities on a farm, and the health and safety requirements around working on fragile surfaces apply to the installation as much as to the building's owner. Where the sheeting needs replacing anyway, doing it as part of the solar project is usually the better sequence.

Grid connection and export

The connection, not the planning, is often the binding constraint. Installations connect under the distribution network operator's process, with smaller systems following the notification route and larger ones requiring an application and an offer before work starts. Connection offers can carry costs that change the economics entirely, and timescales that run to months.

Export limitation is the common workaround. Limiting export to the capacity the network can accept lets a larger array serve the farm's own demand, which suits operations with year-round load such as grain drying, refrigeration or milking. Say what the export arrangement is in the planning submission, because a scheme presented as meeting on-farm demand and then exporting at full capacity reads differently to a case officer.

Glint, glare and safeguarding

Reflection from panels is a planning matter near roads, railways and airfields. Where a site sits within an aerodrome safeguarding zone, or close to a Ministry of Defence technical site, the consultation will happen and a glint and glare study may be requested.

For roof arrays on existing buildings the effect is usually limited, because the roof plane already reflects light. For canopies and large ground-mounted schemes near a major road, expect the highway authority to ask the question. A study costs less than a refusal and takes a fortnight.

Set out the case in the planning statement with the energy use on the holding, the array capacity, the export arrangement and the visual assessment in one place. And check whether the works interact with any barn conversion proposals on the same holding, because a building converted to housing loses its agricultural rights.

Before commissioning anything, enter your postcode on PlanScope to see which supporting documents the application is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

Frequently asked questions

Is solar on a farm shed permitted development?

Usually yes, under Class J of Part 14 of the General Permitted Development Order 2015, which covers solar equipment on the roof or wall of a non-domestic building. The equipment must not protrude more than 0.2 m beyond the roof plane or rise above the highest part of the roof, and siting must minimise the effect on amenity.

Does a solar canopy over a farmyard need planning permission?

Normally yes. A canopy is a building rather than equipment on a building, so Class J does not apply. Agricultural rights under Part 6 cover works reasonably necessary for agriculture, and a structure whose main purpose is generating electricity falls outside that. Where shelter is the real function the argument is available on the facts.

Can I put solar panels on a listed farm building?

It needs listed building consent, and often planning permission as well. Consent decisions turn on the significance of the building and the visibility of the slope chosen, so rear or courtyard-facing roofs are the usual answer. Support the application with a heritage statement explaining significance and why the chosen position causes least harm.

What structural checks are needed before installing a roof array?

A structural appraisal covering purlin and rafter capacity with the array load applied, wind uplift, the condition and age of the sheeting including any asbestos content, and fixing details that transfer load to the frame. Fragile roof work carries real safety risk, and replacing aged sheeting as part of the project is often the better sequence.

Does the grid connection affect the planning application?

It affects the scheme rather than the permission. Connection offers from the distribution network operator carry costs and timescales that can change the economics, and export limitation is often used so a larger array can serve on-farm demand. State the export arrangement in the planning submission so the case officer sees the same scheme the network does.

Sources and further reading

solarfarm buildingspermitted developmentpart 14rural planninggrid connection

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Rural and Agricultural

View all →
Rural and Agricultural7 min read

Succession, tenancies and who applies for permission

Planning permission runs with the land, so a tenant, a landlord or a promoter can all apply over the same field. The safeguard is the ownership certificate and the 21 day notice to agricultural tenants.

Read article →
Rural and Agricultural8 min read

Redundant farm buildings and the demolition question

Most standalone agricultural buildings can be demolished without a planning application, yet demolition removes any later conversion right and brings asbestos, ecology and restoration duties with it.

Read article →
Rural and Agricultural7 min read

Diversifying into events in a working farmyard

Part 4 of the General Permitted Development Order allows 28 days of temporary use a year on land, but excludes buildings and anything inside a curtilage. Where that leaves farm events, and the evidence a permanent consent needs.

Read article →
Rural and Agricultural8 min read

Visibility splays onto a rural lane

A speed survey comes before the drawing. How visibility splays are derived on an unclassified lane, how to measure them, and the land control problem nobody plans for.

Read article →
Rural and Agricultural7 min read

Re-using a rural building in the Green Belt

Two limbs decide a Green Belt conversion: permanent and substantial construction, and preserving openness. Most applications satisfy the first and lose on the curtilage.

Read article →
Rural and Agricultural7 min read

Livestock buildings and the distance to housing

The only fixed figure is the 400 metre permitted development limit. Beyond that, odour modelling, ventilation design and manure management decide what separation is acceptable.

Read article →