Temporary works and the planning permission boundary

7 min readBy PlanScope Editorial Team

Planning permission authorises the development, not the scaffold over the footway or the crane jib over a neighbour's roof. Those come from the Highways Act and private agreements.

Planning permission authorises the development described in the application. It does not authorise the scaffold over the footway, the hoarding across the pavement, the crane jib swinging over the neighbour's roof, or the compound on the field down the road. Those come from separate regimes, mostly the Highways Act 1980 and private property rights, and the gap between the two is where construction programmes slip.

Most temporary works on the site itself need no separate planning permission, because Part 4 of Schedule 2 to the General Permitted Development Order 2015 grants rights for buildings, plant and machinery required temporarily in connection with operations being carried out on that land or on adjoining land. The rights come with conditions: remove the works when the operations finish, and reinstate the land. That is a useful starting point, and it has sharp edges.

For every temporary item, the useful question is whose land or airspace it sits in, and for how long. Planning permission is often the wrong thing to be asking about.

Item Usual consent Granting body
Site cabins, welfare, plant and stores within the site Permitted development under Part 4 of the GPDO 2015 None required, subject to the conditions
Hoarding or fence on the public footway Licence under the Highways Act 1980 Highway authority
Scaffold or staging over the highway Licence under section 169, Highways Act 1980 Highway authority
Building materials or an excavation in the street Licence under section 171, Highways Act 1980 Highway authority
Builders skip on the highway Permission under section 139, Highways Act 1980 Highway authority
Crane oversailing adjoining land Private licence or agreement The adjoining owner
Compound on land that does not adjoin the site Planning permission for a temporary use Local planning authority
Noisy construction works Prior consent under section 61, Control of Pollution Act 1974 Environmental health

Two of those catch people out. The Part 4 right covers land adjoining the site, so a compound on the field next door is usually fine while a compound two fields away is not. And the highway licences are discretionary: the authority can refuse, impose a fee, require a bond and specify pedestrian routing, so a programme that assumes a licence will be granted as a formality is optimistic.

Hoardings, scaffolding and highway licences

Highway licences are applied for separately from the planning application and usually cannot be obtained far in advance, because the authority wants dates. That creates a sequencing problem: the planning permission may be eighteen months old by the time you need the footway, and the traffic management conditions that made sense at determination may no longer match what the authority will accept.

Expect to provide a pedestrian management plan, a signed and lit diversion where the footway is fully closed, insurance to a specified limit, and a photographic condition survey of the surfaces you are taking over. Charges are set locally and usually run per square metre per week, which makes a hoarding line drawn generously an ongoing cost rather than a one-off fee.

Where a footway closure is unavoidable for a long period, raise it at pre-application. Highways officers who first see a full footway closure in a construction management plan submitted to discharge a condition tend to respond with a refusal and a request for redesign.

Crane oversail and third party rights

Airspace above a neighbouring property belongs to that neighbour at the heights a tower crane works in. Swinging a jib across it without consent is trespass, and an injunction is available. Planning permission is irrelevant to this: the authority has no power to authorise interference with private rights, and a condition requiring a crane will not help you.

The practical route is an oversailing licence negotiated with each affected owner, covering the period, the loads, insurance, out of hours restrictions and a fee. Start early, because an adjoining commercial owner has every incentive to negotiate slowly. Where the crane is tall or the site is near an aerodrome, aviation safeguarding adds a further step, and the Civil Aviation Authority's guidance on tall structures and crane notification is the reference point. Our separate piece on crane oversailing of third party land sets out what the licence normally contains.

Party wall matters sit in the same category of parallel regimes. Notices under the Party Wall etc. Act 1996 are a civil process with their own timescales, nothing to do with the planning permission, and the awards can constrain working hours and methods in ways your programme has to absorb.

Temporary structures within the red line

Inside the application boundary, the Part 4 right covers most of what a contractor brings on site. The limits worth knowing are these. The works must be required temporarily in connection with the operations, so a sales suite that stays open after completion falls outside. A concrete batching plant for a long project may be substantial enough that the authority treats it as development in its own right. Site lighting that affects neighbours or a nearby roost is better dealt with by agreement than by argument. And where the site is in a conservation area or contains a listed building, the right does not override the need for listed building consent for anything that touches the historic fabric, including temporary fixings for scaffold ties.

Trees are the other common collision. Protective fencing to BS 5837:2012 has to go up before anything else arrives, and a compound positioned over a root protection area is the most frequent cause of an enforcement complaint on a tight site. We look at that in temporary works and tree protection on constrained sites.

Construction phase conditions that bite

The conditions attached to the permission are the ones that decide whether the temporary works you have planned are allowed. Four recur.

  • A construction management plan or method statement, to be approved before work starts, which the authority will read against the licences you have actually obtained.
  • Hours of work, often 08:00 to 18:00 on weekdays and shorter on Saturdays, with no Sunday working, which may conflict with a highway authority requirement to work at night.
  • A construction traffic routeing and wheel washing requirement, sometimes with a condition survey of the route.
  • A piling method statement where ground conditions, contamination or adjoining structures are in play.

Those first two can contradict each other outright. A highway authority wanting lane closures only between 20:00 and 06:00, and a planning condition forbidding work before 08:00, is a conflict the applicant has to resolve, usually by a variation of the hours condition for a defined phase. Draft a realistic Construction Management Plan rather than a generic one, and pair it with a Construction Traffic Management Plan that names the routes.

Demolition adds its own layer, including prior notification for the method of demolition and restoration, a refurbishment and demolition asbestos survey, and in a conservation area the need for permission for relevant demolition. The documents that go with it are set out in our note on demolition and asbestos surveys in the planning submission.

Site compounds on separate land

A compound on land that does not adjoin the site needs planning permission for the temporary change of use, and the application is a small one that nobody wants to make in month three of a programme. Two alternatives exist. The temporary use provisions in Part 4 allow a limited number of days of temporary use in a calendar year, which suits a short duration need rather than a two year contract, and the day limits have been amended more than once so the current figures need checking.

The better approach is to include the compound inside the red line of the main application from the start, described as a temporary construction compound with a reinstatement condition. It costs nothing extra at that stage. Retrofitting it later means a fresh application, a consultation period and a determination that may land after you needed the land.

Sequencing the consents

Order the work backwards from the first day on site.

  1. Confirm what the permission conditions require to be approved before work starts, and submit those discharge applications early, because eight weeks is the normal determination period and some authorities take longer.
  2. Start oversailing and party wall negotiations with adjoining owners, which are the longest lead items because they depend on someone else's goodwill.
  3. Apply for highway licences once dates are firm, allowing for the authority's stated turnaround plus a contingency.
  4. Serve any section 61 application for prior consent on noise if the works are near sensitive receptors, which buys certainty against a later abatement notice.
  5. Erect tree protection and install the site boundary, then mobilise.

Getting that order wrong is the most common reason a scheme with a valid permission still cannot start. Enter the postcode on PlanScope to see which construction phase documents your authority is likely to ask for alongside the application.

This is general guidance, not legal advice; check the position with your local planning authority, your highway authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Do site cabins and welfare units need planning permission?

Usually not. Part 4 of Schedule 2 to the General Permitted Development Order 2015 grants rights for buildings, plant and machinery required temporarily in connection with operations on that land or adjoining land. The rights are conditional on removal when the works finish and on reinstating the land, and they do not extend to anything kept after completion.

Can the council stop me putting scaffolding over the pavement?

The highway authority controls that, not the planning authority. Scaffolding over the highway needs a licence under section 169 of the Highways Act 1980, and hoardings and material deposits need their own permissions. Licences are discretionary, carry fees usually charged by area and week, and often require a signed pedestrian diversion and insurance.

Does planning permission let a crane oversail my neighbour's land?

No. Airspace above a neighbouring property is theirs, and swinging a jib across it without consent is trespass that an injunction can stop. You need an oversailing licence from each affected owner, covering duration, loads, insurance and a fee. Begin those negotiations months before the crane is needed.

Where can a construction compound go?

On the site itself, or on adjoining land under the Part 4 permitted development right. Land that does not adjoin the site needs planning permission for a temporary change of use. The simplest route is to include the compound within the red line of the main application, described as temporary with a reinstatement condition.

What happens if working hours conditions conflict with highway requirements?

This is common where a highway authority will only allow lane closures at night and the planning condition forbids work before 08:00. The conflict is the applicant's to resolve, normally through an application to vary the hours condition for a defined phase, supported by a noise management plan and notification to affected residents.

Sources and further reading

temporary workshoardingscaffoldingcrane oversailconstruction managementhighways

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements6 min read

External wall information at Planning Gateway One

The planning-stage question on external walls is narrower than full compliance: can the building as drawn be built within the restrictions that apply to it. What to state, and how to keep conditions workable.

Read article →
Fire, Structural and Basements7 min read

Sequencing site investigation before an application

Ground investigation after the design is fixed tells you what went wrong. The order that works, what the desk study should assemble, and why monitoring sets the submission date.

Read article →
Fire, Structural and Basements7 min read

Geotechnical assessment and Eurocode 7 in planning

Planning needs feasibility and risk, not a finished foundation design. How Eurocode 7 and BS 5930 shape the investigation, and how to split the deliverables between planning and construction.

Read article →
Fire, Structural and Basements8 min read

Party wall and planning overlap for basement works

Planning permission does not authorise excavation next to a neighbour, and a party wall award does not authorise development. On a basement the notice periods are fixed by statute and usually decide the programme.

Read article →
Fire, Structural and Basements7 min read

Common basement policy restrictions in London boroughs

London basement schemes are governed by the borough's adopted local plan rather than national policy. The limits on depth, garden coverage and light wells follow a consistent pattern even though the numbers differ.

Read article →
Fire, Structural and Basements7 min read

Fire Statement for a change of use application

Converting an office block over 18m into flats creates a relevant building and triggers the article 9A Fire Statement requirement, even with no external alteration. The fire issues on a conversion are inherited rather than designed.

Read article →