Flood, Drainage and SuDS

Tidal locking and what it does to an outfall design

7 min readBy PlanScope Editorial Team

On an estuary frontage a gravity outfall is shut for hours each tide. The locked duration sets the storage volume, the critical rainfall duration and whether a pump is needed.

Tidal locking is the period when your outfall cannot discharge because the receiving water is higher than the pipe. On an estuary frontage that happens twice a day, for several hours each side of high water, and during that window every drop of runoff has to be stored on site. Size the attenuation for a rainfall event alone and the scheme floods on a dry spring tide.

The number the drainage strategy has to establish is the locked duration for the design condition. Everything else follows from it: storage volume, pipe gradients, whether a pump is needed, and whether the outfall is maintainable at all.

What tidal locking is in drainage terms

A gravity outfall discharges only while the water level in the pipe is above the level in the receiving water. As the tide rises past the outfall invert, discharge slows. Past the soffit it stops. A flap valve then holds the pipe shut against the incoming tide, and the system upstream begins to fill.

Locking is not a failure. It is the designed behaviour of a gravity outfall on a tidal watercourse, and every estuary drainage system in the country works this way. What changes between a working scheme and a flooded one is whether the storage volume matches the locked duration.

Two variables drive the duration. The outfall invert level relative to the tidal curve, which is a design choice within the limits the bank and the defence allow. And the tidal range on the day, which is not a design choice at all. A spring tide locks the outfall for considerably longer than a neap, so the design case has to be a high tide rather than a mean one.

Establishing the locked duration from tide data

Work from a predicted tidal curve for the nearest standard or secondary port, corrected for the site, and overlay the outfall soffit level on it. The locked duration is the period the curve sits above that level.

Then add the surge component. Extreme still water levels for the design annual probability include surge, and a surge coincident with a high spring tide extends the lock beyond anything a tide table shows. Take the extreme levels from the Environment Agency's published data for the frontage rather than from a tide table alone.

Sea level rise makes the duration longer over the development lifetime, and the effect is direct: raise the water level against a fixed outfall and the pipe spends more of each cycle submerged. Apply the allowance for the region and the lifetime, and report the locked duration for both present day and end of lifetime. That second figure is the one that determines the storage volume you build.

Note that a single semi-diurnal cycle is roughly twelve and a half hours, so a storm lasting longer than one tidal cycle will see the outfall open again partway through. Short intense events and long duration events therefore behave quite differently, and both need testing.

Storage volume needed to ride out the lock

The volume required is the runoff generated during the locked period, with no outflow. That is a simple statement with an awkward consequence: the critical duration for an estuary site is often much longer than the critical duration inland.

Inland, a small site is usually governed by a short sharp event. On a tidally locked site, the governing case is frequently a long duration, lower intensity event that coincides with high water, because the outfall is shut for the whole of it. Run the full range of durations rather than assuming the 15 or 30 minute event will control the design.

Three design responses reduce the volume:

  1. Raise the outfall invert as high as the bank and the defence will allow, shortening the locked period.
  2. Reduce the runoff reaching the system, through permeable surfaces, green roofs and rainwater use, so the inflow during the lock is smaller. Whether rainwater reuse earns attenuation credit is a separate question, covered in rainwater harvesting and attenuation credit.
  3. Use the pipe network itself as storage, accepting surcharge to a defined level with an exceedance route designed rather than assumed.

Pumping is the fourth option and the one to avoid where possible. A pumped outfall works, but the sewerage undertaker is unlikely to adopt it, which leaves a management company maintaining a pump station in perpetuity and a funder asking who pays for the replacement in year fifteen.

Flap valves, penstocks and their failure modes

A flap valve is a simple device with a poor reputation, mostly earned through lack of maintenance.

The failure modes are worth listing because each has a design answer. Debris jamming the flap open, which lets the tide in. Sedimentation building up on the seat until the flap will not close. Corrosion of the hinge, particularly on a steel valve in saline water. Degradation of the elastomer seal. Marine growth on the face. And simple seizure on a valve that has not moved in five years because the outfall has silted.

Elastomer duckbill valves avoid the hinge problem and tolerate debris better than a hinged plate, at the cost of a higher head loss. A penstock adds positive closure and needs someone to operate it, which means a written procedure and an operator, not an assumption.

Specify two things in the drainage strategy: the valve type with its head loss included in the hydraulic model, and the inspection frequency with the access arrangement. A valve that cannot be reached at low water is a valve that will not be inspected.

Joint probability of tide and rainfall

Combining the extreme tide with the extreme rainfall event overstates the design condition, because the two are not fully dependent. Treating them as independent understates it, because on many estuaries there is some correlation through the weather systems that generate both.

Use a joint probability approach appropriate to the scale of the scheme and state the dependence assumption explicitly. For a small site, a defensible simplification is to test the design rainfall event against a high but not extreme tide, and a lower return period rainfall against the extreme tide, then design for the worse of the two.

Whatever method you use, show the combinations tested in a table. A reviewer who can see the matrix will accept the conclusion. One who is given a single number will ask for the matrix, and the Flood Risk Assessment will come back annotated.

Maintenance access at an estuary outfall

An outfall on a tidal bank is reachable for a limited window each day, in a place that is muddy, often within a flood defence and sometimes below mean high water springs.

Three consenting points follow. Works in, over or near a main river or a tidal flood defence need a flood risk activity permit from the Environment Agency, and the defence byelaw distance is wider than people expect. Works below mean high water springs may require a marine licence. And the ownership of the bank and the right of access have to be established, because a maintenance obligation on land you have no right to enter is worthless.

Design the access as a built element. A stepped or ramped approach, a hardstanding for a small plant item, a chamber with a locked cover above the tide level, and a handrail. The alternative is a maintenance commitment that quietly lapses within a decade.

What the drainage strategy must demonstrate

Set out the levels first: outfall invert and soffit, existing and proposed ground levels, extreme still water levels for the design event with climate change, and the resulting locked duration for both epochs.

Then the hydraulics. Design rainfall events tested across a range of durations, the tide combinations assessed with the dependence assumption stated, the storage provided and where it is, the surcharge levels reached and the exceedance route for events beyond the design case.

Then the ownership and maintenance. Who owns the outfall, who maintains the valve, at what frequency, with what access, and secured by what mechanism.

And say plainly what happens when the system is overwhelmed. An outfall and drainage strategy that ends with a residual risk section naming the route water takes and the depth it reaches is one an officer can recommend. One that stops at the design event leaves the officer to imagine the answer.

Enter your postcode on PlanScope to see which flood and drainage reports your site is likely to need.

This is general guidance rather than legal advice. Check the position with your local planning authority, the lead local flood authority, the Environment Agency or a qualified drainage engineer before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

How do I work out the locked duration for an outfall?

Overlay the outfall soffit level on a predicted tidal curve for the nearest port corrected to the site, then take the period the curve sits above it. Add the surge component from the Environment Agency's extreme still water levels, and repeat the exercise with the sea level rise allowance for the development lifetime.

Why is the critical rainfall duration longer on a tidally locked site?

Because there is no outflow during the lock. Inland sites are usually governed by short intense events, but where the outfall is shut for several hours a long duration, lower intensity event coinciding with high water generates more volume with nowhere to go. Test the full range of durations rather than assuming a short event controls.

Should I combine the extreme tide with the extreme rainfall event?

No, because the two are not fully dependent and combining both extremes overstates the design condition. Use a joint probability approach and state the dependence assumption. For a small site, testing the design rainfall against a high tide and a lower return period rainfall against the extreme tide is a defensible simplification.

Will the water company adopt a pumped outfall?

Usually not, which is the main reason to avoid pumping where gravity and storage can be made to work. An unadopted pump station leaves a management company responsible in perpetuity and a funder asking who pays for replacement plant. Raise the invert, reduce runoff and use surcharge storage before reaching for a pump.

What consents are needed for works at a tidal outfall?

Works in, over or near a main river or a tidal flood defence need a flood risk activity permit from the Environment Agency, and the byelaw distance from a defence is wider than most people assume. Works below mean high water springs may also need a marine licence. Access rights over the bank have to be established separately.

Sources and further reading

drainagetidal lockingoutfallflood risksudsestuary

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS7 min read

The residual risk section of a flood risk assessment

Residual risk is what remains once the mitigation is built and working. Breach, overtopping, blockage, exceedance and mechanical failure each need naming, quantifying and managing.

Read article →
Flood, Drainage and SuDS6 min read

Water supply capacity: what a developer must evidence

Four documents carry the water supply case, none of which the applicant can write. Why the enquiry belongs alongside transport and drainage scoping, not at drafting stage.

Read article →
Flood, Drainage and SuDS6 min read

Rainwater harvesting and the drainage credit

Attenuation needs empty volume and a supply tank is designed to be full. How a credit can be earned through a two-zone tank, and why harvesting belongs in the water efficiency case.

Read article →
Flood, Drainage and SuDS7 min read

Who maintains the SuDS after the houses are sold

Adoption, highway transfer or a management company: the route has to be fixed at concept drainage stage, because each one constrains where components can sit.

Read article →
Flood, Drainage and SuDS7 min read

Surface water sewer capacity and the undertaker's position

The right to connect under section 106 of the Water Industry Act 1991 survives, subject to limited refusal grounds. Why the capacity enquiry has to come before the layout is fixed.

Read article →
Flood, Drainage and SuDS7 min read

Floodplain compensation: level for level volume calculations

Compensatory storage has to be replaced within the same elevation band it was lost from, not just in the same total volume. The calculation method, the siting rules and the drawings that get it approved.

Read article →