Underpinning a party wall under the 1996 Act

7 min readBy PlanScope Editorial Team

Section 2 covers underpinning a party structure and section 6 covers nearby excavation. The notice periods differ, and the sequence decides the programme.

Party wall underpinning is caught by section 2 of the Party Wall etc. Act 1996, which lists the right to underpin, thicken or raise a party structure among the works a building owner may carry out after serving notice. Excavation close to a neighbour's foundations is caught separately by section 6. Most basement and deep foundation projects engage both, and the notice periods differ, so the sequence matters more than people expect.

None of this is planning. The Act is a private law code governing rights between neighbouring owners, running alongside planning permission and building regulations approval without replacing either. A party wall award does not permit development, and planning permission does not authorise work to a party structure.

When the Act is engaged

Three sections do the work, and a single project can trigger all three.

Section 1 covers building a new wall on or astride the line of junction where nothing is built there now. Notice period: one month.

Section 2 covers works to an existing party wall or party structure, including the works listed above, cutting into it to take a beam, demolishing and rebuilding it, and removing chimney breasts from it. Notice period: two months.

Section 6 covers excavation near a neighbour's building. It applies where you excavate within 3 m of a neighbouring structure to a depth lower than the bottom of their foundations, and where you excavate within 6 m and the excavation would cut a line drawn downwards at 45 degrees from the bottom of their foundations. Notice period: one month.

Deepening a party wall to form a basement therefore needs a section 2 notice, and the excavation alongside it needs section 6 notices to every affected neighbour, including those to the rear and across a side passage. Serve them together and work to the longer period.

A notice must identify the building owner, describe the proposed work, and state the date on which it is intended to start. A section 6 notice must also state whether the building owner proposes to strengthen or safeguard the adjoining owner's foundations, and must be accompanied by plans and sections showing the site and depth of the excavation.

Serve on every adjoining owner. That means freeholders and leaseholders with an unexpired term over a year, which in a converted terrace can be four or five people for one wall.

The adjoining owner has 14 days to respond. Consent in writing ends the process for that owner and no award is needed. Silence for 14 days means a dispute is deemed to have arisen, as does a written dissent. There is no penalty for dissenting and most surveyors advise adjoining owners to dissent as a matter of course, so plan on an award rather than hoping for consent.

Starting work without serving notice is the expensive mistake. The remedy available to the neighbour is an injunction, and a court that grants one can stop a partially excavated site indefinitely.

Surveyors and the award

Once a dispute is deemed to exist, the parties either appoint a single agreed surveyor to act impartially for both, or each appoints their own. Where two are appointed they must select a third surveyor at the outset, who resolves any disagreement between them.

The surveyors are not advocates. A surveyor appointed by the building owner acts under a statutory duty, not as their representative, which surprises clients who expected an ally.

The award settles three things: the right to carry out the work, the time and manner of carrying it out, and any other matter arising out of or incidental to the dispute, including costs. It becomes binding once served, and either party may appeal to the county court within 14 days of service.

Where the works involve structural intervention, the award will usually require the design to be certified by a structural engineer and may set out a sequence for the work. That is where the party wall process and the engineering evidence meet, and the calculations behind it are the same ones discussed in Eurocode 7 and geotechnical evidence.

Schedules of condition

A schedule of condition is not required by the Act. Do not skip it.

It is a dated record, written and photographic, of the state of the adjoining property before work starts, covering the rooms and external elevations that could be affected. It exists to answer the claim that a crack appeared because of your excavation when it was there beforehand.

Three points on doing it properly. Record the interior as well as the exterior, since most disputes concern internal finishes. Note existing cracks with dimensions and a scale reference rather than photographing them loosely. And agree the schedule with the adjoining owner's surveyor and attach it to the award, so its status is settled rather than argued about later.

Where the excavation is deep or the ground is sensitive, monitoring during the works complements the schedule, and the practicalities are covered in movement monitoring during basement construction.

What the award can and cannot control

The award governs the party wall works and matters incidental to them. It can set the method, the sequence, the hours during which noisy work may take place, access arrangements, and requirements for making good.

It cannot grant planning permission or approve the work under building regulations. It cannot resolve a boundary dispute about where the legal line runs, though section 1 deals with building on the line of junction. It cannot deal with a rights of light claim, which is a separate civil matter. And it cannot authorise work to a tree, which remains subject to any Tree Preservation Order.

Nor does it override planning conditions. A planning condition restricting working hours or requiring a construction management plan applies regardless of what the award says, and where the two differ the more restrictive controls in practice. The boundary between the two regimes is set out in party wall matters that are not planning matters.

Costs and who pays

The general position is that the building owner pays, because the works are for their benefit. That covers their own surveyor, the adjoining owner's surveyor, the third surveyor where one is called on, and the cost of making good any damage caused.

Costs can be apportioned differently where the work benefits both owners, for example where a defective party wall is rebuilt, or where the adjoining owner requests additional work or behaves unreasonably in the appointment process.

Budget for more than one adjoining owner. A mid-terrace basement with neighbours on both sides and a rear neighbour within the section 6 distance can involve three separate appointments, each with its own award. An adjoining owner may also request security for expenses before work begins, which ties up cash for the duration.

How this sits alongside planning permission

Sequence the two processes rather than running them together.

Get planning permission first where the scheme needs it, because the party wall notices have to describe the work that will actually be done, and a scheme amended during determination means re-serving. Then serve notices, allowing two months for section 2 and one month for section 6, plus time for appointments and the award itself. A realistic allowance from first notice to award is three to four months where there is more than one adjoining owner.

Discharge the pre-commencement planning conditions in parallel. Structural evidence prepared for the planning application, such as a Structural Survey or a Basement Impact Assessment, usually does double duty in the party wall process, which is an argument for commissioning it properly the first time.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. To see which planning documents a basement or deep foundation scheme is likely to need, enter your postcode on PlanScope.

Frequently asked questions

Which party wall notice applies to work beneath a party wall?

A section 2 party structure notice, because section 2 of the Party Wall etc. Act 1996 includes the right to underpin, thicken or raise a party structure. The notice period is two months. Excavation alongside the wall usually also needs section 6 notices, which carry a one month period, so serve both together.

What is the 3 metre and 6 metre rule?

Section 6 applies where you excavate within 3 m of a neighbouring structure to a depth lower than the bottom of their foundations, and within 6 m where the excavation would cut a line drawn downwards at 45 degrees from the bottom of those foundations. Both require notice with plans and sections showing depth.

What happens if my neighbour does not reply to the notice?

Silence for 14 days means a dispute is deemed to have arisen, and the process moves to the appointment of surveyors and an award. It is not consent. Most surveyors advise adjoining owners to dissent in any event, so plan and budget on an award being needed rather than hoping for written agreement.

Who pays the party wall surveyors?

Usually the building owner, because the works are for their benefit, covering their own surveyor, the adjoining owner's surveyor and the third surveyor if called on. Costs can be shared where the work benefits both owners, such as rebuilding a defective party wall, or where an adjoining owner acts unreasonably.

Can I start work before the award is served?

No, where a dispute has arisen. The remedy available to an adjoining owner is an injunction, and a court can stop a partially excavated site. Serving notice late is the most expensive error in the whole process, because the programme is then held by someone with no reason to help.

Does a party wall award replace planning permission?

No. The Act governs rights between neighbouring owners and is separate from planning and building regulations. An award does not permit development, and planning permission does not authorise work to a party structure. Where a planning condition and an award differ on matters such as working hours, the more restrictive one applies in practice.

Sources and further reading

party wallunderpinningbasementexcavationadjoining ownerconstruction

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Fire, Structural and Basements

View all →
Fire, Structural and Basements7 min read

Plant screens, enclosures and separation distances for substations

There is no single separation standard for a substation. Operator access rules, BS 4142 noise assessment and street frontage design all pull on the same position, and all three belong on the first layout.

Read article →
Fire, Structural and Basements8 min read

Shoring and temporary works during demolition

Planning does not approve temporary works, but propping footprint, highway occupation and party wall stability all constrain the permanent scheme. Resolve them at design stage, not after permission.

Read article →
Fire, Structural and Basements8 min read

Excavating a swimming pool in a garden

Class E of the GPDO covers a swimming pool in a domestic garden, but the enclosure, the plant room, twenty lorries of spoil and the backwash discharge are where schemes come unstuck.

Read article →
Fire, Structural and Basements7 min read

Rooftop plant and the capacity of an existing roof

An existing roof usually has very little spare capacity, and the reserve it appears to have is often in the slab rather than in the beams carrying it.

Read article →
Fire, Structural and Basements7 min read

Building beside railway infrastructure: asset protection

The council decides the application. The infrastructure manager decides whether your piling rig, your crane and your drainage are acceptable next to a live railway.

Read article →
Fire, Structural and Basements7 min read

Transfer structures over a commercial ground floor

The transfer zone sits between the commercial ceiling and the first residential floor, and it is additive. Developers usually discover that after the massing is fixed.

Read article →