A dropped kerb is a highway authority consent under section 184, separate from any planning permission for the access or the hard surface. Here is what each one covers and what the specification demands.

A dropped kerb application is made to the highway authority, not to the planning department, and on most unclassified residential streets that is the only consent you need. The confusion arises because two or three separate permissions can apply to the same driveway: the vehicle crossing itself under the Highways Act 1980, planning permission for the access where the road is classified, and planning permission for the hard surface if it is impermeable and drains to the road.

Get the sequence wrong and you can end up with a lawful driveway and no way to drive onto it.

When planning permission is needed as well

Forming a means of access to a highway is permitted development under the General Permitted Development Order 2015 where it is needed in connection with other permitted development, but that right does not apply where the highway is a trunk road or a classified road. Classified means an A, B or C road. So a crossover onto an unnumbered residential street is normally outside planning control, and the same crossover onto a B road needs a planning application.

The hard surface is a separate question. Laying a driveway within the curtilage of a house is permitted development, but government guidance treats an impermeable surface of more than five square metres between the principal elevation and the highway as needing permission unless surface water is directed to a permeable area within the curtilage. Gravel, permeable block paving, a porous asphalt, or a channel discharging to a lawn or border all keep you inside the right.

Then there is the front boundary. Removing or lowering a wall, fence or hedge next to a highway is permitted development up to one metre in height, and in a conservation area or on a listed property the position can be different again. If the wall is part of the listing, taking it down without listed building consent is an offence rather than a planning breach.

A Lawful Development Certificate is the only formal way to confirm that works are lawful. Where the position is finely balanced, particularly on an impermeable surface or a boundary wall in a conservation area, an application under section 192 of the Town and Country Planning Act 1990 removes the doubt.

Applying to the highway authority

The application is made under section 184 of the Highways Act 1980 to the county council, unitary authority or London borough acting as local highway authority. Most publish an online form, a plan requirement and a fee for the initial assessment.

What they want with the application:

  • A location plan and a sketch showing the proposed crossing width, the position relative to the property boundaries and the depth of the parking area behind the footway.
  • Photographs of the frontage showing existing kerb line, footway width, street furniture and any trees.
  • Confirmation of who owns the frontage, and where the property is leasehold, evidence of the freeholder's consent.
  • Details of any planning permission already granted, or a statement that none is needed.

The assessment is a site visit by a highways officer. Approval is a technical decision against the authority's own standards, and there is no appeal to the Planning Inspectorate against a refusal. That is the part householders find hardest: the only routes are a revised design or a complaint through the authority's own procedure.

Construction standard and who does the work

The crossing is part of the public highway, so the authority controls how it is built. Most authorities either carry out the work themselves through their term contractor or allow an approved contractor from a published list to do it under a permit, with the authority inspecting. A private builder cannot simply lower the kerbs.

The specification usually covers a reinforced concrete or bound sub-base under the crossing, dropped kerbs with transition kerbs at each end, tactile paving where the footway crossing meets a route used by pedestrians, and reinstatement of the footway surface to match. Where a verge is crossed, the whole width is normally constructed to a vehicular standard rather than left as grass.

Costs are set by each authority and published. They vary by crossing width, whether a verge is involved and whether statutory undertakers' apparatus has to be moved, so ask for a written quotation rather than working from a neighbour's invoice from five years ago. Larger accesses formed as part of a development permission follow a different route entirely, through the agreements described in the note on section 278 works that follow a permission.

Depth, gradient and visibility

Three dimensions decide most applications.

The depth of the parking area behind the footway has to be enough for a car to stand clear of the highway. Authorities commonly work to a minimum parking bay of about 4.8 metres by 2.4 metres, measured from the back of the footway, and a shallow forecourt on a Victorian terrace often fails on this alone. A car overhanging the footway is an obstruction, so a driveway that cannot contain a vehicle will not be approved.

Gradient matters because a steep rise off the footway grounds vehicles and pushes surface water back onto the highway. Authorities set a maximum fall or rise over the first few metres and will want a level or gently graded threshold immediately behind the crossing.

Visibility is assessed in both directions along the carriageway from a point set back behind the footway. On a bend, near a crest or close to a junction the splay may not be achievable at all.

Trees, gullies, signs and street furniture

A crossover cannot be built through a gully, a lamp column, a telecoms cabinet, a parking meter, a bus stop cage, a pedestrian guardrail or a street tree. Moving each of those is possible in principle and paid for by the applicant, and the timescales differ wildly: a gully relocation is straightforward, while a statutory undertaker's diversion can take months.

Street trees are the hardest case. A tree in the verge or footway usually belongs to the highway authority, its removal is a decision for that authority under highways legislation rather than through tree preservation control, and many authorities operate a presumption against removing a healthy street tree to create a private access. Where a crossing is permitted near a tree, expect conditions on the construction method inside the root protection area and a requirement for a tree survey prepared to BS 5837:2012 by an arboriculturist.

Classified roads and the extra tests

Where planning permission is needed because the road is classified, the application is judged on highway safety in the usual way. The authority will look at the accident record, the speed of traffic, whether the frontage allows a vehicle to enter and leave in forward gear, and whether the access conflicts with a cycle lane or bus route.

On a busy classified road, being asked to turn within the site rather than reverse onto the carriageway is common, which needs more depth than a simple parking bay. A Planning Statement that sets out the visibility achieved, the turning provision and the relevant local plan policy is worth more than a bare form, even on a small householder application.

Electric vehicle charging is worth planning into the same job while the surface is open, and the note on charging provision in new residential development sets out what is expected now.

Why crossovers get refused

The recurring reasons are the same across authorities: not enough depth to stand a car clear of the footway, inadequate visibility, proximity to a junction or crossing, conflict with a bus stop or loading restriction, loss of on street parking that the authority is unwilling to give up, an immovable street tree, and a gradient that cannot be resolved. Refusal for loss of an on street space is more common than people expect in controlled parking zones.

Two practical habits help. Ask the highway authority for an informal view before you commission drawings, because an officer will often say on the phone that a frontage is too shallow. And if the answer is no, ask which dimension failed, because a 300 millimetre change in the position of the crossing sometimes fixes it.

Enter your postcode on PlanScope to see which reports your driveway or access project is likely to need.

This is general guidance, not legal advice; check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Do I need planning permission for a dropped kerb?

Usually not on an unclassified residential street, where forming the access is permitted development and the only consent needed is the highway authority's approval under section 184 of the Highways Act 1980. You do need planning permission where the road is a trunk road or a classified A, B or C road, and possibly for an impermeable driveway surface.

How deep does my driveway need to be for a crossover?

Enough to stand a car entirely clear of the footway. Many authorities work to a minimum parking area of roughly 4.8 metres by 2.4 metres measured from the back of the footway. Shallow forecourts on terraced streets often fail this test, which is the most common single reason a crossover application is refused.

Can I build the dropped kerb myself?

No. The crossing forms part of the public highway, so the work is carried out either by the authority's own contractor or by a contractor from the authority's approved list working under a permit and inspection. Lowering kerbs without approval is an unauthorised interference with the highway and the authority can require reinstatement at your cost.

Can a street tree stop my dropped kerb?

Often, yes. A tree in the footway or verge normally belongs to the highway authority and its removal is that authority's decision, not a tree preservation matter. Many authorities will not remove a healthy street tree for a private access. Where a crossing is allowed nearby, expect conditions on working methods within the root protection area.

Is there an appeal against a refused crossover application?

There is no appeal to the Planning Inspectorate, because a section 184 decision is a highway authority decision rather than a planning decision. The practical options are a revised design addressing the reason given, or the authority's own complaints procedure if you think the assessment was wrong. Ask which dimension failed before redesigning.

Sources and further reading

dropped kerbaccesshighwayshouseholderpermitted developmentparking

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Transport, Highways and Parking

View all →
Transport, Highways and Parking6 min read

Temporary traffic orders for construction works

A construction programme usually needs four separate highway permissions, each under a different power. What each one covers, how long it lasts and what happens when works overrun.

Read article →
Transport, Highways and Parking8 min read

Highway drainage for a new rural access

Highway authorities treat run-off and material transfer onto a rural lane as a safety matter. The design comes down to the levels in the first few metres and the consent position for the roadside ditch.

Read article →
Transport, Highways and Parking7 min read

Car club and travel voucher contributions

The money is simple. The on-street bay needs a traffic regulation order the developer cannot deliver, and the operator may never come forward.

Read article →
Transport, Highways and Parking7 min read

Gated accesses and emergency service override

Three bodies have a view on a gated access: the highway authority, the fire service and the waste service. Design for all three before the driveway is drawn.

Read article →
Transport, Highways and Parking7 min read

Blocking back and queue length at a junction

A capacity ratio tells you how hard an arm is working. Only the queue in metres, compared against measured storage, tells you whether the junction behind will block.

Read article →
Transport, Highways and Parking7 min read

Which design vehicles to test in a swept path analysis

A tracking drawing is only as good as the vehicle chosen. The routine and occasional movements to test, and the parked car case most submissions omit.

Read article →