London

Waste capacity and borough apportionment in London

6 min readBy PlanScope Editorial Team

Policy SI 8 of the London Plan 2021 safeguards existing waste sites and apportions tonnage to each borough. Losing capacity means replacing it, measured at maximum throughput.

London boroughs are each given a share of the capital's waste to plan for, and Policy SI 8 of the London Plan 2021 is where that apportionment and the protection of existing waste sites sit. If your site is a safeguarded waste site, or an operating waste facility, the policy starting point is refusal unless you provide compensatory capacity elsewhere. That requirement catches a lot of industrial redevelopment schemes late in the process, when the site history finally surfaces.

The underlying aim is net self-sufficiency: London managing its own waste within its own boundary rather than exporting it. Boroughs deliver that through land allocations in their local plans, and applicants meet it by not removing capacity without replacing it.

How waste capacity is apportioned to boroughs

The London Plan sets out borough-level apportionment targets in tonnes, stepped across future years, covering household and commercial or industrial waste. Each borough is expected to identify sufficient land in its local plan to manage its apportioned tonnage, either alone or jointly with neighbouring boroughs through a waste planning group.

That apportionment is a plan-making obligation rather than a test applied to each application. It still matters to applicants, because a borough that is behind on its apportionment will defend every remaining waste site hard, and will take a narrow view of what counts as adequate compensation.

Check two things before buying or designing. Whether the site is identified as a safeguarded waste site in the borough's local plan or waste policies, and whether the borough's apportionment is being met. Both come from the adopted plan and its evidence base.

Safeguarded waste sites and the no net loss rule

Existing waste sites are safeguarded. Policy SI 8 expects proposals that would result in the loss of waste management capacity to be refused unless compensatory capacity is provided, and the benchmark is the maximum throughput of the existing site rather than its current trading level.

That distinction does the damage. A transfer station running at half capacity because of a soft market still has to be replaced at its permitted or operational maximum. Pull the environmental permit and the planning history, because the permitted tonnage in the environmental permit is where the number usually comes from.

Safeguarding also attaches to land allocated for waste use even where no facility is operating. A cleared yard with a waste allocation is treated the same way as a working facility.

What a scheme on a waste site has to show

The application needs to answer four questions in order, and the answers belong in the planning statement rather than scattered through technical appendices.

  1. Is the site a safeguarded waste site, or allocated for waste, in the development plan?
  2. What is the existing capacity, measured as maximum throughput, with the permit and planning history to evidence it?
  3. Where will compensatory capacity be provided, and is it secured?
  4. Does the replacement capacity handle the same waste streams at an equivalent point in the hierarchy?

The fourth question is the one most often ducked. Replacing a mixed municipal transfer station with a specialist recycling facility that takes a narrow waste stream is not equivalent capacity, however impressive the tonnage looks. The borough and the Greater London Authority will both say so.

Where a site is truly redundant and no compensatory capacity is offered, the case has to be evidenced rather than asserted: marketing evidence, permit surrender, the borough's own apportionment position, and the contribution of alternative sites. That is a harder argument than most applicants expect, and it has clear parallels with protecting industrial land in London under the no net loss and SIL policy.

Compensatory provision and where it can go

Compensatory capacity should be provided within London. Preference runs to the same borough, then to the waste planning group, then elsewhere in the capital. Capacity provided outside London undermines the self-sufficiency aim and will be resisted.

Securing it is the practical difficulty. Options in use include a planning obligation tying the redevelopment to the delivery of replacement capacity at a named site, a parallel application for the replacement facility determined alongside the scheme, and a Grampian style condition preventing implementation until the replacement is operational.

Developers dislike all three because they couple the scheme's programme to a facility they often do not control. Starting the conversation with the borough's waste officer at pre-application, well before the planning application, is the only way to make the mechanism work. Sites within an Opportunity Area allocation sometimes have a strategic answer already identified in the framework document, which is worth checking first.

Construction and demolition waste expectations

Separately from capacity, London schemes are expected to deal with the waste they generate. The London Plan sets high recycling and recovery expectations for construction and demolition waste and for excavation material, with beneficial use rather than landfill as the default.

For a referable scheme, a circular economy statement is required, setting out how materials will be retained, reused and recycled, with a bill of materials and targets. Even below the referable threshold, boroughs commonly ask for a site waste management plan by condition despite the regulations requiring them having been revoked.

Excavation material deserves early attention on sites with basements. Moving spoil off site is expensive and carbon intensive, and a scheme that can reuse material in landscaping or retain it on site has a better answer at both ends, something the design-led approach in optimising site capacity under policy D3 tends to flush out early.

Operational waste storage in a new building

The everyday version of waste policy is the bin store, and it fails more applications at officer level than apportionment ever does.

Boroughs publish waste storage standards in their local plans or supplementary planning documents, covering container numbers, separation of recyclable streams, the maximum carry distance from a dwelling to the store, and the maximum drag distance from the store to the collection point. Refuse vehicle swept path analysis is normally expected where collection happens on site.

Design the store as a room with ventilation, drainage, a washable surface and lighting rather than a cupboard added at the end. Mixed use schemes need separate commercial and residential provision, because the collection arrangements and the contractors differ.

Evidencing the position in the application

Pull the evidence together in one place. The development plan designation with the policy reference, the site's permit and planning history, the throughput calculation, the compensatory proposal and its delivery mechanism, then the construction waste and operational storage strategies.

Councils will check the designation themselves, so stating it accurately at the outset builds credibility for everything that follows. Where the site is not safeguarded, say so plainly and show the plan extract rather than staying silent and inviting the question.

A clear, well sourced waste chapter rarely wins an application on its own. A missing one, on a safeguarded site, will lose it. For borough specific rules that sit alongside this, the interaction with Article 4 directions in London is worth checking at the same time, since both turn on designations recorded in the local plan rather than anything visible on site.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it.

Enter your postcode on PlanScope to see which supporting reports a London redevelopment site is likely to need.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

What is borough waste apportionment in London?

The London Plan allocates each borough a share of London's household and commercial waste to plan for, stepped across future years. Boroughs must identify enough land in their local plans to manage that tonnage, alone or jointly through a waste planning group. It is a plan-making duty rather than a test applied to each application.

Can I redevelop a safeguarded waste site?

Only with compensatory capacity, or with strong evidence that the site is surplus to the borough's waste needs. Policy SI 8 expects refusal where waste management capacity would be lost without replacement. The benchmark is the maximum throughput of the existing facility rather than the tonnage it currently handles.

Where can compensatory waste capacity be provided?

Within London, with preference for the same borough, then the waste planning group, then elsewhere in the capital. Capacity outside London works against the net self-sufficiency aim and is normally resisted. The replacement must handle comparable waste streams at an equivalent point in the waste hierarchy.

How is compensatory capacity secured in practice?

Through a planning obligation tying redevelopment to delivery at a named replacement site, a parallel application for the replacement facility determined alongside the scheme, or a condition preventing implementation until the replacement is operational. All three couple the scheme programme to a facility the applicant may not control.

Do I still need a site waste management plan?

The regulations requiring them were revoked, but many London boroughs continue to ask for one by condition. Referable schemes also need a circular economy statement with a bill of materials and reuse targets. Treat both as live requirements and check the borough's validation list before submitting.

Sources and further reading

london planwastesi 8apportionmentsafeguarded sitescircular economy

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in London

View all →
London7 min read

Wind microclimate assessment for a London tower

A usable wind assessment names its test locations, states the criteria and season for each, and includes consented but unbuilt neighbours in a cumulative scenario.

Read article →
London7 min read

Energy strategy: Be Lean, Be Clean, Be Green, Be Seen

The London energy hierarchy is four steps, and the fourth commits you to reporting metered performance for years after occupation. Here is what each stage has to evidence.

Read article →
London7 min read

Play space on a London podium: making the deck work

Podium play space is judged on whether it functions, not on whether it measures 10 m2 per child. Here is how supervision, loading, drainage and wind shape the deck.

Read article →
London7 min read

Housing design standards: space, aspect and dual aspect

London residential schemes are tested against the national space standard, a tighter ceiling height, a dual aspect expectation and limits on units per core. Those four together decide whether a layout works.

Read article →
London7 min read

Fire safety and policy D12 in a London application

Policy D12 of the London Plan asks every development to meet the highest standards of fire safety and asks major schemes for a statement from a suitably qualified independent assessor. It overlaps with Planning Gateway One without replacing it.

Read article →
London6 min read

Water consumption targets and how to reach 105 litres

The 105 litre target in London is delivered through the optional requirement in Part G of the Building Regulations, imposed by planning condition. Here is how the calculator works and which fittings actually get you there.

Read article →