Costs, Fees and Budgeting

What drives the cost of a coal mining risk assessment

7 min readBy PlanScope Editorial Team

The desk study is the modest part. Mine entries, zones of influence and intrusive drilling are what move a coalfield site budget and programme.

If your site falls in a Development High Risk Area, the local planning authority will expect a Coal Mining Risk Assessment with the planning application. The desk study end of that work is modest. The cost that hurts comes afterwards, when the desk study identifies a mine entry, shallow workings or a recorded seam outcrop and intrusive investigation is needed to find out what is actually under the plot.

Budget in two stages. Stage one is the assessment itself, built from records. Stage two is drilling, and it is the stage that can cost many times the first and move your programme by months.

Where the referral area triggers the requirement

The Coal Authority, which now operates as the Mining Remediation Authority, maintains the mapping that defines coalfield referral areas. Development High Risk Areas are where recorded mining features, shallow workings or mine entries mean that coal mining legacy could affect the stability or safety of new development, and they cover a modest share of the wider coalfield.

Check the position before you buy. The authority's interactive map and its property search products will tell you whether a site is in a high risk area and whether a mine entry is recorded on or close to it. The British Geological Survey holds borehole records and geological mapping that fills the picture in.

Where the site is in a Development High Risk Area, the Mining Remediation Authority is consulted on the application, and a risk assessment is a validation requirement on most coalfield authorities' local lists. Where the site is in a low risk area, no assessment is normally needed, though the standing advice still applies.

Desk study content and the data sources

Stage one costs are driven by data purchase and the author's time, and both are reasonably predictable.

The assessment pulls together the mining report for the site, abandoned mine plans, the recorded positions and dimensions of mine entries, seam names, depths and inclinations, historic Ordnance Survey mapping to spot surface features such as spoil, bell pits and tramways, borehole logs, and any records of past grouting or treatment. It then reaches a conclusion: no further work, further investigation, or a design response.

Costs rise where the records are poor. Pre-nationalisation workings, shallow pillar-and-stall extraction and unrecorded bell pit fields all push the assessment towards recommending intrusive work, because the honest conclusion from thin records is that the ground is unproven.

The published prices for the authority's mining report and data products are reviewed periodically, so check the current schedule rather than reusing a quote.

Mine entries and the standoff that follows

A recorded shaft or adit near the plot is the single biggest cost driver, and it works through geometry rather than through remediation.

Mine entries carry a zone of influence, a radius around the entry within which development is restricted until the entry has been located, proved and treated. The radius depends on the shaft diameter and the depth of unconsolidated deposits above rockhead, so a wide shaft under deep superficial deposits produces a much larger exclusion area than a narrow one in shallow ground.

Two consequences follow. The recorded position of an old shaft is often inaccurate by tens of metres, so locating it requires a search programme of trial pits or a geophysical survey followed by confirmation drilling. And until the entry is proved, the zone of influence has to be kept clear of buildings, which on a small plot can remove the developable area entirely.

Find this out at option stage. A shaft 10 metres outside your boundary can be as expensive as one inside it.

Intrusive investigation and what drives the price

Stage two costs are driven by the number of holes, their depth, the rig type, access and standing time.

Cost driver What increases it
Number of holes Site area, seam count, whether workings must be proved across the footprint
Depth Seam depth, superficial deposit thickness, the need to prove rockhead
Rig and access Restricted access needing a small or tracked rig, hand-dug inspection pits, traffic management
Standing time Weather, service clearance delays, waiting for permits
Laboratory and reporting Gas monitoring visits, ground gas risk assessment, structural design input

Ground gas is the item that surprises people. Where workings are present, methane and carbon dioxide monitoring over several visits across varying barometric pressure is normally expected, and that is weeks of elapsed time rather than a single day on site. Combine the coal work with the contaminated land investigation where both are needed, because one mobilisation covering both is far less expensive than two, and a Geotechnical Assessment can draw on the same boreholes.

Permits before any drilling

You cannot drill into coal seams or mine workings without permission. The Coal Industry Act 1994 vests the unworked coal and the mine workings in the authority, so entering or disturbing them requires its written consent, commonly obtained as a permit covering the proposed investigation.

Allow lead time. The permit application needs the proposed locations, depths, drilling method and grouting details, and it has to be in place before the rig is booked rather than after. The same applies to any grouting programme, which is a separate permission.

This is the stage at which programmes slip most often, because the site investigation contractor assumes the client has the permit and the client assumes the contractor arranges it. Settle who does what in the appointment.

Remediation by grouting or foundation design

Where shallow workings are proved, there are two broad routes.

Treatment means drilling a grid of holes and injecting grout to fill the voids, then verifying the result. Costs scale with the plan area treated, the void volume and the grout take, which is unknown until the work starts, so this is the one item that cannot honestly be fixed-priced with confidence. Expect a provisional sum.

Design means leaving the ground alone and spanning it, usually with a reinforced raft or piles founded below the workings into competent strata. That transfers cost from groundworks to structure, and on a single dwelling it is often the lower-cost route. On a scheme with gardens, roads and services crossing the workings, treatment usually wins because you cannot raft a driveway.

Mine entries are different again: they are capped and treated to the authority's requirements, and the cap design and the zone of influence then constrain the layout permanently.

Sequencing against the planning application

  1. Check the referral area and any recorded mine entry before you commit to the site, as the article on the coalfield interactive map before you buy a site sets out.
  2. Commission the desk study assessment and read its recommendation before fixing the layout.
  3. Where intrusive work is recommended, decide whether to do it before the application or accept a condition. Doing it first gives certainty on developable area and foundation cost.
  4. Apply for the authority's permit in good time, and combine the coal, geotechnical and contamination investigation in one mobilisation.
  5. Submit the application with the assessment, and expect a condition requiring any remediation and a verification report.
  6. Allow a provisional sum for grout take, and keep the verification records for the handover file.

Many self-builders accept a condition and investigate later. That costs less up front and is riskier, because a condition requiring remediation to the authority's satisfaction is open-ended, and discovering a large zone of influence after you own the land is the expensive version of this problem. What goes in the report itself is covered in the piece on coalfield referral areas and what the report must cover.

This is general guidance, not legal advice. Check the position with your local planning authority, the current standing advice and a qualified geotechnical professional before relying on it, and see PlanScope pricing if you are comparing document costs.

PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval. For specialist technical reports, qualified professional input may be required.

Frequently asked questions

When do I need a coal mining risk assessment?

Where the site falls within a Development High Risk Area as mapped by the Coal Authority, now operating as the Mining Remediation Authority. In those areas the authority is consulted on applications and most coalfield councils include the assessment on their local validation list. In low risk areas no assessment is normally needed, though standing advice still applies.

What is a zone of influence around a mine entry?

A radius around a recorded shaft or adit within which development is restricted until the entry is located, proved and treated. The radius depends on the shaft diameter and the thickness of unconsolidated deposits above rockhead, so a wide shaft in deep superficial ground produces a much larger exclusion area than a narrow one in shallow ground.

Do I need permission to drill?

Yes. The Coal Industry Act 1994 vests unworked coal and mine workings in the authority, so entering or disturbing them requires written consent, usually obtained as a permit covering the investigation. The permit needs locations, depths, method and grouting details, and must be in place before the rig is booked. Grouting needs its own permission.

Is grouting or a raft foundation the better answer?

On a single dwelling, a reinforced raft or piles founded below the workings often costs less than treating the ground. On a scheme with roads, gardens and services crossing the workings, grouting usually wins because you cannot raft a driveway. Grout take is unknown until work starts, so carry a provisional sum.

Should I investigate before applying or accept a condition?

Investigating first costs more up front and gives certainty on developable area and foundation cost. Accepting a condition costs less at application stage but leaves an open-ended obligation to remediate to the authority's satisfaction. Discovering a large zone of influence after buying the land is the expensive version of this problem.

Sources and further reading

coal mining risk assessmentcostscoalfieldground investigationself-buildbudgeting

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Costs, Fees and Budgeting

View all →
Costs, Fees and Budgeting8 min read

Costing a stopping up order for a highway or footpath

Public rights do not lapse through disuse and planning permission does not override them. This covers the section 247 and 257 routes, what objectors actually argue about, and how to keep the order off the critical path.

Read article →
Costs, Fees and Budgeting7 min read

Costing an affordable housing review mechanism

Early and late stage review mechanisms are decided by their definitions, not their headline percentages. This covers the inputs that move the answer, who pays for the review and the caps to secure before signing.

Read article →
Costs, Fees and Budgeting7 min read

Costing an employment land assessment for an allocated site

On an allocated employment site the fee sits in evidence gathering, not analysis. This covers the marketing records councils expect, the suitability tests that decide it, and how to sequence the work.

Read article →
Costs, Fees and Budgeting7 min read

Costing an odour assessment for a kitchen or waste use

The fee for an odour assessment depends on whether the council accepts a qualitative risk based appraisal or expects dispersion modelling. Here is what sits behind each, and how to scope the work before you commission it.

Read article →
Costs, Fees and Budgeting6 min read

Costing a telecommunications compliance declaration for a mast

An ICNIRP declaration is produced by the operator's own radio engineers and closes the health issue. Siting and appearance are the only matters the council can decide on.

Read article →
Costs, Fees and Budgeting6 min read

Costing an equalities impact assessment for a public applicant

The public sector equality duty is continuing, so an equalities impact assessment has to be revisited at every material change. Budgeting for one document is the common mistake.

Read article →