Which rainfall dataset to cite in a drainage calculation

7 min readBy PlanScope Editorial Team

Name the rainfall model, the version, the grid reference and the extraction date. Here is how the Flood Estimation Handbook revisions differ, why storm profiles change the answer, and what a drainage reviewer checks first.

Every surface water calculation you submit rests on a rainfall dataset, and the reviewer's first question is which one. Name the model, the version, the grid reference and the date you extracted the data. In England the practical choice is between the Flood Estimation Handbook depth duration frequency models, the 1999 version and the 2013 revision, and the older Flood Studies Report rainfall used by some drainage software by default. Getting this wrong does not usually produce an obviously silly answer. It produces a plausible one that turns out to be undersized.

Why the rainfall source has to be on the page

A drainage calculation is a chain: rainfall depth for a given duration and return period, a storm profile, a runoff model, then storage sized to hold the difference between inflow and the permitted discharge rate. Change the first link and everything downstream moves.

Lead local flood authorities review hundreds of these a year. They are not recalculating your model. They are checking that the inputs are stated, current and defensible, and that the outputs follow. An unsourced rainfall figure means the reviewer cannot do their job, and the usual outcome is a holding objection rather than a refusal.

So state it. Dataset, version, grid reference, extraction date, and the return periods and durations tested. Four lines of text that remove an entire round of correspondence.

The national rainfall models and their revisions

The Flood Studies Report rainfall model dates from 1975 and still appears as a default in drainage software, often through the Wallingford Procedure routines. It is the oldest of the three and the hardest to defend on a new application.

The Flood Estimation Handbook depth duration frequency model published in 1999, usually shortened to FEH99, replaced it for most purposes. The 2013 revision, FEH13, rebuilt the model on a longer and denser record of rain gauge data. The difference between the two is not uniform across the country. In some locations FEH13 gives greater short duration depths than FEH99, in others less, and the direction of travel varies with return period as well as with place.

That variability is the reason a blanket rule fails. You cannot say the newer dataset is always more onerous. You can say that using a dataset from 1975 on a scheme designed in the 2020s invites a question you will struggle to answer.

Point rainfall data for a site is obtained by grid reference from the FEH web service, which is a licensed product. Keep the download, because a reviewer asking for the source wants the extract, not a screenshot of a results table.

Grid references and getting the location right

FEH point data is supplied on a one kilometre grid. For a small development site, the centroid of the site is the right reference. For a drainage catchment that extends beyond the red line, use the centroid of the contributing catchment instead, and say which you used.

Two common errors. The first is taking the grid reference from a postcode centroid, which can sit several hundred metres from the site and, in hilly country, in a different rainfall regime. The second is using the same extract for a phased scheme where later phases drain to a different outfall.

Neither error is large. Both are avoidable, and both look careless when the reviewer spots them.

Storm profiles and what they do to the answer

A rainfall depth is not a storm. The profile distributes that depth over the duration, and the choice of profile changes the shape of the inflow hydrograph.

Summer profiles are peakier and tend to be critical for systems limited by conveyance or by the rate of infiltration. Winter profiles are flatter, with antecedent conditions that generate more runoff volume, and they tend to be critical for storage dominated systems such as attenuation basins and tanks.

The practical answer is to test both and report the critical case for each element of the system. A scheme with a small orifice and a large basin can be sized by a winter event even though the peak flow arrives in a summer one. Presenting only the case that suits the design is the fastest way to lose a reviewer's confidence.

Run a range of durations too, from short intense events through to several hours, and show the critical duration for each return period rather than assuming the one hour event governs.

Areal reduction, and when it does not apply

Areal reduction factors account for the fact that heavy rainfall is not uniform over a large catchment. The factor reduces point rainfall to an average depth across the area.

For a typical development site the factor is one, because the site is small enough that the point value applies. Applying an areal reduction to a two hectare site is an error that reduces the rainfall and therefore the storage, and it is one of the few mistakes in this field that produces an undersized system while looking like diligence.

The factor becomes relevant on larger catchments, and the threshold above which it matters is a matter for the hydrologist rather than a rule of thumb. If your contributing catchment is measured in square kilometres rather than hectares, take advice.

When two datasets disagree

Sometimes FEH99 and FEH13 give materially different answers for the same site, and the design flips from comfortable to tight. Three responses work.

  1. Check whether the lead local flood authority has published a preference. Several have, and if yours has, that settles it.
  2. Present both, adopt the more onerous, and note the margin. This costs storage volume and buys an uncontested review.
  3. Where adopting the more onerous case cannot be made to work on the site, set out the comparison, explain the choice and evidence the residual risk in the Flood Risk Assessment rather than burying it in an appendix of the drainage calculations.

Climate change allowances are a separate layer applied on top of the chosen rainfall dataset, using the Environment Agency's published peak rainfall intensity allowances. Those figures are revised from time to time, so check the current allowance at the point of design rather than copying one from a previous job.

An illustrative example. A 1.8 hectare brownfield site drains to a surface water sewer with a 5 litres per second discharge limit. Sized on the 1999 dataset the attenuation tank comes out at 310 cubic metres. Rerun on the 2013 dataset the same design needs about 8 per cent more volume, which the layout can absorb by deepening the tank rather than widening it. The consultant presents both, adopts the larger, and the drainage officer signs it off without comment. Figures here are illustrative rather than taken from a real scheme.

Writing it down so a reviewer can check it

Put the inputs in one table near the front of the Drainage Strategy, not scattered through appendices. It should carry:

  • Rainfall model and version, with the extraction date and the grid reference used.
  • Return periods and durations modelled, and the critical duration for each.
  • Storm profiles applied, summer and winter, and which governed.
  • Areal reduction factor, stated as one where no reduction applies.
  • Climate change allowance applied, with the source and the epoch.
  • Urban creep allowance, where the local standards require one.

The same discipline applies to the other evidence in a drainage submission. If you are citing the surface water map, read it without overstating what it shows, and where groundwater is part of the picture, set out the evidence for it properly.

Drainage calculations should be prepared by someone competent in hydraulic design, and councils expect a suitably qualified author. An AI-assisted draft can build the strategy structure, set out the policy framework and mark exactly where your rainfall inputs and discharge rates need to go, then flag the values it does not hold. The arithmetic remains yours.

Enter your postcode on PlanScope to see which reports your site is likely to need before you commission the drainage work.

This is general guidance, not legal advice; check the position with your lead local flood authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Should I use the 1999 or the 2013 Flood Estimation Handbook rainfall model?

Use the 2013 revision unless your lead local flood authority has published a different preference. The difference between the two is not uniform across the country, so neither is always the more onerous. Where the two give materially different answers, present both, adopt the larger storage requirement and note the margin.

Where does the rainfall data for my site come from?

Point depth duration frequency data is obtained by grid reference from the Flood Estimation Handbook web service, which is a licensed product supplied on a one kilometre grid. Use the site centroid for a development site, or the centroid of the contributing catchment where drainage extends beyond the red line, and keep the extract.

Do I need to model both summer and winter storms?

Yes, for most schemes. Summer profiles are peakier and usually critical for conveyance and infiltration, while winter profiles carry more volume and usually govern storage sizing. Test both, run a range of durations, and report which case was critical for each element rather than presenting only the favourable result.

Does an areal reduction factor apply to a small site?

No. For a typical development site the factor is one, because the point rainfall value already applies across an area that small. Applying a reduction to a site measured in hectares understates the rainfall and undersizes the storage. Areal reduction becomes relevant only where the contributing catchment is measured in square kilometres.

Is the climate change allowance part of the rainfall dataset?

No, it is a separate layer applied on top. The Environment Agency publishes peak rainfall intensity allowances for use in drainage design, and these are revised periodically. Check the current allowance and the relevant epoch at the point of design, and state both alongside the rainfall model in your inputs table.

Sources and further reading

drainagesudsrainfall dataflood risksurface waterattenuation

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Flood, Drainage and SuDS

View all →
Flood, Drainage and SuDS8 min read

Local resilience forums and flood emergency planning

Flood emergency planning sits with local resilience forums under the Civil Contingencies Act, not with the planning system. Here is how the two meet.

Read article →
Flood, Drainage and SuDS8 min read

Sewerage design standards and sewer adoption approval

Adoptable sewers are designed to the sewerage undertaker's standards, not the council's. Here is what governs the layout, how the application runs and where the programme slips.

Read article →
Flood, Drainage and SuDS6 min read

Flood Re and what buyers will ask about

Homes built on or after 1 January 2009 cannot use Flood Re, so new build insurance rests on the open market. What to hand over at completion and what not to promise.

Read article →
Flood, Drainage and SuDS7 min read

Trash screens and the liability they create

Screens protect a culvert and introduce a new flood risk upstream. How blockage is modelled, which designs degrade gracefully, and who maintains the structure afterwards.

Read article →
Flood, Drainage and SuDS7 min read

Car park change of use and surface water retrofit

An existing impermeable site protects you from a greenfield requirement but not from a betterment expectation. How to evidence the baseline discharge and what the strategy must show.

Read article →
Flood, Drainage and SuDS7 min read

Attenuation under an adopted highway: what is allowed

Highway authorities rarely accept attenuation storage under an adopted carriageway. The reasons, the technical bar where it is considered, and the alternatives that keep storage inside the site.

Read article →