Which reports a scheme with a public right of way needs

6 min readBy PlanScope Editorial Team

Recorded rights of way need an order under section 257 or the Highways Act before a scheme can build over them. The timing trap, the objection risk and the evidence to submit.

A recorded public right of way crossing a development site is a highway, and planning permission gives you no authority whatsoever to obstruct it. That single point governs everything else. The public right of way planning reports a scheme needs sit alongside a separate order-making process under the Town and Country Planning Act 1990 or the Highways Act 1980, and the order usually controls the start on site rather than the planning permission.

Build across a footpath without an order in place and you have obstructed a highway, which is an offence, and the authority can require the obstruction removed whatever your permission says.

Checking the definitive map

The definitive map and statement, maintained by the surveying authority under the Wildlife and Countryside Act 1981, is the legal record. The surveying authority is the county council or the unitary authority, and its rights of way team holds it.

Four categories of recorded route exist and each carries different rights.

Footpath, on foot only.

Bridleway, on foot, on horseback and by bicycle.

Restricted byway, on foot, on horseback, by bicycle and by non-mechanically propelled vehicle.

Byway open to all traffic, all of the above plus motor vehicles.

Two complications arise often enough to plan for. The definitive statement sometimes records a width and sometimes does not, and where it does not, the width is a question of evidence rather than a number you can pick. And the route on the ground is frequently not the route on the map, because walkers have taken an easier line for 40 years. The legal route is the mapped one.

Order a definitive map search early and ask specifically whether any application to add or modify a route affects the land, because an outstanding definitive map modification order application can sit on a site for years without appearing anywhere else.

Obstruct, divert or stop up

Decide which of these the scheme does, because the answer picks the legal route.

Outcome Usual mechanism Who makes the order
Route retained on its existing line None needed Not applicable
Diverted or stopped up to enable permitted development Section 257, Town and Country Planning Act 1990 The local planning authority
Diverted in the landowner's or the public's interest, unrelated to a permission Section 119, Highways Act 1980 The surveying authority
Extinguished because it is not needed Section 118, Highways Act 1980 The surveying authority
A road rather than a path affected by development Section 247, Town and Country Planning Act 1990 The Secretary of State

Section 257 is the route most development uses. It allows an authority to make an order stopping up or diverting a footpath, bridleway or restricted byway where it is necessary to do so to enable development to be carried out in accordance with a planning permission that has been granted.

The words "has been granted" are the programme problem. In most cases the permission has to exist before the order can be made, so the order process runs after determination rather than alongside it.

Timing, and the objection risk

An uncontested section 257 order takes a few months: the authority makes the order, advertises it on site and in a local newspaper, serves notice on the prescribed consultees, and if no objections are received it can confirm the order itself.

If objections are received and not withdrawn, the authority cannot confirm its own order. It goes to the Secretary of State, which in practice means the Planning Inspectorate, and is determined by written representations, a hearing or an inquiry. That adds many months and, on a contested rural route, can add more than a year.

Who objects, predictably: the Ramblers and other user groups, the parish council, the local access forum, and individual users. Their grounds are almost always about the quality of the replacement route rather than the principle, which is useful information for the design.

Three ways to reduce the risk.

Design a replacement route that is plainly as good or better: similar length, sensible gradients, a pleasant alignment, not a corridor between two fences.

Engage the rights of way officer and the local access forum before the planning application, not after permission.

Avoid the need for an order altogether where the layout can retain the route, which is often possible on a larger site at the cost of one plot.

Layout changes that keep the route

Retaining a path usually costs less and takes less time than diverting it, and it earns credit in the design and sustainability narrative.

The moves that work are consistent. Run the route through public open space or a green corridor rather than between rear garden fences. Give it a defensible edge with active frontage overlooking it, because a path with blank boundaries on both sides becomes a management problem. Keep the surface and width suitable for the recorded category, which for a bridleway means a bound or well drained surface wide enough for a horse and a cyclist to pass. Light it where it becomes an urban route and leave it unlit where it stays rural and crosses ecologically sensitive ground.

A lighting assessment is the document that reconciles those last two, and the guidance councils cite on obtrusive light applies to path lighting as much as to car parks.

Where the route forms part of the open space provision, an open space assessment should treat it as linear open space with its own maintenance regime rather than folding it into a general figure.

Ecology and hedgerows along the route

Old paths follow old boundaries, which means hedgerows, mature trees and ditches. Three consequences.

Hedgerow removal to widen or realign a route may need a notice under the hedgerow regulations, and an important hedgerow cannot be removed without the authority's agreement. Check this before assuming a gap can be made.

Breeding birds occupy hedgerows between March and August, so clearance timing is constrained and a condition will usually say so.

Bats commute along linear features, so lighting a formerly dark path is an ecological change as well as a design one. A preliminary ecological appraisal should scope this explicitly rather than treating the route as a blank line on the plan.

The submission contents

On a site crossed by a recorded route, expect to produce the following alongside the standard pack.

A plan showing the recorded route, its category and its width where recorded, overlaid on the proposed layout.

A statement explaining whether the scheme retains, diverts or stops up the route, and if an order is needed, which provision is relied on and what stage it has reached.

A plan and description of any replacement route, with lengths, surfacing, widths, gradients and crossing points.

A transport statement or transport assessment dealing with the route as part of the walking and cycling network, including crossings of estate roads.

The ecological appraisal, lighting assessment and arboricultural material relevant to the corridor.

A construction management plan addressing how the route is kept open, or lawfully closed under a temporary closure order, during the works.

That last item is the one most often missed. A temporary closure during construction is a separate application to the highway authority with its own notice period, and site compounds have a habit of landing on footpaths before anyone has applied for it.

Start the rights of way conversation at pre-application stage. It is the item on this type of site most likely to move the start on site by a year.

This is general guidance, not legal advice; check the position with your local planning authority, the surveying authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Can I build over a public footpath once I have planning permission?

No. A recorded public right of way is a highway and planning permission gives no authority to obstruct it. You need a stopping up or diversion order, usually under section 257 of the Town and Country Planning Act 1990. Obstructing a highway without one is an offence, whatever the permission says.

When can a section 257 order be made?

In most cases after planning permission has been granted, because the provision allows an order where it is necessary to enable development to be carried out in accordance with a permission that has been granted. That sequencing means the order process runs after determination rather than in parallel, which is the usual programme problem.

How long does a diversion order take?

A few months if nobody objects, since the authority can confirm its own unopposed order after advertising it and serving notice. If objections are made and not withdrawn the order goes to the Secretary of State and is determined by written representations, a hearing or an inquiry, which can add a year on a contested rural route.

What makes a replacement route acceptable?

Similar length, sensible gradients, a pleasant alignment and a surface and width suited to the recorded category. User groups object to poor replacements rather than to the principle, so a route squeezed between two close boarded fences attracts objections while one through open space with active frontage usually does not.

Do I need anything to close a path during construction?

Yes. A temporary closure is a separate application to the highway authority with its own notice period, and it is not covered by the planning permission or by a diversion order. Address it in the construction management plan, because site compounds frequently land on footpaths before anyone has applied.

Sources and further reading

public right of waysection 257definitive mapfootpath diversionhighways actmajor development

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Which Reports Do I Need

View all →
Which Reports Do I Need7 min read

Reports for a sand and gravel extension of six hectares

A six hectare gravel extension is decided by the mineral planning authority, needs an EIA screening opinion, and turns on hydrogeology and restoration rather than on blasting.

Read article →
Which Reports Do I Need6 min read

Reports for a traveller site with four pitches

A four pitch traveller site is a minor application with a major policy test. Need evidence, pitch separation and flood vulnerability decide most of these cases.

Read article →
Which Reports Do I Need7 min read

Reports for a micro hydro scheme on a weir

Micro hydro at a weir needs planning permission plus abstraction, impoundment and flood risk permits. The fish pass is often the costliest item, and it has to be settled before the drawings.

Read article →
Which Reports Do I Need7 min read

Reports for a student accommodation scheme of 200 beds

A 200 bed student scheme is a major application with two documents that have no equivalent on a standard residential pack: the institutional need case and the student management plan.

Read article →
Which Reports Do I Need7 min read

Reports needed for a church hall replacement

Rebuilding a church hall means answering three questions at once: the community facility replacement test, the setting of the adjoining listed church, and what lies under a churchyard.

Read article →
Which Reports Do I Need7 min read

Consents for a scaffold gantry over the public highway

Hoardings and scaffolds sit inside Part 4 permitted development, but the licences that control them come from the highway authority under the Highways Act 1980, and hoarding graphics are a separate advertisement consent.

Read article →