Withdrawing and resubmitting: the free resubmission rule

6 min readBy PlanScope Editorial Team

England's fee regulations exempt one repeat planning application from the fee. The conditions are narrow, the twelve-month clock starts on different dates for refused and withdrawn applications, and the exemption can only be used once.

A free resubmission planning application is possible because the England fee regulations exempt one repeat application from the fee, so long as the second application covers development of the same character or description, on the same site, by the same applicant, and arrives within twelve months. The trade calls it the one free go. What catches people out is the start date for those twelve months, which is not the same for a refused application as for a withdrawn one.

Get it wrong and the council returns the application as invalid for non-payment, and the revised scheme loses another month.

Where the exemption comes from

The Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, as amended, set every planning application fee in England, and they also set the exemptions. The repeat-application exemption is one of them. It is not a discretion your case officer exercises. The validation team applies the test to the facts on the form, and where the test is met the fee is nil.

Government guidance sits in the Planning Practice Guidance chapter on fees. Fees were uplifted in December 2023 and are indexed annually from April 2025, so check the current schedule before you quote a client a figure.

The exemption covers the planning application fee and nothing else. Pre-application advice charges, applications to discharge conditions, section 73 applications and section 96A non-material amendment requests all carry their own fees, and none of them is caught by it. The wider set of fee exemptions and reductions sits elsewhere in the same regulations and is worth checking separately.

The conditions that have to be met

Five things have to line up.

  1. The earlier application was made by the same applicant. A change of applicant name between the two submissions, including a move from a personal name to a limited company, breaks the chain.
  2. The site is the same. A red line redrawn to add a strip of garden is a different site in the council's eyes, and boundary changes are the most common reason a free go is refused at validation.
  3. The development is of the same character or description as the earlier proposal.
  4. The earlier application was granted, refused, or withdrawn before it was determined.
  5. The new application arrives within twelve months of the relevant date, and the earlier application was not itself a fee-exempt repeat.

That last limb quietly removes the second bite. You cannot resubmit free, get refused again, and resubmit free a second time against the same original application.

What the same character or description means in practice

The regulations do not define the phrase, and councils do not publish a checklist for it. A validation officer is asking whether this is recognisably the same project, revised in response to the reasons for refusal, rather than a new proposal that happens to sit on the same land.

A rear extension refused on depth and resubmitted 1.5 m shorter is the same description. The same extension resubmitted with a loft conversion and two dormers added usually is not, because the scheme now contains work the council never assessed. Moving the proposal into a different use class almost always ends the claim, as does a shift from a householder application to a full application for two dwellings.

Where you are close to the line, say so in the covering material. A short paragraph in the Planning Statement that gives the earlier reference number, the reasons for refusal and the specific change made against each reason gives the validation officer something to point at. It also saves the case officer a week working out what moved.

How the twelve months is counted

For a refused application the twelve months runs from the date on the decision notice, not from the committee resolution and not from the day the notice reached your inbox. For a granted application it runs from the date of that grant. Where the earlier application went to appeal, the clock runs from the date the appeal was decided or withdrawn, which can push the window well past a year from the original refusal.

Earlier application Date the twelve months runs from
Refused Date of the decision notice
Granted Date of the decision notice
Appealed, then decided or withdrawn Date the appeal was determined or withdrawn
Withdrawn before determination Date the earlier application was made

The last row is the one to commit to memory.

Withdrawn applications and the trap in the dates

When an application is withdrawn, the twelve months does not restart from the withdrawal. It runs from the date the earlier application was made. A scheme submitted on 3 March, nursed through consultation, amended twice and finally withdrawn on 12 November has already spent more than eight of its twelve months. Resubmit the following April and the free go has gone.

That changes how you advise a client heading for a refusal. Withdrawing keeps a refusal off the planning record, which matters because a refusal is a material consideration a future officer will read and a question on most conveyancing enquiries. But a withdrawal burns the fee exemption window faster than a refusal does, and the later in the determination period you withdraw, the less of the window survives.

One honest uncertainty. Councils are not consistent about which date they take for a withdrawn application, and a few will accept the withdrawal date. Do not plan around that. Work from the submission date and leave yourself a margin.

One exemption, and how to time a withdrawal

The exemption attaches to the earlier application, and it can be used once. Sequence the revisions accordingly. If you expect to need two goes, spend the exemption on the attempt most likely to succeed and budget the fee for the other. On a householder scheme the fee is small against the drawing time. On a major application it is not, and the arithmetic changes.

Where a refusal is coming and the reasons look fixable, there is a real case for letting it be refused. You get reasons in writing, which beats an officer's verbal summary, and the consultee replies sit on file, so reading the officer's case file tells you what actually drove the decision. The same timing calculation applies where an authority has simply not decided, which is the live question in appealing non-determination or waiting.

An illustrative example. A two-storey side extension on a 1930s semi is submitted on 10 January and refused on 7 March for an overbearing effect on the neighbour's rear window. A resubmission on 2 June, with the first floor set back 1.2 m and the flank window obscure-glazed, is the same character and description, on the same site, by the same applicant, within twelve months of 7 March. No fee. Had the scheme instead been withdrawn on 1 March, the window would have closed on 10 January the following year.

Keep the paperwork. A dated copy of the earlier decision notice or withdrawal confirmation, the earlier reference number on the new form, and one line claiming the exemption in the covering letter will usually clear validation without a phone call. Councils do check, and a missing reference number is enough to stall the application for a fortnight.

Before you resubmit, re-read the reasons for refusal against the documents you are about to send again. Several of the 66 report types on PlanScope exist because a council asked for evidence the first submission did not contain. Enter your postcode on PlanScope to see which reports your site is likely to need.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

Is a resubmitted planning application always free?

No. The exemption only applies where the second application is for development of the same character or description, on the same site, by the same applicant, and is submitted within twelve months of the relevant date. The earlier application must also not have been a fee-exempt repeat itself. Outside those conditions the full fee is payable at validation.

Does the free go apply after a withdrawal or only after a refusal?

It applies to both, and also after a grant. The difference is the date the twelve months runs from. For a refusal or a grant it runs from the decision notice. For a withdrawn application it runs from the date that earlier application was made, so a late withdrawal leaves much less of the window available.

Can I change the red line boundary and still claim the exemption?

Usually not. The exemption requires the same site, and validation teams read that strictly. Adding a strip of garden, pulling in an access or extending the application site to cover a parking area will normally be treated as a different site, and the fee becomes payable. Keep the boundary identical if you want the exemption.

How many times can I use the exemption on one scheme?

Once in relation to any one earlier application. A resubmission made under the exemption cannot itself generate a further free resubmission. If you expect two rounds of revision, decide which attempt is most likely to succeed and keep the exemption for that one, budgeting the full fee for the other.

Do I still need to pay anything if the exemption applies?

The exemption covers the planning application fee only. Pre-application advice charges, applications to discharge conditions, section 73 variations and section 96A non-material amendments each carry their own fee. Fees are indexed annually from April, so confirm the current figure on the published schedule rather than reusing one from an old job file.

How do I tell the council I am claiming the exemption?

Quote the earlier application reference number on the form, attach the decision notice or withdrawal confirmation, and add one line to the covering letter setting out why the test is met. That is usually enough to clear validation. Without the reference number the submission is likely to be queried, which costs a week or two.

Sources and further reading

planning feesresubmissionplanning processvalidationwithdrawn application

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Planning Process

View all →
Planning Process8 min read

Habitats regulations assessment inside the application process

The habitats regulations assessment is the council's finding, not your appendix. How screening, appropriate assessment and mitigation actually run through an English planning application.

Read article →
Planning Process7 min read

Challenging a local plan under section 113

An adopted development plan document can only be questioned under section 113 of the 2004 Act, within six weeks of adoption. The grounds are procedural, and the usual remedy is partial quashing.

Read article →
Planning Process7 min read

Prior approval deadlines across the permitted development classes

Prior approval periods are a property of the class, not a single rule: 28 days for agricultural and demolition, 42 for larger home extensions, 56 for change of use and upward extensions.

Read article →
Planning Process7 min read

Transferring a permission and a change of applicant

Section 75 makes a permission a benefit of the land, so a buyer acquires it on completion with no form or fee. The levy paperwork and undischarged conditions are where the risk sits.

Read article →
Planning Process8 min read

Decision notices: conditions, informatives and reasons

The permission is the description, the conditions and the drawings those conditions list. The officer report is not part of it, and a superseded drawing revision in the list is a real problem.

Read article →