A business storing hazardous substances

6 min readBy PlanScope Editorial Team

Consent under the Planning (Hazardous Substances) Act 1990 is separate from planning permission and is triggered by presence rather than use. Aggregation, consultation distances and conditions all catch operators out.

Hazardous substances consent is a separate consent from planning permission, and you need it once a controlled substance is present at or above its controlled quantity. The regime sits in the Planning (Hazardous Substances) Act 1990 and the Planning (Hazardous Substances) Regulations 2015, with the quantities listed in the Regulations. A business can hold planning permission for its use, be meeting every term of its lease, and still be operating unlawfully because nobody checked the tonnage against Schedule 1.

The trigger is presence, not activity. Storing the substance counts, whether or not it is used on site.

Consent is required where a hazardous substance is, or is to be, present on, over or under land at or above its controlled quantity. The application goes to the hazardous substances authority, which for most sites is the district or unitary council, with county councils taking minerals and waste sites.

Three features of the regime surprise people.

It runs with the land, not with the operator. Consent attaches to the land and continues after a sale, which is why a purchaser's due diligence should include a hazardous substances search.

Aggregation applies. Substances in the same category are added together across the site, and a site holding several substances below their individual thresholds can still reach a controlled quantity by the aggregation rule in the Regulations.

And a change in the person in control of part of the land can affect the consent. The Act deals with this expressly and the consequence can be revocation, so a partial sale or a sublet of part of a site needs checking against the Act before it completes.

Controlled quantities and the thresholds

The controlled quantities sit in Schedule 1 to the 2015 Regulations, in two parts: named substances, and categories of substance defined by hazard classification. The thresholds are aligned with the lower tier of the major accident hazard regime, which is why the two often arrive together.

The practical method:

  1. Get the safety data sheet for every substance held, and read the hazard classification rather than the trade name.
  2. Establish the maximum quantity that will be present, including deliveries in transit on site and waste awaiting collection.
  3. Look up the named substance entries first, then the category entries for anything not named.
  4. Apply the aggregation rule for substances in the same category.
  5. Compare against the controlled quantity and record the calculation, because you will be asked for it.

Common triggers for small and medium businesses are bulk liquefied petroleum gas, chlorine at water treatment and leisure sites, ammonia in refrigeration plant, oxidising agents, and flammable solvent storage at coating and printing operations. The Regulations are the authority on the figures and they have been amended, so check the current text rather than a summary.

The relationship with planning permission

Two consents, two applications, two decisions. Neither substitutes for the other.

Matter Which consent
The tanks, bunds, buildings and hardstanding Planning permission for the operational development
A change in the use of the site Planning permission, where the change is material
Presence of the substance at or above the controlled quantity Hazardous substances consent
Operating the installation safely Separate health and safety regime, not planning

The sequencing question is worth thinking about. Applying for both together lets the authority see the whole proposal, which usually helps, and it avoids a planning permission granted for a facility that cannot lawfully hold its intended inventory. Where the planning application is finely balanced, some applicants prefer to settle planning first. There is no single right answer, and the authority's own preference is worth asking about at pre-application stage.

Tanker movements are a planning matter in their own right, and on a constrained site the access geometry for a rigid or articulated tanker is often the point that causes the highway authority to object. A Transport Statement with swept-path drawings for the delivery vehicle answers it, and should cover the delivery frequency and the standing position during discharge.

Consultation with the safety regulator

The Health and Safety Executive is consulted on hazardous substances consent applications and advises the authority on the risks to people in the surrounding area. Its advice does not bind the authority. But a council granting consent against advice from the safety regulator is in a difficult position, and the officer report will say so.

What the Executive looks at is the quantity, the substance, the containment, the separation distances to occupied buildings and to vulnerable uses such as schools and care homes, and the population around the site. The assessment is about the consequences of a major accident rather than about day-to-day operation.

Prepare for it. A site layout showing the storage location, the bund capacity, the separation distances to the boundary and to the nearest occupied buildings, and the population context, gives the Executive what it needs to advise without a request for further information.

Consultation distances and nearby development

Once consent exists, the Executive maintains consultation distances around the installation. Any planning application for development inside those distances is referred to it, and it advises the authority either to raise no objection or to advise against the proposal on safety grounds.

That has two consequences for the operator.

Your consent constrains your neighbours. A residential application next door can be refused on the basis of your installation, which is sometimes welcome and sometimes the reason a neighbouring landowner starts asking questions about your tonnage.

And it constrains you. Development inside your own consultation distance, including an office extension or a new welfare building on your own site, goes through the same referral.

Where spill risk and ground conditions are in play, the containment design and any historic contamination from previous storage belong in the Land Contamination assessment, which needs a suitably qualified and experienced professional under the approach in planning practice guidance.

Conditions and site changes

Hazardous substances consent can carry conditions, typically on the quantity, the location of the storage, the containment arrangements and the manner in which the substance is kept. Read them as carefully as planning conditions, because exceeding a conditioned quantity is a breach even where the total stays below the controlled quantity in the Regulations.

Changes needing a fresh look:

  • An increase in the maximum inventory, even a temporary one for a seasonal peak.
  • Relocating the storage within the site.
  • Adding a substance in the same category, because of aggregation.
  • Substituting a product with a different hazard classification, which happens quietly when a supplier reformulates.
  • Any partial disposal or sublet of the land.

Set a review date each year and check the inventory against the consent. The usual cause of a breach is accumulation, not a decision.

What to submit

An application for consent needs the substance and its hazard classification, the maximum quantity, a plan of the land showing where the substance will be kept and the containment, a description of the manner of keeping or use, and a plan showing the surroundings. Notice has to be given to owners and, where relevant, to others with an interest in the land, with the usual certificates.

Build the pack around the Executive's needs rather than the planning officer's, because the Executive's advice is what the decision will rest on. To see which supporting documents the accompanying planning application is likely to need, enter your postcode on PlanScope or browse the 66 report types.

This is general guidance, not legal advice. Check the position with your local planning authority or a qualified professional before relying on it. PlanScope provides AI-assisted draft reports for planning applications. Reports should be reviewed before submission. We do not guarantee planning approval.

Frequently asked questions

When does a business need hazardous substances consent?

When a hazardous substance is, or is to be, present on, over or under land at or above its controlled quantity, as set out in Schedule 1 to the Planning (Hazardous Substances) Regulations 2015. The trigger is presence rather than use, so storage counts whether or not the substance is processed on site.

Does the consent transfer when the site is sold?

The consent attaches to the land and continues after a sale, which is why a purchaser's due diligence should include a hazardous substances search. A change in the person in control of part of the land is dealt with expressly in the Act and can lead to revocation, so check before a partial sale or sublet completes.

Can several small quantities trigger the threshold?

Yes. Substances in the same category are aggregated across the site under the rule in the Regulations, so a site holding several substances each below its individual threshold can still reach a controlled quantity. Establish the maximum present, including deliveries in transit and waste awaiting collection.

Is the safety regulator's advice binding on the council?

Not binding, though an authority granting consent against advice from the Health and Safety Executive is in a difficult position and the officer report will say so. The Executive assesses the substance, quantity, containment, separation distances and surrounding population, looking at major accident consequences rather than day-to-day operation.

How does a consent affect neighbouring development?

The Executive maintains consultation distances around the installation, and planning applications for development inside them are referred to it for advice. That can lead to a refusal of a neighbouring residential scheme, and it also catches development on your own site, including an office extension or a new welfare building.

What causes most breaches of a hazardous substances consent?

Accumulation rather than a decision. Inventories creep up, storage gets relocated within the site, a supplier reformulates a product into a different hazard classification, or a substance in the same category is added. Set an annual review date and check the actual inventory against the conditioned quantity and location.

Sources and further reading

hazardous substancesconsentcommercial occupiershealth and safetylpgsite safety

This article is general guidance about the planning system in England and, where stated, the rest of the UK. It is not legal or professional advice. Check your local planning authority’s validation requirements and take professional advice for your specific site.

More in Commercial Occupiers

View all →
Commercial Occupiers7 min read

A projecting or hanging sign on a commercial frontage

A hanging sign can need advertisement consent, a highway licence and listed building consent at once. The deemed consent conditions on height, projection and illumination decide which.

Read article →
Commercial Occupiers7 min read

Dessert shop planning permission and the waste stream

A cold dessert or bubble tea shop is within Class E, so moving into a former shop needs no permission. Hot food, hours, queueing and waste are the real issues.

Read article →
Commercial Occupiers7 min read

Church hall letting space to a commercial nursery

Whether a commercial nursery in a church hall needs permission turns on the planning unit. Exclusive occupation, physical alteration and intensity are what decide it.

Read article →
Commercial Occupiers7 min read

A microbrewery's effluent and the undertaker's consent

Brewing effluent is far stronger than domestic sewage. The sewerage undertaker, not the council, decides whether it can go down the drain, and on what terms.

Read article →
Commercial Occupiers6 min read

A pet crematorium and the environmental permit

Animal cremation sits outside the use classes, needs an environmental permit as well as planning permission, and is normally decided on stack height, odour and the visitor element.

Read article →
Commercial Occupiers6 min read

A seasonal food kiosk on private land: the planning rules

Part 4 of the GPDO allows temporary use of land for 28 days a year, including a moveable kiosk. The curtilage exclusion, the day count across the planning unit and any hardstanding or services decide whether you need to apply.

Read article →